Summary

PRBD202305751
Building
Finaled
US FEDERAL CREDIT UNION
Alteration/Repair/Replace
Not Required
Interior renovation of office space
05/31/2023
06/23/2023
02/13/2024
08/17/2023

Locations

Permits

Permit Number: PRBD202305751

Building
Finaled
06/23/2023
02/13/2024

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 7/13/2023 (8:00 - 10:00) 7/13/2023 (AM) 07/13/2023
Corrections:


Miscellaneous/Other
Carried Forward
07/13/2023
Correction... Office front wall by vestibile entry to have framing corrected. The wall section above ceiling is not properly supported by the wall built for the office front wall. The wall built is only supported by studs slid into the gypsum and attached to gypsum. Contractor to correct by either cleating studs in the separate wall sections together, or installing a box beam and correting framing. Call for reinspection of this wall.

Miscellaneous/Other
Comment Only
07/13/2023
Remaining walls framing are approved, see outstanding comments for correction.

Framing Inspection Passed 7/14/2023 (8:00 - 10:00) 7/14/2023 (AM) 07/14/2023
Corrections:


Miscellaneous/Other
Resolved
07/14/2023
Correction... Office front wall by vestibile entry to have framing corrected. The wall section above ceiling is not properly supported by the wall built for the office front wall. The wall built is only supported by studs slid into the gypsum and attached to gypsum. Contractor to correct by either cleating studs in the separate wall sections together, or installing a box beam and correting framing. Call for reinspection of this wall.

Miscellaneous/Other
Comment Only
07/14/2023
All framing approved.

Building Final Inspection Partial Pass 8/11/2023 (8:00 - 10:00) 8/11/2023 (AM) 08/11/2023
Corrections:


Miscellaneous/Other
Carried Forward
08/11/2023
Approved for temp occupancy only at this time. Call in for sprinkler inspection final and electrical permits for this buildout to be final as well.

Fire Inspection Final Passed 8/11/2023 (8:00 - 10:00) 8/11/2023 (AM) 08/14/2023
Building Final Inspection Passed 08/17/2023
Corrections:


Miscellaneous/Other
Resolved
08/17/2023
Approved for temp occupancy only at this time. Call in for sprinkler inspection final and electrical permits for this buildout to be final as well.

Miscellaneous/Other
Comment Only
08/17/2023
Final approved