PRBD202305939
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Rough-in Inspection | Pending | |||
Framing Inspection | Partial Pass | 9/1/2023 (7:00 - 8:00) | 9/1/2023 (AM) | 09/01/2023 |
Corrections:
Miscellaneous/Other
Comment Only
09/01/2023
All wall framing approved, ok to cover all walls except the bathrooms can only be one sided. Reinspection needed for the bathrooms.
Fitting room ceiling and storefront framing approved and ok to cover.
|
||||
Framing Inspection | Partial Pass | 9/7/2023 (12:30 - 2:30) | 9/7/2023 (PM) | 09/07/2023 |
Corrections:
Miscellaneous/Other
Comment Only
09/07/2023
Hard lids in fitting rooms and hallways ... approved to cover.
|
||||
Progress Inspection | Not Ready | 9/11/2023 (8:00 - 10:00) | 9/11/2023 (AM) | 09/11/2023 |
Corrections:
Miscellaneous/Other
Comment Only
09/11/2023
Meeting with mall representative, fire inspector, and contractor about the fire protection in the storage room. Due to classification of storage and no ceiling being installed in the storage room, either the sprinkler coverage needs to be updated and installed to comply for this storage, or a ceiling would need to be put in this storage room. Since this was planned to not have a ceiling, electrical and ductwork would need to be adjusted for the installation of a ceiling. This in turn would affect the racking height and storage height allowed.
FM global and the NFPA requirements are the driving force in this requirement.
|
||||
Fire Rough-in Inspection | Not Ready | 9/11/2023 (8:00 - 10:00) | 9/11/2023 (AM) | 09/11/2023 |
Progress Inspection | Passed | 09/13/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
09/13/2023
Above ceiling at store sales... approved
|
||||
Building Final Inspection | Partial Pass | 11/2/2023 (8:00 - 10:00) | 11/2/2023 (AM) | 11/02/2023 |
Corrections:
Miscellaneous/Other
Comment Only
11/02/2023
Approved to bring in stock items and set up space only.
Call for final when all trades inspections are done and this space is ready for turnover.
|
||||
Fire Inspection Final | Passed | 11/15/2023 (12:30 - 2:30) | 11/15/2023 (PM) | 11/16/2023 |
Building Final Inspection | Passed | 11/16/2023 (12:30 - 2:30) | 11/16/2023 (PM) | 11/16/2023 |
Corrections:
Miscellaneous/Other
Comment Only
11/16/2023
Final approved... ok to open
|