PRBD202306568
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 9/7/2023 (8:00 - 10:00) | 9/7/2023 (AM) | 09/07/2023 |
Corrections:
Miscellaneous/Other
Comment Only
09/07/2023
Framing and fire stops... approved
|
||||
Progress Inspection | Passed | 9/15/2023 (8:00 - 10:00) | 9/15/2023 (AM) | 09/15/2023 |
Corrections:
Miscellaneous/Other
Comment Only
09/15/2023
Rated floor ... holes are being plugged with concrete to the floor depth... approved
|
||||
Above Ceiling Inspection | Passed w/ Conditions | 9/22/2023 (8:00 - 10:00) | 9/22/2023 (AM) | 09/22/2023 |
Corrections:
Miscellaneous/Other
Comment Only
09/22/2023
Above ceiling approved, pending patching holes in the adjoining wall to bathrooms. Contractor to send photos or schedule reinspection.
|
||||
Building Final Inspection | Partial Pass | 11/16/2023 (8:00 - 10:00) | 11/16/2023 (AM) | 11/16/2023 |
Corrections:
Miscellaneous/Other
Comment Only
11/16/2023
Approved for Temp.
Final for plumbing permit, and EH approval once sneeze guards are installed needed. Call in for inspection when ready.
|
||||
Fire Inspection Final | Passed | 11/16/2023 (8:00 - 10:00) | 11/16/2023 (AM) | 11/17/2023 |
Building Final Inspection | Passed | 11/20/2023 (8:00 - 10:00) | 11/20/2023 (AM) | 11/20/2023 |
Corrections:
Miscellaneous/Other
Comment Only
11/20/2023
Final approved. Ok to remove barakade.
|