PRBD202306738
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Partial Pass | 8/8/2023 (8:00 - 10:00) | 8/30/2023 (AM) | 08/30/2023 |
Corrections:
Miscellaneous/Other
Comment Only
08/30/2023
This was a informational inspection about the storefront framing and requirements.
|
||||
Framing Inspection | Partial Pass | 9/20/2023 (8:00 - 10:00) | 9/20/2023 (AM) | 09/20/2023 |
Corrections:
Miscellaneous/Other
Comment Only
09/20/2023
Back of house wall framing approved to one side only. Leave open wall framing where any piping is run for inspection of the penetrations firestops.
|
||||
Progress Inspection | Partial Pass | 9/27/2023 (8:00 - 10:00) | 9/27/2023 (AM) | 09/27/2023 |
Corrections:
Miscellaneous/Other
Comment Only
09/27/2023
Framing.... back oh house offices and stock room, and hallway... framing approved.... ok to cover both sides where firestops have been completed and inspected, and electrical has been approved.
|
||||
Progress Inspection | Passed | 10/4/2023 (8:00 - 10:00) | 10/4/2023 (AM) | 10/04/2023 |
Corrections:
Miscellaneous/Other
Comment Only
10/04/2023
Framing repaired at existing wall... approved
Firestops approved to through floor penetrations at wall, ok to cover wall.
|
||||
Progress Inspection | Passed | 10/6/2023 (8:00 - 10:00) | 10/6/2023 (AM) | 10/06/2023 |
Corrections:
Miscellaneous/Other
Comment Only
10/06/2023
Fireproofing patching at beams and columns... approved
Hard lid ceiling framing... approved
|
||||
Progress Inspection | Partial Pass | 10/11/2023 (8:00 - 10:00) | 10/11/2023 (AM) | 10/11/2023 |
Corrections:
Miscellaneous/Other
Comment Only
10/11/2023
Storefront framing approved, pending electrical and fire sprinkler inspection before covering.hard lid ceilings in back areas, and drop ceiling framing in storage area... approved
|
||||
Progress Inspection | Passed | 10/18/2023 (8:00 - 10:00) | 10/18/2023 (AM) | 10/18/2023 |
Corrections:
Miscellaneous/Other
Comment Only
10/18/2023
Work is ongoing, questions about inspections and what they can cover.
|
||||
Progress Inspection | Passed | 10/25/2023 (8:00 - 10:00) | 10/25/2023 (AM) | 10/25/2023 |
Corrections:
Miscellaneous/Other
Comment Only
10/25/2023
Framing around columns, fire stops, and patched fireproofing... approved.
|
||||
Progress Inspection | Partial Pass | 11/1/2023 (AM) | 11/01/2023 | |
Corrections:
Miscellaneous/Other
Comment Only
11/01/2023
Went over the mall requirements at the store front with the wood panels contractor installed and a compromised fix to comply with the requirements.
|
||||
Progress Inspection | Passed | 11/14/2023 (8:00 - 10:00) | 11/14/2023 (AM) | 11/14/2023 |
Corrections:
Miscellaneous/Other
Comment Only
11/14/2023
Reviewed with job superintendent the store front and the cooridor wall. Storefront corrections are approved and meet the criteria for the mall. The wall has 2 layers of gypsum and has been approved by the security/ design team, no gypsum will be removed to install plywood.
|
||||
Progress Inspection | Passed | 12/1/2023 (12:30 - 2:30) | 12/1/2023 (PM) | 12/01/2023 |
Corrections:
Miscellaneous/Other
Comment Only
12/01/2023
Fire stops at floor penetrations... approved
|
||||
Fire Inspection Final | Partial Pass | 1/16/2024 (8:00 - 10:00) | 1/16/2024 (AM) | 01/16/2024 |
Building Final Inspection | Partial Pass | 1/16/2024 (8:00 - 10:00) | 1/16/2024 (AM) | 01/16/2024 |
Corrections:
Miscellaneous/Other
Carried Forward
01/16/2024
Items of correction and or completion....
1) all tades inspections to be completed for final of his builout. 2) interior door in the path of exit to be contrasting in some way.
2) Install exir signage where missing
3) fitting room signage to be installed
4) no high shelf storge signage in storage rooms needed
5) complete remaining work in sales area.
|
||||
Miscellaneous/Other
Comment Only
01/16/2024
See outstanding comments for the final inspection requirements.
Today's inspection has pointed out items outstanding that need to be finished or corrected.
Will allow the brand to stock as needed in the back areas.
Final for this permit is not ready at this time.
|
||||
Building Final Inspection | Passed | 2/6/2024 (8:00 - 10:00) | 2/6/2024 (AM) | 02/06/2024 |
Corrections:
Miscellaneous/Other
Resolved
02/06/2024
Items of correction and or completion....
1) all tades inspections to be completed for final of his builout. 2) interior door in the path of exit to be contrasting in some way.
2) Install exir signage where missing
3) fitting room signage to be installed
4) no high shelf storge signage in storage rooms needed
5) complete remaining work in sales area.
|
||||
Miscellaneous/Other
Comment Only
02/06/2024
Final for this space approved, ok to open to public.
|
||||
Fire Inspection Final | Passed | 2/6/2024 (8:00 - 10:00) | 2/6/2024 (AM) | 02/08/2024 |