PRBD202306926
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Investigation Inspection | Partial Pass | 7/27/2023 (2:30 - 3:30) | 7/27/2023 (PM) | 07/27/2023 |
Corrections:
Miscellaneous/Other
Comment Only
07/27/2023
Viewed the paint and the additive used for fire retardent protection, panels are all coated with first coat of paint. The additive to paint will be used for all coats applied and to all fabrics applied to or hanging , per the contractor on site.
|
||||
Framing Inspection | Partial Pass | 08/04/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
08/04/2023
Smoke bulkhead framing approved and ok to cover.
Call for other framing inspections.
|
||||
Framing Inspection | Passed | 8/8/2023 (12:30 - 2:30) | 8/8/2023 (PM) | 08/08/2023 |
Corrections:
Miscellaneous/Other
Comment Only
08/08/2023
Storefront framing approved.
|
||||
Progress Inspection | Passed | 8/28/2023 (12:30 - 2:30) | 8/28/2023 (PM) | 08/28/2023 |
Corrections:
Miscellaneous/Other
Comment Only
08/28/2023
Walk through of this space.... exiting approved.
The partitions and all theme products are fire protected with the products submitted. Work is still ongoing, the next inspection EM lighting will be tested and all signage to be verified.
|
||||
Building Final Inspection | Passed | 9/12/2023 (7:00 - 8:00) | 9/12/2023 (AM) | 09/12/2023 |
Corrections:
Miscellaneous/Other
Comment Only
09/12/2023
Horn strobes and Emergency lighting checked.... approved
Exiting and signage ... approved
Accessible compliant signage being installed at the bathrooms, contractor will send inspector pictures to verify.
Electrical inspection final is scheduled for today , pending outcome of that inspection... final for this space approved.
|
||||
Fire Inspection Final | Passed | 9/12/2023 (7:00 - 8:00) | 9/12/2023 (AM) | 09/15/2023 |