Permit Application Status

PRBD202307899


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202307899
Building
Permit(s) Issued
POLAR SEMICONDUCTOR INC
Addition
Not Required
PHASE 1 - Polar Semiconductor is proposing an interior remodel of existing buildings P1, P2, and P3 and a 3,750 square foot electrical room addition between buildings P2 and P3. The project aims to improve Polar Semiconductor’s manufacturing capabilities and increase the production of semiconductor products. This permit application is for Phase 1 scope of work only. The project will be executed throughout multiple phases with construction occurring over the course of multiple years. Roughly ninety percent of the scope of work is interior remodeling, mechanical/electrical upgrades, and tool installations for Polar Semiconductor’s manufacturing processes. The electrical room addition includes on-grade exterior transformers within an electrical yard. There will be modifications to the site to reconfigure underground utilities and provide additional hardscape and softscape, including a safety fence at the perimeter.
07/14/2023
10/04/2024
10/06/2025

Locations

Permits

Permit Number: PRBD202307899

Building
Issued
10/04/2024
10/06/2025

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Insulation Inspection Pending
Lath Inspection Pending
Fire Inspection Final Pending
Building Final Inspection Pending
Landscaping Inspection Pending
Progress Inspection Passed 12/18/2024 (7:00 - 8:00) 12/18/2024 (AM) 12/18/2024
Corrections:


Miscellaneous/Other
Comment Only
12/18/2024
Dowels and poly at slab on grade approved. Went through on overview of job and inspection requirements with contractor.

Framing Inspection Passed 2/14/2025 2/14/2025 (AM) 02/14/2025
Corrections:


Miscellaneous/Other
Comment Only
02/14/2025
Framing of phase 1 approved, pending the EJ or wall design being used at the hallway waffle deck enclosure of wall.

Footing Inspection Passed 3/25/2025 (8:00 - 10:00) 3/25/2025 (AM) 03/25/2025
Corrections:


Miscellaneous/Other
Comment Only
03/25/2025
New structure being built between the buildings.... Two outer footings running E/W to bulkheads and one footing along existing building running N/S This first pour of footings are approved for concrete placement.

Footing Inspection Passed 3/31/2025 (8:00 - 10:00) 3/31/2025 (AM) 03/31/2025
Corrections:


Miscellaneous/Other
Comment Only
03/31/2025
Interior footing and remaining perimeter footing for structure... approved

Progress Inspection Passed 4/9/2025 (2:30 - 3:30) 4/9/2025 (PM) 04/09/2025
Corrections:


Miscellaneous/Other
Comment Only
04/09/2025
Rebar for structural slab... approved