PRBD202308002
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 9/13/2023 (10:00 - 12:00) | 9/13/2023 (AM) | 09/13/2023 |
Framing : passed. | ||||
Corrections:
Miscellaneous/Other
Comment Only
09/13/2023
Existing tenant suite 700. Framing passed. Call for above ceiling for electrical, low voltage, and fire sprinkler, and mechanical if required.
|
||||
Building Final Inspection | Partial Pass | 11/1/2023 (10:00 - 12:00) | 11/1/2023 (AM) | 11/01/2023 |
Exit signage, max Occupancy for conference rooms, emergency power test,. | ||||
Fire Inspection Final | Partial Pass | 11/1/2023 (10:00 - 12:00) | 11/1/2023 (AM) | 11/02/2023 |
Ensure lobby ceiling squares are properly installed with sprinkler protection. Ensure exit sign near lobby is readable from both sides. Add occupancy capacity signs as needed for training/cafe room. | ||||
Building Final Inspection | Passed | 11/7/2023 (10:00 - 12:00) | 11/7/2023 (AM) | 11/07/2023 |
Final with fire Marshall Pete Miller. | ||||
Fire Inspection Final | Passed | 11/7/2023 (10:00 - 12:00) | 11/7/2023 (AM) | 11/07/2023 |