PRBD202309054
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Framing Inspection | Passed | 10/6/2023 (10:00 - 12:00) | 10/6/2023 (AM) | 10/06/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/06/2023
Wall Framing approved
|
||||
| Above Ceiling Inspection | Partial Pass | 11/7/2023 (8:00 - 10:00) | 11/7/2023 (AM) | 11/07/2023 |
| Framing inspection: A. Electrical room existing door may need to swing out with panic hardware due to electrical amperage in national electrical code. B. Basement below requires all-floor penetrations to be fire caulked. B. All flutes at roof metal decking are filled for tenant fire and smoke separation. C. Attain all required trade inspections for mechanical, electrical, plumbing, HVAC. D. Exterior sign permit requires seperate electrical permit. | ||||
|
Corrections:
Miscellaneous/Other
Outstanding
11/07/2023
Framing passed. All trade permits for mechanical, plumbing, electrical, fire sprinkler system, and electrical low voltage, and environmental health are
(Required.)
|
||||
| Above Ceiling Inspection | Failed | 12/27/2023 (8:00 - 10:00) | 12/27/2023 (AM) | 12/27/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/27/2023
The previous above ceiling inspection details that framing was looked at.
Contractor to open ceiling tiles for above ceiling inspection and have viewing access along the dimising wall as well.
Fire sprinkler inspection to also be performed with ceiling tiles open for viewing. Call in for inspections for above cieling and fire suppression.
|
||||
| Building Final Inspection | Not Ready | 12/27/2023 (8:00 - 10:00) | 12/27/2023 (AM) | 12/27/2023 |
|
Corrections:
Miscellaneous/Other
Carried Forward
12/27/2023
No building final can be given at this time. Open permits with this buildout to be called in for inspection and final inspection. Permits include... fire sprinklerpermit, mechanical permit for refrigeration, Environmental Healt permit, and building permit.
Call in and set up inspections, building final should be last in inspections as all other permit inspections should be completed.
|
||||
| Fire Inspection Final | Not Ready | 12/27/2023 (8:00 - 10:00) | 12/27/2023 (AM) | 12/27/2023 |
| No sprinkler inspections have been completed including rough-in inspection. | ||||
| Fire Inspection Final | Partial Pass | 12/28/2023 (12:30 - 2:30) | 12/28/2023 (PM) | 12/28/2023 |
| Need to sheet rock and enclose the space between/above the retail area and walk-in cooler. | ||||
| Building Final Inspection | Partial Pass | 1/3/2024 (8:00 - 10:00) | 1/3/2024 (AM) | 01/03/2024 |
|
Corrections:
Miscellaneous/Other
Resolved
01/03/2024
No building final can be given at this time. Open permits with this buildout to be called in for inspection and final inspection. Permits include... fire sprinklerpermit, mechanical permit for refrigeration, Environmental Healt permit, and building permit.
Call in and set up inspections, building final should be last in inspections as all other permit inspections should be completed.
|
||||
|
Miscellaneous/Other
Comment Only
01/03/2024
Final approved, pending Environmental Health corrections.
|
||||
| Fire Inspection Final | Passed | 1/3/2024 (8:00 - 10:00) | 1/3/2024 (AM) | 01/03/2024 |
| Building Final Inspection | Passed | 01/17/2024 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
01/17/2024
Final approved
|
||||