Permit Application Status

PRBD202309799


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202309799
Building
Expired
C & G HOLDING ENTRPRS LLC
Addition
Assembly, restaurants, bars, banquet halls, nightclubs
Tenant Remodel Addition
08/18/2023
04/26/2024
04/27/2025

Locations

Permits

Permit Number: PRBD202309799

Building
Expired
04/26/2024
04/27/2025

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Footing Inspection Partial Pass 5/7/2024 (12:30 - 2:30) 5/7/2024 (PM) 05/07/2024
East side footing inspection - passed. Partial pass for ongoing footing and foundation wall inspection. Special inspections by Braun Intertec.
Footing Inspection Passed 5/30/2024 (12:30 - 2:30) 5/30/2024 (PM) 05/30/2024
West side: poured concrete reinforced footing, including new concrete entry stoop footing. Passed.
Corrections:


Miscellaneous/Other
Comment Only
05/30/2024
West side of existing building. Reinforced concrete footing. Passed.

Footing Inspection Passed 5/31/2024 (12:30 - 2:30) 5/31/2024 (PM) 05/31/2024
West side: Footing and foundation. Passed.
Corrections:


Miscellaneous/Other
Comment Only
05/31/2024
West side, footing and foundation wall. Passed.

Framing Inspection Passed w/ Conditions 7/8/2024 (12:30 - 2:30) 7/8/2024 (PM) 07/08/2024
New, One level exterior roof framing system, steel beams support wood laminated beams, for east side of existing restaurant dinning room only.
Corrections:


Miscellaneous/Other
Comment Only
07/08/2024
Steel Framing for exterior walls for east side dinning room only. Passed with conditions.

Insulation Inspection Passed 7/17/2024 (8:00 - 10:00) 7/17/2024 (AM) 07/17/2024
Insulation inspection, resteraunt remodel, Passed.
Footing Inspection Partial Pass 7/24/2024 (12:30 - 2:30) 7/24/2024 (PM) 07/24/2024
Concrete Footing inspection, passed. A.partial pass to allow for additional inspections.
Corrections:


Miscellaneous/Other
Comment Only
07/24/2024
Footing inspection passed. Partial pass, to allow for additional inspections.

Insulation Inspection Partial Pass 8/7/2024 (2:30 - 3:30) 8/7/2024 (PM) 08/08/2024
PROGRESS - INSULATION , ONGOING.
Corrections:


Miscellaneous/Other
Comment Only
08/08/2024
Progress, insulation.

Lath Inspection Partial Pass 8/7/2024 (2:30 - 3:30) 8/7/2024 (PM) 08/08/2024
Progress. Lath for Sheathing-exterior plywood
Corrections:


Miscellaneous/Other
Comment Only
08/08/2024
Progress, exterior lath for stucco.

Footing Inspection Passed 8/12/2024 (10:00 - 12:00) 8/12/2024 (AM) 08/12/2024
New additional footings.
Above Ceiling Inspection Partial Pass 08/19/2024
Ongoing inspections, partial pass.
Insulation Inspection Partial Pass 8/19/2024 (12:30 - 2:30) 8/19/2024 (PM) 08/19/2024
Insulation: Ongoing inspections, PARTIAL PASS.
Framing Inspection Partial Pass 8/19/2024 (12:30 - 2:30) 8/19/2024 (PM) 08/19/2024
Progress framing inspection, passed. PARTIAL PASS ONGOING FRAMING.
Insulation Inspection Partial Pass 8/23/2024 (10:00 - 12:00) 8/23/2024 (AM) 08/23/2024
Insulation ongoing, partial pass.
Corrections:


Miscellaneous/Other
Comment Only
08/23/2024
Ongoing insulation, passed

Lath Inspection Partial Pass 9/3/2024 (8:00 - 10:00) 9/3/2024 (AM) 09/03/2024
Stucco lath inspection. Passed. PARTIAL PASS for Ongoing inspections.
Corrections:


Miscellaneous/Other
Comment Only
09/03/2024
Stucco lath inspection, passed, ongoing inspections. Partial pass

Miscellaneous/Other
Comment Only
09/03/2024
Stucco lath inspection. Passed. Partial pass for ongoing inspections.

Landscaping Inspection Passed 10/7/2024 10/07/2024
Building Final Inspection Not Ready 10/16/2024 (12:30 - 2:30) 10/16/2024 (PM) 10/16/2024
Need to have final inspection for (new parking lot pervious engineering, final environmental health, final (electrical, mechanical, plumbing, natural gas, accessible parking, other ?
Corrections:


Miscellaneous/Other
Outstanding
10/16/2024
Watershed permit final for drainable permeable parking lot pavers.

Fire Inspection Final Partial Pass 10/16/2024 (12:30 - 2:30) 10/16/2024 (PM) 10/16/2024
Kitchen hood tested, FA tested, sprinkler tamper and waterflow tested. Needs the following: FACP and electrical room signs, Knox box installed and keys added
Fire Inspection Final Passed w/ Conditions 10/21/2024
Building Final Inspection Passed w/ Conditions 10/21/2024 (2:30 - 3:30) 10/21/2024 (PM) 10/21/2024
Need all trade finals and plan review condition's, final approved.
Lighting Inspection Passed 10/28/2024 10/29/2024