PRBD202309799
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Footing Inspection | Partial Pass | 5/7/2024 (12:30 - 2:30) | 5/7/2024 (PM) | 05/07/2024 |
| East side footing inspection - passed. Partial pass for ongoing footing and foundation wall inspection. Special inspections by Braun Intertec. | ||||
| Footing Inspection | Passed | 5/30/2024 (12:30 - 2:30) | 5/30/2024 (PM) | 05/30/2024 |
| West side: poured concrete reinforced footing, including new concrete entry stoop footing. Passed. | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
05/30/2024
West side of existing building. Reinforced concrete footing. Passed.
|
||||
| Footing Inspection | Passed | 5/31/2024 (12:30 - 2:30) | 5/31/2024 (PM) | 05/31/2024 |
| West side: Footing and foundation. Passed. | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
05/31/2024
West side, footing and foundation wall. Passed.
|
||||
| Framing Inspection | Passed w/ Conditions | 7/8/2024 (12:30 - 2:30) | 7/8/2024 (PM) | 07/08/2024 |
| New, One level exterior roof framing system, steel beams support wood laminated beams, for east side of existing restaurant dinning room only. | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
07/08/2024
Steel Framing for exterior walls for east side dinning room only. Passed with conditions.
|
||||
| Insulation Inspection | Passed | 7/17/2024 (8:00 - 10:00) | 7/17/2024 (AM) | 07/17/2024 |
| Insulation inspection, resteraunt remodel, Passed. | ||||
| Footing Inspection | Partial Pass | 7/24/2024 (12:30 - 2:30) | 7/24/2024 (PM) | 07/24/2024 |
| Concrete Footing inspection, passed. A.partial pass to allow for additional inspections. | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
07/24/2024
Footing inspection passed. Partial pass, to allow for additional inspections.
|
||||
| Insulation Inspection | Partial Pass | 8/7/2024 (2:30 - 3:30) | 8/7/2024 (PM) | 08/08/2024 |
| PROGRESS - INSULATION , ONGOING. | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
08/08/2024
Progress, insulation.
|
||||
| Lath Inspection | Partial Pass | 8/7/2024 (2:30 - 3:30) | 8/7/2024 (PM) | 08/08/2024 |
| Progress. Lath for Sheathing-exterior plywood | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
08/08/2024
Progress, exterior lath for stucco.
|
||||
| Footing Inspection | Passed | 8/12/2024 (10:00 - 12:00) | 8/12/2024 (AM) | 08/12/2024 |
| New additional footings. | ||||
| Above Ceiling Inspection | Partial Pass | 08/19/2024 | ||
| Ongoing inspections, partial pass. | ||||
| Insulation Inspection | Partial Pass | 8/19/2024 (12:30 - 2:30) | 8/19/2024 (PM) | 08/19/2024 |
| Insulation: Ongoing inspections, PARTIAL PASS. | ||||
| Framing Inspection | Partial Pass | 8/19/2024 (12:30 - 2:30) | 8/19/2024 (PM) | 08/19/2024 |
| Progress framing inspection, passed. PARTIAL PASS ONGOING FRAMING. | ||||
| Insulation Inspection | Partial Pass | 8/23/2024 (10:00 - 12:00) | 8/23/2024 (AM) | 08/23/2024 |
| Insulation ongoing, partial pass. | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
08/23/2024
Ongoing insulation, passed
|
||||
| Lath Inspection | Partial Pass | 9/3/2024 (8:00 - 10:00) | 9/3/2024 (AM) | 09/03/2024 |
| Stucco lath inspection. Passed. PARTIAL PASS for Ongoing inspections. | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
09/03/2024
Stucco lath inspection, passed, ongoing inspections. Partial pass
|
||||
|
Miscellaneous/Other
Comment Only
09/03/2024
Stucco lath inspection. Passed. Partial pass for ongoing inspections.
|
||||
| Landscaping Inspection | Passed | 10/7/2024 | 10/07/2024 | |
| Building Final Inspection | Not Ready | 10/16/2024 (12:30 - 2:30) | 10/16/2024 (PM) | 10/16/2024 |
| Need to have final inspection for (new parking lot pervious engineering, final environmental health, final (electrical, mechanical, plumbing, natural gas, accessible parking, other ? | ||||
|
Corrections:
Miscellaneous/Other
Outstanding
10/16/2024
Watershed permit final for drainable permeable parking lot pavers.
|
||||
| Fire Inspection Final | Partial Pass | 10/16/2024 (12:30 - 2:30) | 10/16/2024 (PM) | 10/16/2024 |
| Kitchen hood tested, FA tested, sprinkler tamper and waterflow tested. Needs the following: FACP and electrical room signs, Knox box installed and keys added | ||||
| Fire Inspection Final | Passed w/ Conditions | 10/21/2024 | ||
| Lighting Inspection | Passed | 10/28/2024 | 10/29/2024 | |
| Fire Inspection Final | Passed | 12/23/2024 | ||
| All corrections have been made. Patio exiting approved. | ||||
| Building Final Inspection | Passed | 10/21/2024 (2:30 - 3:30) | 10/21/2024 (PM) | 12/23/2024 |
| Need all trade finals and plan review condition's, final approved. | ||||