PRBD202310478
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Pending | |||
Footing Inspection | Partial Pass | 12/20/2023 (12:30 - 2:30) | 12/20/2023 (PM) | 12/20/2023 |
Corrections:
Miscellaneous/Other
Comment Only
12/20/2023
Viewed the rebar and epoxy for the inbed into existing footing.
Threaded rods were not epoxied in place at this time, special inspection to view this and all reports to be sent to city inspector.
|
||||
Building Final Inspection | Passed | 3/7/2024 (8:00 - 10:00) | 3/7/2024 (AM) | 03/07/2024 |
Corrections:
Miscellaneous/Other
Comment Only
03/07/2024
All inspections are completed and approved. Final for this permit approved.
|
||||
Fire Inspection Final | Passed | 3/7/2024 (8:00 - 10:00) | 3/7/2024 (AM) | 03/14/2024 |