PRBD202310480
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Footing Inspection | Partial Pass | 10/13/2023 (8:00 - 10:00) | 10/13/2023 (AM) | 10/13/2023 |
Corrections:
Miscellaneous/Other
Comment Only
10/13/2023
Base footing pad and rebar... approved
|
||||
Footing Inspection | Passed | 10/18/2023 | ||
Corrections:
Miscellaneous/Other
Comment Only
10/18/2023
Poured walls with rebar at pad footing... approved
|
||||
Framing Inspection | Passed | 12/13/2023 (10:00 - 12:00) | 12/13/2023 (AM) | 12/13/2023 |
Corrections:
Miscellaneous/Other
Comment Only
12/13/2023
Steel framework and infill steel stud wall... approved
|
||||
Fire Inspection Final | Passed | 12/21/2023 (8:00 - 10:00) | 12/21/2023 (AM) | 12/21/2023 |
Ride aborted and returned to home when initial alarm activated. After 5 minutes, the alarm went to full alarm status and shut down the power activation button so the ride could not be operated. Water flow triggered an immediate full alarm status notifying the ride operator. | ||||
Building Final Inspection | Passed | 12/21/2023 (8:00 - 10:00) | 12/21/2023 (AM) | 12/21/2023 |
Corrections:
Miscellaneous/Other
Comment Only
12/21/2023
All inspections are completed. Ride inspector is going to be out this morning to final ride before opening to public. Final for this permit approved.
|