Permit Application Status

PRBD202312098


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202312098
Building
Finaled
GKII NORTHLAND CENTER LLC
Alteration/Repair/Replace
Not Required
NCI Cushman & Wakefield minor office remodel suite 200
10/03/2023
11/20/2023
11/12/2024
05/16/2024

Locations

Permits

Permit Number: PRBD202312098

Building
Finaled
11/20/2023
11/12/2024

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Partial Pass 11/28/2023 (8:00 - 10:00) 11/28/2023 (AM) 11/28/2023
Framing 2nd floor: #1, of multiple small area inspections with existing break room sink and new granite counter top.
Corrections:


Miscellaneous/Other
Comment Only
11/28/2023
Ongoing Framing # 1, for 2nd floor. (Ongoing small areas for existing tenant.)

Framing Inspection Partial Pass 12/28/2023 (12:30 - 2:30) 12/28/2023 (PM) 12/28/2023
Corrections:


Miscellaneous/Other
Comment Only
12/28/2023
Framing for first floor only approved.

Progress Inspection Passed 2/12/2024 (8:00 - 10:00) 2/12/2024 (AM) 02/12/2024
(Suite 200. Main floor.) Existing tenant. Progress remodel inspection. Upgrade kitchenette area, add lighting and work areas. Minimal framing. Trade inspections have passed.
Corrections:


Miscellaneous/Other
Comment Only
02/12/2024
Suite 200, main floor. Rough in inspection.

Fire Inspection Final Passed 5/14/2024 (10:00 - 12:00) 5/14/2024 (AM) 05/14/2024
Building Final Inspection Passed 5/14/2024 (10:00 - 12:00) 5/14/2024 (AM) 05/14/2024
Suite 750. Elevator lobby, artwork on wall. Passed
Corrections:


Miscellaneous/Other
Comment Only
05/14/2024
Final suite 750, artwork on elevator lobby wall. Passed.