Permit Application Status

PRBD202312181


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202312181
Building
Finaled
OXBOW REALTY PARTNERS LLC
Alteration/Repair/Replace
Not Required
Interior build-out of an existing shell space with a electronic chip manufacturing facility. Shell permit under PRBD201914504
10/04/2023
11/17/2023
04/06/2025
10/08/2024

Locations

Permits

Permit Number: PRBD202312181

Building
Finaled
11/17/2023
04/06/2025

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Progress Inspection Passed 1/8/2024 (8:00 - 10:00) 1/8/2024 (AM) 01/08/2024
Corrections:


Miscellaneous/Other
Comment Only
01/08/2024
Mat slab rebar with column bars... as per plan and approved.

Progress Inspection Partial Pass 1/12/2024 (10:00 - 12:00) 1/12/2024 (AM) 01/12/2024
Corrections:


Miscellaneous/Other
Comment Only
01/12/2024
Columns on lines 3&4. Rebar as per design, clearance to forms checked as well... approved

Progress Inspection Passed 1/17/2024 (10:00 - 12:00) 1/17/2024 (AM) 01/17/2024
Corrections:


Miscellaneous/Other
Comment Only
01/17/2024
rebar assembly for columns on lines 5,6,&7... approved

Progress Inspection Passed 1/22/2024 (12:30 - 2:30) 1/22/2024 (PM) 01/22/2024
Corrections:


Miscellaneous/Other
Comment Only
01/22/2024
All remaining columns for this area of construction as per plan design and approved for concrete placement.

Progress Inspection Passed 2/8/2024 (8:00 - 10:00) 2/8/2024 (AM) 02/08/2024
Corrections:


Miscellaneous/Other
Comment Only
02/08/2024
This inspection was for the installation of the waffle slab rebar. Rebar , clearance, bar laps, imbeds.... all comply to the design submitted. Approved for concrete placement.

Progress Inspection Partial Pass 3/12/2024 (10:00 - 12:00) 3/12/2024 (AM) 03/12/2024
Corrections:


Miscellaneous/Other
Comment Only
03/12/2024
Viewed the firestops in the sub level and main level for through penetrations at rated walls and floors. Assembly's and installation approved. Fur wall framing at perimeter walls in sub level and main level... approved per design.

Progress Inspection Passed 3/20/2024 (8:00 - 10:00) 3/20/2024 (AM) 03/20/2024
Corrections:


Miscellaneous/Other
Comment Only
03/20/2024
Viewed the mineral wool insulation and poly barrier installed at framed walls... approved Partial covering of the metal panels with the RF tape at seams and fasteners... approved

Building Final Inspection Not Ready 8/14/2024 (10:00 - 12:00) 8/14/2024 (AM) 08/14/2024
Corrections:


Miscellaneous/Other
Carried Forward
08/14/2024
Unable to give a final inspection at this time. Items to be completed for final of this permit... 1)Testing of sprinkler system tamper and flow. 2) install exit sign at vestibule doors, testing of mag holds drop at fire alarm, and manual release of doors. 3) EM lighting and exit signs are on battery backup generator along with the rest of the building... testing verification needed. Inspection to be scheduled wit building and fire inspection, and electrical inspection as needed.

Building Final Inspection Issue TCO 9/3/2024 (10:00 - 12:00) 9/3/2024 (AM) 09/03/2024
Corrections:


Miscellaneous/Other
Resolved
09/03/2024
Unable to give a final inspection at this time. Items to be completed for final of this permit... 1)Testing of sprinkler system tamper and flow. 2) install exit sign at vestibule doors, testing of mag holds drop at fire alarm, and manual release of doors. 3) EM lighting and exit signs are on battery backup generator along with the rest of the building... testing verification needed. Inspection to be scheduled wit building and fire inspection, and electrical inspection as needed.

Miscellaneous/Other
Comment Only
09/03/2024
All testing completed and passed. Final CO is pending the install and testing of the fire dept required EMS repeters. Approved for a 30 day Temp occupancy.

Fire Inspection Final Issue TCO 9/3/2024 (10:00 - 12:00) 9/3/2024 (AM) 09/03/2024
30 day
Fire Inspection Final Passed 10/08/2024
Building Final Inspection Issue CO 10/08/2024
Corrections:


Miscellaneous/Other
Comment Only
10/08/2024
All requirements have been completed, final for this scope of work and permit approved. C of O can be issued for this buildout.