PRBD202312181
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Progress Inspection | Passed | 1/8/2024 (8:00 - 10:00) | 1/8/2024 (AM) | 01/08/2024 |
Corrections:
Miscellaneous/Other
Comment Only
01/08/2024
Mat slab rebar with column bars... as per plan and approved.
|
||||
Progress Inspection | Partial Pass | 1/12/2024 (10:00 - 12:00) | 1/12/2024 (AM) | 01/12/2024 |
Corrections:
Miscellaneous/Other
Comment Only
01/12/2024
Columns on lines 3&4. Rebar as per design, clearance to forms checked as well... approved
|
||||
Progress Inspection | Passed | 1/17/2024 (10:00 - 12:00) | 1/17/2024 (AM) | 01/17/2024 |
Corrections:
Miscellaneous/Other
Comment Only
01/17/2024
rebar assembly for columns on lines 5,6,&7... approved
|
||||
Progress Inspection | Passed | 1/22/2024 (12:30 - 2:30) | 1/22/2024 (PM) | 01/22/2024 |
Corrections:
Miscellaneous/Other
Comment Only
01/22/2024
All remaining columns for this area of construction as per plan design and approved for concrete placement.
|
||||
Progress Inspection | Passed | 2/8/2024 (8:00 - 10:00) | 2/8/2024 (AM) | 02/08/2024 |
Corrections:
Miscellaneous/Other
Comment Only
02/08/2024
This inspection was for the installation of the waffle slab rebar. Rebar , clearance, bar laps, imbeds.... all comply to the design submitted. Approved for concrete placement.
|
||||
Progress Inspection | Partial Pass | 3/12/2024 (10:00 - 12:00) | 3/12/2024 (AM) | 03/12/2024 |
Corrections:
Miscellaneous/Other
Comment Only
03/12/2024
Viewed the firestops in the sub level and main level for through penetrations at rated walls and floors. Assembly's and installation approved.
Fur wall framing at perimeter walls in sub level and main level... approved per design.
|
||||
Progress Inspection | Passed | 3/20/2024 (8:00 - 10:00) | 3/20/2024 (AM) | 03/20/2024 |
Corrections:
Miscellaneous/Other
Comment Only
03/20/2024
Viewed the mineral wool insulation and poly barrier installed at framed walls... approved
Partial covering of the metal panels with the RF tape at seams and fasteners... approved
|
||||
Building Final Inspection | Not Ready | 8/14/2024 (10:00 - 12:00) | 8/14/2024 (AM) | 08/14/2024 |
Corrections:
Miscellaneous/Other
Carried Forward
08/14/2024
Unable to give a final inspection at this time.
Items to be completed for final of this permit...
1)Testing of sprinkler system tamper and flow.
2) install exit sign at vestibule doors, testing of mag holds drop at fire alarm, and manual release of doors.
3) EM lighting and exit signs are on battery backup generator along with the rest of the building... testing verification needed.
Inspection to be scheduled wit building and fire inspection, and electrical inspection as needed.
|
||||
Building Final Inspection | Issue TCO | 9/3/2024 (10:00 - 12:00) | 9/3/2024 (AM) | 09/03/2024 |
Corrections:
Miscellaneous/Other
Resolved
09/03/2024
Unable to give a final inspection at this time.
Items to be completed for final of this permit...
1)Testing of sprinkler system tamper and flow.
2) install exit sign at vestibule doors, testing of mag holds drop at fire alarm, and manual release of doors.
3) EM lighting and exit signs are on battery backup generator along with the rest of the building... testing verification needed.
Inspection to be scheduled wit building and fire inspection, and electrical inspection as needed.
|
||||
Miscellaneous/Other
Comment Only
09/03/2024
All testing completed and passed.
Final CO is pending the install and testing of the fire dept required EMS repeters.
Approved for a 30 day Temp occupancy.
|
||||
Fire Inspection Final | Issue TCO | 9/3/2024 (10:00 - 12:00) | 9/3/2024 (AM) | 09/03/2024 |
30 day | ||||
Fire Inspection Final | Passed | 10/08/2024 | ||
Building Final Inspection | Issue CO | 10/08/2024 | ||
Corrections:
Miscellaneous/Other
Comment Only
10/08/2024
All requirements have been completed, final for this scope of work and permit approved.
C of O can be issued for this buildout.
|