Permit Application Status

PRBD202312195


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202312195
Building
Finaled
SOUTHTOWN OFFICE PARK LLP
Alteration/Repair/Replace
Business
Remodel of existing office space. (Existing space to a new tenant)
10/04/2023
11/09/2023
12/02/2024
06/05/2024

Locations

Permits

Permit Number: PRBD202312195

Building
Finaled
11/09/2023
12/02/2024

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Passed 11/16/2023 (8:00 - 10:00) 11/16/2023 (AM) 11/16/2023
Suite 180 , main floor.
Fire Inspection Final Passed 12/27/2023 (8:00 - 10:00) 12/27/2023 (AM) 12/27/2023
Building Final Inspection Partial Pass 12/27/2023 (8:00 - 10:00) 12/27/2023 (AM) 12/27/2023
Corrections:


Miscellaneous/Other
Comment Only
12/27/2023
Tennants want to take possession of space to set up and use space even though the glass windows are not installed and on backorder. A temp will be allowed for this, pending the final inspection once all glass is installed and final inspection called in. Trades permits to also be final at the time of building final inspection.

Building Final Inspection Passed 6/5/2024 (8:00 - 10:00) 6/5/2024 (AM) 06/05/2024
Corrections:


Miscellaneous/Other
Comment Only
06/05/2024
Final approved