Permit Application Status

PRBD202312626


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202312626
Building
Finaled
GKII NORTHLAND CENTER LLC
Alteration/Repair/Replace
Not Required
Tenant improvement of the buildings 3rd floor including interior demolition, non-structural framing, floor/wall/ceiling finishes, modification of mechanical/electrical/plumbing as required.
10/13/2023
11/14/2023
09/07/2024
03/11/2024

Locations

Permits

Permit Number: PRBD202312626

Building
Finaled
11/14/2023
09/07/2024

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Passed 12/18/2023 (12:30 - 2:30) 12/18/2023 (PM) 12/18/2023
Corrections:


Miscellaneous/Other
Comment Only
12/18/2023
Wall Framing and fire stops... approved

Progress Inspection Partial Pass 1/8/2024 (8:00 - 10:00) 1/8/2024 (AM) 01/08/2024
Progress for total 3rd floor remodel as is. No structural alteration.
Corrections:


Miscellaneous/Other
Comment Only
01/08/2024
3rd floor remodel, no load bearing alterations. Adding offices and additional rooms. Building Progress inspection. A. Note, provide for all mechanical, plumbing, electrical, and fire sprinkler alteration inspections. City inspector Brian Post. Cell phone 952-292-1549.

Progress Inspection Not Ready 1/25/2024 (12:30 - 2:30) 1/25/2024 (PM) 01/25/2024
Corrections:


Miscellaneous/Other
Carried Forward
01/25/2024
Add and or relocate exit signs as per walk through today. Need final fire inspection for first phase. Inspector to return next day to confirm corrections and issue partial occupancy.

Fire Inspection Final Failed 1/26/2024 (12:30 - 2:30) 1/26/2024 (PM) 01/26/2024
Building Final Inspection Partial Pass 2/22/2024 (8:00 - 10:00) 01/26/2024
Corrections:


Miscellaneous/Other
Comment Only
01/26/2024
Partial occupancy approved for phase 1 only.

Building Final Inspection Issue TCO 2/22/2024 (8:00 - 10:00) 2/22/2024 (AM) 02/22/2024
Corrections:


Miscellaneous/Other
Carried Forward
02/22/2024
1. Need final electrical. 2. Complete installation of door hardware. 3. Complete fire, caulking in electrical room. 4. 30 day temporary occupancy approved.

Fire Inspection Final Passed w/ Conditions 2/22/2024 (8:00 - 10:00) 2/22/2024 (AM) 02/23/2024
Building Final Inspection Passed 3/11/2024 (10:00 - 12:00) 3/11/2024 (AM) 03/11/2024
Corrections:


Miscellaneous/Other
Resolved
03/11/2024
1. Need final electrical. 2. Complete installation of door hardware. 3. Complete fire, caulking in electrical room. 4. 30 day temporary occupancy approved.