PRBD202313324
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Building Final Inspection | Partial Pass | 11/16/2023 (12:30 - 2:30) | 11/16/2023 (PM) | 11/16/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/16/2023
Approved to set up and stock as per EH.
Complete installations and call for final.
|
||||
| Building Final Inspection | Partial Pass | 11/21/2023 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
11/21/2023
All shelving and counters with cashwrap installed... approved
Approved for temp and to open.
final inspection with open permits to be scheduled.
|
||||
| Fire Inspection Final | Passed | 11/16/2023 (12:30 - 2:30) | 11/16/2023 (PM) | 11/21/2023 |
| Building Final Inspection | Passed | 12/1/2023 (2:30 - 3:30) | 12/1/2023 (PM) | 12/01/2023 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/01/2023
Final approved... pending final of electrical permit.
|
||||