PRBD202313901
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Building Final Inspection | Pending | |||
Framing Inspection | Partial Pass | 1/12/2024 (8:00 - 10:00) | 1/12/2024 (AM) | 01/12/2024 |
Corrections:
Miscellaneous/Other
Comment Only
01/12/2024
Fire stops of through floor penetrations at 2nd floor breakroom... approved
|
||||
Building Final Inspection | Partial Pass | 3/7/2024 (7:00 - 8:00) | 3/7/2024 (AM) | 03/07/2024 |
Corrections:
Miscellaneous/Other
Comment Only
03/07/2024
Exiting to be corrected on second floor. Exit signs to be relocated to the proper door used in exiting.
Approved for temp final for second floor pending corrections and reinspection for final of this phase.
|
||||
Fire Inspection Final | Partial Pass | 3/7/2024 (7:00 - 8:00) | 3/7/2024 (AM) | 03/14/2024 |
Framing Inspection | Passed | 4/19/2024 (10:00 - 12:00) | 4/19/2024 (AM) | 04/19/2024 |
Corrections:
Miscellaneous/Other
Comment Only
04/19/2024
Framing on first phase of 3rd floor approved
|
||||
Progress Inspection | Passed | 6/25/2024 (8:00 - 10:00) | 6/25/2024 (AM) | 06/25/2024 |
Corrections:
Miscellaneous/Other
Comment Only
06/25/2024
3rd floor phase 1 approved for tenant use, pending fire inspection approval.
|
||||
Fire Inspection Final | Partial Pass | 6/26/2024 (8:00 - 10:00) | 6/26/2024 (AM) | 06/26/2024 |
Progress Inspection | Passed | 7/24/2024 (10:00 - 12:00) | 7/24/2024 (AM) | 07/24/2024 |
Corrections:
Miscellaneous/Other
Comment Only
07/24/2024
Framing of phase 2 of 3rd floor, (lobby) approved
|
||||
Framing Inspection | Passed | 9/3/2024 (8:00 - 10:00) | 9/3/2024 (AM) | 09/03/2024 |
Corrections:
Miscellaneous/Other
Comment Only
09/03/2024
Framing and fire stops of 3rd floor phase 3... approved
|
||||
Building Final Inspection | Partial Pass | 10/25/2024 (8:00 - 10:00) | 10/25/2024 (AM) | 10/25/2024 |
Corrections:
Miscellaneous/Other
Comment Only
10/25/2024
Partial pass for the final of this project. Retesting of the alarm and strobes is needed. Schedule final with fire inspection when system has been made functional.
|
||||
Fire Inspection Final | Passed | 10/25/2024 (8:00 - 10:00) | 10/25/2024 (AM) | 11/04/2024 |