Permit Application Status

PRBD202314643


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202314643
Building
Expired
MOAC MALL HOLDINGS LLC
Alteration/Repair/Replace
Not Required
Sweet Paris - 100 North Garden - Tenant Remodel Construct new restaurant in old Tiger Sushi and adjacent retail space on the first floor of the Mall of America next to Nordstrom.
12/01/2023
02/12/2024
12/03/2024

Locations

Permits

Permit Number: PRBD202314643

Building
Expired
02/12/2024
12/03/2024

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Fire Inspection Final Pending
Framing Inspection Passed 3/1/2024 (8:00 - 10:00) 3/1/2024 (AM) 03/01/2024
Corrections:


Miscellaneous/Other
Comment Only
03/01/2024
All Framing and fire stops... approved

Framing Inspection Passed 5/6/2024 (8:00 - 10:00) 5/6/2024 (AM) 05/06/2024
Corrections:


Miscellaneous/Other
Comment Only
05/06/2024
Above ceiling and suspended ceiling framing... approved

Building Final Inspection Partial Pass 5/24/2024 (2:30 - 3:30) 5/24/2024 (PM) 05/24/2024
Corrections:


Miscellaneous/Other
Carried Forward
05/24/2024
Corrections.... 1) install smoke seal at rear door 2) install escutcheon to sprink head outsie of rear door 3) install fire extinguishers by food cooking area. 4) shelving above prep area in back is to close to ceiling and sprinkler, 18" of clearance needed to ceiling and sprinkler head from any stored goods. 5) label electrical room for fire department requirements. These items to be checked at final inspection.

Miscellaneous/Other
Comment Only
05/24/2024
Approved to set up and train staff. Call for final when all is completed.

Fire Inspection Final Partial Pass 5/24/2024 (2:30 - 3:30) 5/24/2024 (PM) 05/30/2024
Building Final Inspection Passed 6/6/2024 (8:00 - 10:00) 6/6/2024 (AM) 06/06/2024
Corrections:


Miscellaneous/Other
Resolved
06/06/2024
Corrections.... 1) install smoke seal at rear door 2) install escutcheon to sprink head outsie of rear door 3) install fire extinguishers by food cooking area. 4) shelving above prep area in back is to close to ceiling and sprinkler, 18" of clearance needed to ceiling and sprinkler head from any stored goods. 5) label electrical room for fire department requirements. These items to be checked at final inspection.

Miscellaneous/Other
Comment Only
06/06/2024
Final for this buildout approved.