Permit Application Status

PRBD202315421


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202315421
Building
Expired
8800 QUEEN LLC
Alteration/Repair/Replace
Business
General Dynamics Phase 1 - Demo of interior office space and build out of new IT Space
12/20/2023
12/29/2023
09/30/2024

Locations

Permits

Permit Number: PRBD202315421

Building
Expired
12/29/2023
09/30/2024

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Building Final Inspection Pending
Framing Inspection Partial Pass 1/10/2024 (8:00 - 10:00) 1/10/2024 (AM) 01/10/2024
Area B per plan. A. consult with contractor on fire caulk areas, origional to building. B. Space was demolitioned. C. Reviewed ( Major) large ductwork origional to building requires fire caulk systems thru origional building masonry wall. D. All new (HVAC diffusers, fire sprinkler supply, and ceiling lighting.)
Corrections:


Miscellaneous/Other
Comment Only
01/10/2024
( Work Area B.) Call for all trade rough in inspections. Framing, Mechanical, Electrical, low voltage control wiring, fire sprinkler piping, and fire caulk rated systems. Note- DJ Kranze representitive on site.

Above Ceiling Inspection Not Ready 2/15/2024 (10:00 - 12:00) 2/15/2024 (AM) 02/15/2024
Cancelled by contractor as sub contractor work not completed, thx. [jsmidt @ 02/15/2024 8:32 AM]
Corrections:


Miscellaneous/Other
Comment Only
02/15/2024
Not ready for inspection. Call when ready.

Above Ceiling Inspection Passed 2/20/2024 (10:00 - 12:00) 2/20/2024 (AM) 02/20/2024
Above ceiling with contractor.
Corrections:


Miscellaneous/Other
Comment Only
02/20/2024
Above ceiling passed. Verbal order to general contractor to check that all trades have had there above ceiling inspections passed.

Fire Inspection Final Not Ready 3/26/2024 (12:30 - 2:30) 3/26/2024 (PM) 03/26/2024
Building Final Inspection Partial Pass 3/27/2024 (8:00 - 10:00) 3/27/2024 (AM) 03/27/2024
Phase 1of 2 passed only.
Corrections:


Miscellaneous/Other
Comment Only
03/27/2024
Final for phase 1 only of 2 phase. Pass for office addition north. Status, phase 2 to follow.

Framing Inspection Passed 3/27/2024 (8:00 - 10:00) 3/27/2024 (AM) 03/27/2024
Building final for phase 1 only of 2 phases. Pass phase 1 only.
Corrections:


Miscellaneous/Other
Outstanding
01/10/2024
( Work Area B.) Call for all trade rough in inspections. Framing, Mechanical, Electrical, low voltage control wiring, fire sprinkler piping, and fire caulk rated systems. Note- DJ Kranze representitive on site.

Fire Inspection Final Passed 04/03/2024