PRBD202400513
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Partial Pass | 3/13/2024 (8:00 - 10:00) | 3/13/2024 (AM) | 03/13/2024 |
Corrections:
Miscellaneous/Other
Comment Only
03/13/2024
Partial framing of new corridor, what is in place is approved.
Mall to verify the layes of gypsum at the one stairwell for the assembly used, there is only 1 layer of gypsuon the corridor side of that stairwell.
|
||||
Framing Inspection | Passed | 4/8/2024 (10:00 - 12:00) | 4/8/2024 (AM) | 04/08/2024 |
Corrections:
Miscellaneous/Other
Comment Only
04/08/2024
Framing approved
|
||||
Fire Inspection Final | Not Ready | 5/13/2024 (8:00 - 10:00) | 5/13/2024 (AM) | 05/13/2024 |
Corrections:
Miscellaneous/Other
Carried Forward
05/13/2024
Fire alarm testing has not been completed.
|
||||
Building Final Inspection | Partial Pass | 5/13/2024 (8:00 - 10:00) | 5/13/2024 (AM) | 05/13/2024 |
Corrections:
Miscellaneous/Other
Comment Only
05/13/2024
1) fire inspection to follow up with system testing.
2) flex sprinkler head to be removed.
3) door to be stenciled as " no exit" on the side leading to the dead end.
Final can be given when these items are completed and approved.
|
||||
Fire Inspection Final | Passed | 05/20/2024 | ||
Corrections:
Miscellaneous/Other
Outstanding
05/13/2024
Fire alarm testing has not been completed.
|
||||
Building Final Inspection | Passed | 05/20/2024 | ||
Corrections:
Miscellaneous/Other
Comment Only
05/20/2024
All corrections completed, fire testing has been approved.
Final for this permit approved.
|