PRBD202401182
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed w/ Conditions | 3/21/2024 (12:30 - 2:30) | 3/21/2024 (PM) | 03/21/2024 |
Corrections:
Miscellaneous/Other
Comment Only
03/21/2024
Framing at walls approved, pending removal of wood backing in storefront.
Ceilings need to be open for sprinkler inspection, once fire inspection has approved sprinklers... those can be covered.
|
||||
Building Final Inspection | Partial Pass | 5/3/2024 (10:00 - 12:00) | 5/3/2024 (AM) | 05/03/2024 |
Corrections:
Miscellaneous/Other
Carried Forward
05/03/2024
Corrections....
1) install the lathing strike for the detac unit at back door.
2) patch holes in stairwell wall by extinguisher.
3) call for final when sign is installed and inspected.
Approved for temporary occupancy
|
||||
Building Final Inspection | Passed | 5/8/2024 (10:00 - 12:00) | 5/8/2024 (AM) | 05/08/2024 |
Corrections:
Miscellaneous/Other
Resolved
05/08/2024
Corrections....
1) install the lathing strike for the detac unit at back door.
2) patch holes in stairwell wall by extinguisher.
3) call for final when sign is installed and inspected.
Approved for temporary occupancy
|
||||
Miscellaneous/Other
Comment Only
05/08/2024
Final approved
|
||||
Fire Inspection Final | Passed | 5/3/2024 (10:00 - 12:00) | 5/3/2024 (AM) | 05/10/2024 |