Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 4/23/2024 (12:30 - 2:30) | 4/23/2024 (PM) | 06/17/2024 |
Steel stud framing - passed, but need many holes thru walls to other tenants, fire caulked with 2 hr fire caulk. | ||||
Corrections:
Miscellaneous/Other
Resolved
06/17/2024
Framing passed, but partial pass due to many holes to other tenant's.
Use requires 2 hour fire caulk. Partial pass to return to inspect fire caulk above ceilings.
|
||||
Framing Inspection | Passed w/ Conditions | 6/17/2024 (10:00 - 12:00) | 6/17/2024 (AM) | 06/17/2024 |
A. Framing passed. B. (NOTE, Need mechanical rough and fire sprinkler rough in inspection, passed for above ceiling, prior to covering. | ||||
Corrections:
Miscellaneous/Other
Comment Only
06/17/2024
A. Fire caulk passed. B. Comment, slope floor along existing ADA COUNTER TOP, AS DISCUSSED, TO ACHIEVE 34 INCHES ON ABOVE FLOOR TO MEET ADA. C. Need mechanical and fire sprinkle rough in inspection passed.
|
||||
Building Final Inspection | Passed | 8/29/2024 (2:30 - 3:30) | 8/29/2024 (PM) | 08/29/2024 |
Corrections:
Miscellaneous/Other
Comment Only
08/29/2024
Building final approved, pending fire inspection final to close permit.
|
||||
Fire Inspection Final | Not Ready | 8/29/2024 (2:30 - 3:30) | 8/29/2024 (PM) | 09/06/2024 |
Fire Inspection Final | Passed | 01/06/2025 |