PRBD202402418
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Footing Inspection | Pending | |||
Insulation Inspection | Pending | |||
Lath Inspection | Pending | |||
Fire Inspection Final | Pending | |||
Building Final Inspection | Pending | |||
Lighting Inspection | Pending | 9/30/2025 | ||
Landscaping Inspection | Pending | 9/30/2025 | ||
Framing Inspection | Partial Pass | 09/25/2024 | ||
Corrections:
Miscellaneous/Other
Comment Only
09/25/2024
Exterior wall framing for fist floor, at line 8, grids A through E.
Wall line on grid E, lines 8-9
|
||||
Framing Inspection | Passed | 2/6/2025 (10:00 - 12:00) | 09/27/2024 | |
Corrections:
Miscellaneous/Other
Comment Only
09/27/2024
Exterior wall framing of level 1, at grid B, line 4-7
Grid A, line 7' to 9
|
||||
Framing Inspection | Passed | 10/01/2024 | ||
Corrections:
Miscellaneous/Other
Comment Only
10/01/2024
Exterior wall section at level 1 on line 2.6, grid B to C.5.
|
||||
Framing Inspection | Partial Pass | 10/03/2024 | ||
Corrections:
Miscellaneous/Other
Comment Only
10/03/2024
Exterior wall framing on level 1, grid J, from lines 4 to 6.
|
||||
Framing Inspection | Partial Pass | 10/14/2024 | ||
Corrections:
Miscellaneous/Other
Comment Only
10/14/2024
More exterior wall sections are being placed on second level west side. Viewed the installation of the slab edge fire stop system at floor.... approved
|
||||
Framing Inspection | Partial Pass | 10/23/2024 | ||
Corrections:
Miscellaneous/Other
Comment Only
10/23/2024
Exterior wall sections around 2nd level perimeter framing and floor edge fire stops are in process and approved.
|
||||
Progress Inspection | Passed | 12/30/2024 | ||
Corrections:
Miscellaneous/Other
Comment Only
12/30/2024
Windows installed all around building, installation approved.
Housewrap on building installed per manufacture requirements.
|
||||
Progress Inspection | Passed | 1/2/2025 (10:00 - 12:00) | 1/2/2025 (AM) | 01/02/2025 |
Vapor barrier inspection | ||||
Corrections:
Miscellaneous/Other
Comment Only
10/28/2024
Slab on grade with mesh reinforcement at grids H to J, lines 1 to 4.
|
||||
Progress Inspection | Passed | 1/8/2025 (10:00 - 12:00) | 1/8/2025 (AM) | 01/08/2025 |
Vapor barrier | ||||
Corrections:
Miscellaneous/Other
Comment Only
12/11/2024
Slab on grade reinforcment and poly barrier grids E to F, lines 4.5 to 6 and grids A to E, lines 5 to 9
|
||||
Framing Inspection | Passed | 1/16/2025 (12:30 - 2:30) | 1/16/2025 (PM) | 01/16/2025 |
Corrections:
Miscellaneous/Other
Comment Only
01/16/2025
2nd floor framing and firestops... all areas approved except for servery area.
|
||||
Framing Inspection | Passed | 1/17/2025 (10:00 - 12:00) | 1/17/2025 (AM) | 01/17/2025 |
Corrections:
Miscellaneous/Other
Comment Only
01/17/2025
Large section of slab on grade with poly barrier and mesh reinforcement. This section covers the south end of building about halfway to center to the north.... approved
|
||||
Progress Inspection | Passed | 02/11/2025 | ||
Corrections:
Miscellaneous/Other
Comment Only
02/11/2025
Framing of third level... approved
|
||||
Framing Inspection | Passed | 2/21/2025 (8:00 - 10:00) | 2/21/2025 (AM) | 02/21/2025 |
Corrections:
Miscellaneous/Other
Comment Only
02/21/2025
Framing at 4th floor and above ceiling and ceiling framing of 2nd floor... approved
|
||||
Framing Inspection | Partial Pass | 2/24/2025 (12:30 - 2:30) | 2/24/2025 (PM) | 02/24/2025 |
Corrections:
Miscellaneous/Other
Comment Only
02/24/2025
Framing that is up for first floor isnt all completed. What is standing is approved, but pending inspection of electrical and plumbing prior to covering.
|
||||
Framing Inspection | Passed | 03/28/2025 | ||
Corrections:
Miscellaneous/Other
Comment Only
03/28/2025
Framing of Front shaft wall of elevator.
Gypsum layers at stairway... approved
Viewedroof section that had fire damage.This section had damage to the top layer of insulation and the roofing cover, damage did not happen to the structure.
|
||||
Above Ceiling Inspection | Passed | 04/14/2025 | ||
Corrections:
Miscellaneous/Other
Comment Only
04/14/2025
Ceiling framing and supports for bathrooms of floors 2&3... approved
Kneewall framing at atrium 4th level.
Service elevator shaft wall framing floors 1-4.
Fire proofing of beam at roof.
Approved
|
||||
Gypsum Board/Sheet Rock Inspection | Passed | 04/23/2025 | ||
Corrections:
Miscellaneous/Other
Comment Only
04/23/2025
Main elevators floors 1-3... front wall is of shaft wall framing. Install and framing approved .
Rebuild of damaged parapet on roof... approved
|