PRBD202402776
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 5/28/2024 (10:00 - 12:00) | 5/28/2024 (PM) | 05/28/2024 |
Corrections:
Miscellaneous/Other
Comment Only
05/28/2024
Wall Framing approved
|
||||
Building Final Inspection | Partial Pass | 7/11/2024 (7:00 - 8:00) | 7/11/2024 (AM) | 07/11/2024 |
Corrections:
Miscellaneous/Other
Comment Only
07/11/2024
Complete setup of space with the displays , cashwrap, and fitting room signage. Call for final inspection when space is setup.
Approved to bring in goods and finish up the setup.
|
||||
Building Final Inspection | Passed | 7/15/2024 (8:00 - 10:00) | 7/15/2024 (AM) | 07/15/2024 |
Corrections:
Miscellaneous/Other
Comment Only
07/15/2024
Final approved and ok to stock and open to public.
|
||||
Fire Inspection Final | Passed | 7/11/2024 (7:00 - 8:00) | 7/11/2024 (AM) | 07/16/2024 |