PRBD202403365
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 4/23/2024 (10:00 - 12:00) | 4/23/2024 (AM) | 04/23/2024 |
A. Framing inspection passed. B. Existing spray applied fire proofing - passed | ||||
Corrections:
Miscellaneous/Other
Comment Only
04/23/2024
Framing and spray applied fireproofing. Passed.
|
||||
Fire Inspection Final | Not Ready | 6/10/2024 (12:30 - 2:30) | 6/10/2024 (PM) | 06/10/2024 |
Building Final Inspection | Issue CO | 6/10/2024 (12:30 - 2:30) | 6/10/2024 (PM) | 06/10/2024 |
Corrections:
Miscellaneous/Other
Comment Only
06/10/2024
Final approval contingent on final fire approval.
|
||||
Fire Inspection Final | Passed | 06/20/2024 |