PRBD202403846
Building
Permit(s) Issued
HRA CITY OF BLOOMINGTON
New
Residential, multiple family
New construction of a 99-unit multi-family apartment building. 1 level of underground parking with a precast lid and 4 stories of wood framed apartments above.
04/01/2024
06/20/2024
09/28/2025

Locations

Permits

Permit Number: PRBD202403846

Building
Issued
06/20/2024
09/28/2025

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Fire Inspection Final Pending
Landscaping Inspection Pending 5/31/2025
Framing Inspection Not Ready 7/29/2024 (8:00 - 10:00) 7/29/2024 (AM) 07/29/2024
Framing not ready,
Corrections:


Miscellaneous/Other
Comment Only
07/29/2024
Framing not ready.

Framing Inspection Partial Pass 7/31/2024 (8:00 - 10:00) 7/31/2024 (AM) 07/31/2024
Framing, prefabricated wall panels, except elevator shaft, and others. Passed. Partial pass for ongoing inspections.
Corrections:


Miscellaneous/Other
Comment Only
07/31/2024
Framing inspection, prefabricated wall panels. Passed, Partial pass for ongoing work.

Framing Inspection Partial Pass 8/2/2024 (8:00 - 10:00) 8/2/2024 (AM) 08/02/2024
Framing partial pass. Panelized walls, constructed in truss plant.
Corrections:


Miscellaneous/Other
Comment Only
08/02/2024
Framing progress, panelized in truss plant. PARTIAL PASS.

Framing Inspection Partial Pass 8/5/2024 (8:00 - 10:00) 8/5/2024 (AM) 08/05/2024
Framing progress inspection Passed. (Partial pass for ongoing inspections.)
Corrections:


Miscellaneous/Other
Comment Only
08/05/2024

Miscellaneous/Other
Comment Only
08/05/2024
(Framing inspection passed) partial pass status for ongoing inspections.

Framing Inspection Partial Pass 8/7/2024 (8:00 - 10:00) 8/7/2024 (AM) 08/07/2024
Progress framing. level 1, Passed.
Corrections:


Miscellaneous/Other
Comment Only
08/07/2024
Progress framing , floor 1. Passed.

Framing Inspection Partial Pass 8/9/2024 (8:00 - 10:00) 8/9/2024 (AM) 08/09/2024
Framing progress inspection, Partial pass. Ongoing progress inspections.
Corrections:


Miscellaneous/Other
Comment Only
08/09/2024
Progress Framing inspections, PARTIAL PASS, ONGOING INSPECTIONS.

Framing Inspection Passed 8/12/2024 (8:00 - 10:00) 8/12/2024 (AM) 08/12/2024
Framing inspection, ongoing. Passed.
Corrections:


Miscellaneous/Other
Comment Only
08/12/2024
Framing inspection passed, ongoing inspections. PARTIAL PASS

Framing Inspection Partial Pass 8/19/2024 (8:00 - 10:00) 8/19/2024 (AM) 08/19/2024
Ongoing framing inspections. PASSED.
Corrections:


Miscellaneous/Other
Comment Only
08/19/2024
On going; Framing, PARTIAL PASS.

Framing Inspection Partial Pass 8/21/2024 (8:00 - 10:00) 8/21/2024 (AM) 08/21/2024
Framing for prefabricated wall sections,
Corrections:


Miscellaneous/Other
Comment Only
08/21/2024
Framing ; for prefabricated walls with gypsum sheeting, from truss plant. ( Ongoing. Partial pass. )

Framing Inspection Partial Pass 8/23/2024 (8:00 - 10:00) 8/23/2024 (AM) 08/23/2024
Framing progress inspection. Partial pass. Ongoing.
Corrections:


Miscellaneous/Other
Comment Only
08/23/2024
Progress . Framing partial Pass, ongoing.

Framing Inspection Partial Pass 8/26/2024 (8:00 - 10:00) 8/26/2024 (AM) 08/27/2024
Ongoing framing for prefabricated wall panels, PASSED.
Corrections:


Miscellaneous/Other
Comment Only
08/27/2024
FRAMING, Prefabricated WALL PANELS.Partial pass ongoing.

Framing Inspection Partial Pass 8/28/2024 (8:00 - 10:00) 8/28/2024 (AM) 08/28/2024
Framing; Progress inspection passed. Note PARTIAL PASS for ongoing inspections.
Corrections:


Miscellaneous/Other
Comment Only
08/28/2024
Framing: Progress inspection. Passed. Partial pass status for ongoing inspections.

Framing Inspection Partial Pass 8/30/2024 (8:00 - 10:00) 8/30/2024 (AM) 09/03/2024
Progress Framing inspection. Partial pass. Ongoing.
Corrections:


Miscellaneous/Other
Comment Only
09/03/2024
Progress framing inspection. Ongoing inspections. Partial pass.

Framing Inspection Partial Pass 9/4/2024 (8:00 - 10:00) 9/4/2024 (AM) 09/04/2024
Progress framing, floor 1, A. Tyvek and setting windows. Passed. ( Ongoing partial pass status.)
Corrections:


Miscellaneous/Other
Comment Only
09/04/2024
First floor framing, housewrap, and installing windows. Passed. Partial pass for ongoing work.

Follow-up Inspection Passed w/ Conditions 09/05/2024
Framing Inspection Partial Pass 9/6/2024 (8:00 - 10:00) 9/6/2024 (AM) 09/06/2024
Framing, partial pass, for ongoing inspections
Framing Inspection Partial Pass 9/9/2024 (8:00 - 10:00) 9/9/2024 (AM) 09/09/2024
Progress inspection framing, Passed. Partial pass for ongoing work
Corrections:


Miscellaneous/Other
Comment Only
09/09/2024
Framing progress Inspection, Passed. partial pass for ongoing work.

Framing Inspection Partial Pass 9/11/2024 (8:00 - 10:00) 9/11/2024 (AM) 09/11/2024
Progress Framing. PASSED.
Corrections:


Miscellaneous/Other
Comment Only
09/11/2024
Progress framing, PASSED.

Framing Inspection Partial Pass 9/13/2024 (8:00 - 10:00) 9/13/2024 (AM) 09/13/2024
Framing inspection, partial pass, ongoing.
Framing Inspection Partial Pass 9/16/2024 (8:00 - 10:00) 9/16/2024 (AM) 09/16/2024
Framing, progress inspection, passed, PARTIAL PASS FOR ONGOING INSPECTIONS.
Framing Inspection Partial Pass 9/18/2024 (8:00 - 10:00) 9/18/2024 (AM) 09/18/2024
Progress, start of elevator shaft fire rated assembly. (2 layers of FRP( Fire rated ply wood. Note, off set all seams, ( both horizontal and vertical )
Corrections:


Miscellaneous/Other
Comment Only
09/18/2024
Start of 2 layers of (fire rated plywood) NOTE, OFF SET ALL SEAMS.

Framing Inspection Partial Pass 9/20/2024 (8:00 - 10:00) 09/18/2024
Ongoing inspections passed. Partial pass for additional inspections.
Framing Inspection Partial Pass 9/23/2024 (8:00 - 10:00) 9/23/2024 (AM) 09/23/2024
Progress Framing. PASSED. PARTIAL PASS FOR ONGOING INSPECTIONS.
Fire Rough-in Inspection Partial Pass 09/23/2024
Verified standpipes were installed in both stairwells. Pre-incident tour with FM5,C4, E4 (A shift).
Framing Inspection Partial Pass 9/25/2024 (8:00 - 10:00) 9/25/2024 (AM) 09/25/2024
Framing ; Progress inspection PASSED. PARTIAL PASS FOR ONGOING INSPECTIONS.
Framing Inspection Partial Pass 9/27/2024 (8:00 - 10:00) 9/27/2024 (AM) 09/27/2024
Framing inspection, Passed. (Partial pass status for ongoing inspections.)
Framing Inspection Partial Pass 9/30/2024 (8:00 - 10:00) 9/30/2024 (AM) 09/30/2024
Framing; floors 1-4. Passed. (Partial pass for ongoing framing inspections.)
Progress Inspection Partial Pass 10/2/2024 (8:00 - 10:00) 10/2/2024 (AM) 10/02/2024
Ongoing inspections.
Progress Inspection Partial Pass 10/4/2024 (8:00 - 10:00) 10/4/2024 (AM) 10/04/2024
Framing concepts, passed. Note partial pass for ongoing inspections.
Progress Inspection Partial Pass 10/7/2024 (8:00 - 10:00) 10/7/2024 (AM) 10/07/2024
Progress Framing, PASSED. (Partial pass for on going inspections.)
Progress Inspection Partial Pass 10/9/2024 (8:00 - 3:30) 10/9/2024 (AM) 10/09/2024
4th floor fire caulk. East to west.(Passed.) partial pass for ongoing inspections
Progress Inspection Passed 10/11/2024 (8:00 - 10:00) 10/11/2024 (AM) 10/11/2024
Framing firecaulk (4th floor east to west ) PASSED. (PARTIAL PASS for ongoing inspections.
Progress Inspection Partial Pass 10/14/2024 (8:00 - 10:00) 10/14/2024 (AM) 10/14/2024
Insulation; exterior wall with vapor barrier, and interior walls for sound insulation.PASSED. (Partial pass status for ongoing insulation inspections..)
Corrections:


Miscellaneous/Other
Comment Only
10/14/2024
3rd floor: (Interior; wall Insulation, ) (exterior wall insulation with poly vapor barrier. PASSED.

Progress Inspection Passed 10/16/2024 (8:00 - 10:00) 10/16/2024 (AM) 10/16/2024
4 th floor, framing and firecaulk. Completed. Passed. (Partial pass for ongoing inspections )
Progress Inspection Partial Pass 10/18/2024 (8:00 - 10:00) 10/18/2024 (AM) 10/21/2024
General walk thru, all trades, passed. Partial pass for on going inspections.
Progress Inspection Passed 10/21/2024 (8:00 - 10:00) 10/21/2024 (AM) 10/21/2024
On going
Progress Inspection Partial Pass 10/23/2024 (8:00 - 10:00) 10/23/2024 (AM) 10/23/2024
Framing and fire caulk for living units. Passed. (Partial pass status for ongoing inspections.)
Corrections:


Miscellaneous/Other
Comment Only
10/23/2024
Framing and fire caulk inspections. Passed.

Progress Inspection Partial Pass 10/25/2024 (8:00 - 10:00) 10/25/2024 (AM) 10/25/2024
Progress Framing, passed. Partial pass for ongoing inspections.
Progress Inspection Partial Pass 10/28/2024 (8:00 - 10:00) 10/28/2024 (AM) 10/28/2024
Insulation passed
Corrections:


Miscellaneous/Other
Comment Only
10/28/2024
Insulation passed. Partial pass for on going inspections.

Progress Inspection Partial Pass 10/30/2024 (8:00 - 10:00) 10/30/2024 (AM) 10/30/2024
Framing and firecaulk inspection. Passed. (Partial pass for ongolng inspections)
Progress Inspection Passed 11/1/2024 (8:00 - 10:00) 11/1/2024 (AM) 11/01/2024
Progress Inspection Partial Pass 11/4/2024 (8:00 - 10:00) 11/4/2024 (AM) 11/04/2024
Progress framing, not ready.
Corrections:


Miscellaneous/Other
Comment Only
11/04/2024
Not ready. Interior framing and fire caulking.

Progress Inspection Partial Pass 11/5/2024 (Afternoon) 11/5/2024 (PM) 11/05/2024
2nd floor. Framing and fire caulk. Passed. (Partial pass status for ongoing inspections.)
Progress Inspection Partial Pass 11/6/2024 (8:00 - 10:00) 11/6/2024 (AM) 11/06/2024
2nd floor, framing and firecaulk inspection. Passed.(Partial pass status for additional inspections.)
Progress Inspection Partial Pass 11/8/2024 (8:00 - 10:00) 11/8/2024 (AM) 11/08/2024
2nd floor. Framing and firecaulk.PASSED. (PARTIAL PASS FOR ONGOING inspections.)
Progress Inspection Partial Pass 11/13/2024 (8:00 - 10:00) 11/13/2024 (AM) 11/13/2024
Exterior building Stucco meeting with Olympic stucco. Passed. Partial pass for ongoing inspections.
Corrections:


Miscellaneous/Other
Comment Only
11/13/2024
Stucco meeting on site, with Olympic stucco.passed. ( Partial pass for ongoing inspections)

Progress Inspection Partial Pass 11/15/2024 (8:00 - 10:00) 11/15/2024 (AM) 11/15/2024
Ongoing inspections, exterior stucco progress inspections. PASSED.
Progress Inspection Partial Pass 11/18/2024 (8:00 - 10:00) 11/18/2024 (AM) 11/18/2024
1st floor fire caulk - ceiling only. ( 1st Floor, floor fire caulk from parking ramp below.)
Progress Inspection Partial Pass 11/19/2024
Progress, stucco, firecaulk, framing.
Progress Inspection Not Ready 11/20/2024 (8:00 - 10:00) 11/20/2024 (AM) 11/20/2024
Please schedule framing and insulation, for Friday November 21. 8;00 AM.
Corrections:


Miscellaneous/Other
Comment Only
11/20/2024
Framing and Insulation. Schedule for Thursday NOVEMBER 21, 2024.

Progress Inspection Partial Pass 11/22/2024 (8:00 - 10:00) 11/22/2024 (AM) 11/22/2024
Insulation-vapor barier. Passed. ( Partial pass for ongoing inspections.)
Progress Inspection Partial Pass 11/25/2024 (8:00 - 10:00) 11/25/2024 (AM) 11/25/2024
Stucco exterior
Corrections:


Miscellaneous/Other
Comment Only
11/25/2024
Exterior stucco, partial pass. Ongoing.

Progress Inspection Partial Pass 11/27/2024 (8:00 - 10:00) 11/27/2024 (AM) 11/27/2024
On going inspections.
Building Final Inspection Partial Pass 2/24/2025 (8:00 - 10:00) 2/24/2025 (AM) 02/27/2025
Building Final Inspection Partial Pass 2/21/2025 (8:00 - 10:00) 2/21/2025 (AM) 02/27/2025
Building Final Inspection Partial Pass 2/26/2025 (8:00 - 10:00) 2/26/2025 (AM) 02/27/2025
Building Final Inspection Partial Pass 3/3/2025 (8:00 - 10:00) 3/3/2025 (AM) 03/03/2025
Corrections:


Miscellaneous/Other
Comment Only
03/03/2025
Went through 3rd floor units and electrical closet/room for the future final. all areas inspected at 3rd level comply with code... 2 decks need t be installed yet and contractor has them on the schedule for installation... approved

Lighting Inspection Passed 3/3/2025 (PM) 03/04/2025
Building Final Inspection Partial Pass 3/5/2025 (8:00 - 10:00) 3/5/2025 (AM) 03/05/2025
Corrections:


Miscellaneous/Other
Comment Only
03/05/2025
floors 1 and 2 for apartment units are approved for ongoing final.

Building Final Inspection Not Ready 3/7/2025 (8:00 - 10:00) 3/7/2025 (AM) 03/07/2025
Building Final Inspection Partial Pass 3/10/2025 (8:00 - 10:00) 3/10/2025 (AM) 03/11/2025
Corrections:


Miscellaneous/Other
Comment Only
03/11/2025
Inspected for the upcoming final.... Roof and guards... approved Garage with stripping, accessible parking and signage, Firestops, and exiting... approved 1st floor common areas... approved Items to be completed... 1) Exterior parking accessible unloading zones need signage installed 2) signage on gate to basement garage in stair 3) Installation of bollards in garage 4) lighting inspection to be performed by planning Testing of the C.O system in garage scheduled for 3/11.

Building Final Inspection Issue TCO 3/11/2025 (AM) 03/11/2025
Corrections:


Miscellaneous/Other
Comment Only
03/11/2025
Damper testing, EM lighting, Garage CO detection, Mag hold doors, were all tested and approved. This building meets the requirements for a TCO at this time. when the final inspection takes place at next inspection, these items are to be completed. 1) Fire inspection with the items left to follow up on. 2) bollards to be completed for installation. 3) storage fencing units to be completed. 4) lighting inspection for exterior lighting to be completed by planning if not already done. This building is approved for a TCO at this time.

Building Final Inspection Not Ready 3/21/2025 (8:00 - 10:00) 03/19/2025
Building Final Inspection Not Ready 3/24/2025 (8:00 - 10:00) 3/24/2025 (AM) 03/19/2025
Building Final Inspection Not Ready 3/26/2025 (8:00 - 10:00) 3/26/2025 (AM) 03/19/2025
Building Final Inspection Not Ready 3/28/2025 (8:00 - 10:00) 3/28/2025 (AM) 03/19/2025
Building Final Inspection Issue CO 04/01/2025
Corrections:


Miscellaneous/Other
Comment Only
04/01/2025
This building is completed and all inspections completed.. approved to issue Certificate of Occupancy.