PRBD202403846
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Inspection Final | Pending | |||
Landscaping Inspection | Pending | 5/31/2025 | ||
Framing Inspection | Not Ready | 7/29/2024 (8:00 - 10:00) | 7/29/2024 (AM) | 07/29/2024 |
Framing not ready, | ||||
Corrections:
Miscellaneous/Other
Comment Only
07/29/2024
Framing not ready.
|
||||
Framing Inspection | Partial Pass | 7/31/2024 (8:00 - 10:00) | 7/31/2024 (AM) | 07/31/2024 |
Framing, prefabricated wall panels, except elevator shaft, and others. Passed. Partial pass for ongoing inspections. | ||||
Corrections:
Miscellaneous/Other
Comment Only
07/31/2024
Framing inspection, prefabricated wall panels. Passed, Partial pass for ongoing work.
|
||||
Framing Inspection | Partial Pass | 8/2/2024 (8:00 - 10:00) | 8/2/2024 (AM) | 08/02/2024 |
Framing partial pass. Panelized walls, constructed in truss plant. | ||||
Corrections:
Miscellaneous/Other
Comment Only
08/02/2024
Framing progress, panelized in truss plant. PARTIAL PASS.
|
||||
Framing Inspection | Partial Pass | 8/5/2024 (8:00 - 10:00) | 8/5/2024 (AM) | 08/05/2024 |
Framing progress inspection Passed. (Partial pass for ongoing inspections.) | ||||
Corrections:
Miscellaneous/Other
Comment Only
08/05/2024
|
||||
Miscellaneous/Other
Comment Only
08/05/2024
(Framing inspection passed) partial pass status for ongoing inspections.
|
||||
Framing Inspection | Partial Pass | 8/7/2024 (8:00 - 10:00) | 8/7/2024 (AM) | 08/07/2024 |
Progress framing. level 1, Passed. | ||||
Corrections:
Miscellaneous/Other
Comment Only
08/07/2024
Progress framing , floor 1. Passed.
|
||||
Framing Inspection | Partial Pass | 8/9/2024 (8:00 - 10:00) | 8/9/2024 (AM) | 08/09/2024 |
Framing progress inspection, Partial pass. Ongoing progress inspections. | ||||
Corrections:
Miscellaneous/Other
Comment Only
08/09/2024
Progress Framing inspections, PARTIAL PASS, ONGOING INSPECTIONS.
|
||||
Framing Inspection | Passed | 8/12/2024 (8:00 - 10:00) | 8/12/2024 (AM) | 08/12/2024 |
Framing inspection, ongoing. Passed. | ||||
Corrections:
Miscellaneous/Other
Comment Only
08/12/2024
Framing inspection passed, ongoing inspections. PARTIAL PASS
|
||||
Framing Inspection | Partial Pass | 8/19/2024 (8:00 - 10:00) | 8/19/2024 (AM) | 08/19/2024 |
Ongoing framing inspections. PASSED. | ||||
Corrections:
Miscellaneous/Other
Comment Only
08/19/2024
On going; Framing, PARTIAL PASS.
|
||||
Framing Inspection | Partial Pass | 8/21/2024 (8:00 - 10:00) | 8/21/2024 (AM) | 08/21/2024 |
Framing for prefabricated wall sections, | ||||
Corrections:
Miscellaneous/Other
Comment Only
08/21/2024
Framing ; for prefabricated walls with gypsum sheeting, from truss plant.
( Ongoing. Partial pass. )
|
||||
Framing Inspection | Partial Pass | 8/23/2024 (8:00 - 10:00) | 8/23/2024 (AM) | 08/23/2024 |
Framing progress inspection. Partial pass. Ongoing. | ||||
Corrections:
Miscellaneous/Other
Comment Only
08/23/2024
Progress . Framing partial Pass, ongoing.
|
||||
Framing Inspection | Partial Pass | 8/26/2024 (8:00 - 10:00) | 8/26/2024 (AM) | 08/27/2024 |
Ongoing framing for prefabricated wall panels, PASSED. | ||||
Corrections:
Miscellaneous/Other
Comment Only
08/27/2024
FRAMING, Prefabricated WALL PANELS.Partial pass ongoing.
|
||||
Framing Inspection | Partial Pass | 8/28/2024 (8:00 - 10:00) | 8/28/2024 (AM) | 08/28/2024 |
Framing; Progress inspection passed. Note PARTIAL PASS for ongoing inspections. | ||||
Corrections:
Miscellaneous/Other
Comment Only
08/28/2024
Framing: Progress inspection. Passed. Partial pass status for ongoing inspections.
|
||||
Framing Inspection | Partial Pass | 8/30/2024 (8:00 - 10:00) | 8/30/2024 (AM) | 09/03/2024 |
Progress Framing inspection. Partial pass. Ongoing. | ||||
Corrections:
Miscellaneous/Other
Comment Only
09/03/2024
Progress framing inspection. Ongoing inspections. Partial pass.
|
||||
Framing Inspection | Partial Pass | 9/4/2024 (8:00 - 10:00) | 9/4/2024 (AM) | 09/04/2024 |
Progress framing, floor 1, A. Tyvek and setting windows. Passed. ( Ongoing partial pass status.) | ||||
Corrections:
Miscellaneous/Other
Comment Only
09/04/2024
First floor framing, housewrap, and installing windows. Passed.
Partial pass for ongoing work.
|
||||
Follow-up Inspection | Passed w/ Conditions | 09/05/2024 | ||
Framing Inspection | Partial Pass | 9/6/2024 (8:00 - 10:00) | 9/6/2024 (AM) | 09/06/2024 |
Framing, partial pass, for ongoing inspections | ||||
Framing Inspection | Partial Pass | 9/9/2024 (8:00 - 10:00) | 9/9/2024 (AM) | 09/09/2024 |
Progress inspection framing, Passed. Partial pass for ongoing work | ||||
Corrections:
Miscellaneous/Other
Comment Only
09/09/2024
Framing progress Inspection, Passed. partial pass for ongoing work.
|
||||
Framing Inspection | Partial Pass | 9/11/2024 (8:00 - 10:00) | 9/11/2024 (AM) | 09/11/2024 |
Progress Framing. PASSED. | ||||
Corrections:
Miscellaneous/Other
Comment Only
09/11/2024
Progress framing, PASSED.
|
||||
Framing Inspection | Partial Pass | 9/13/2024 (8:00 - 10:00) | 9/13/2024 (AM) | 09/13/2024 |
Framing inspection, partial pass, ongoing. | ||||
Framing Inspection | Partial Pass | 9/16/2024 (8:00 - 10:00) | 9/16/2024 (AM) | 09/16/2024 |
Framing, progress inspection, passed, PARTIAL PASS FOR ONGOING INSPECTIONS. | ||||
Framing Inspection | Partial Pass | 9/18/2024 (8:00 - 10:00) | 9/18/2024 (AM) | 09/18/2024 |
Progress, start of elevator shaft fire rated assembly. (2 layers of FRP( Fire rated ply wood. Note, off set all seams, ( both horizontal and vertical ) | ||||
Corrections:
Miscellaneous/Other
Comment Only
09/18/2024
Start of 2 layers of (fire rated plywood) NOTE, OFF SET ALL SEAMS.
|
||||
Framing Inspection | Partial Pass | 9/20/2024 (8:00 - 10:00) | 09/18/2024 | |
Ongoing inspections passed. Partial pass for additional inspections. | ||||
Framing Inspection | Partial Pass | 9/23/2024 (8:00 - 10:00) | 9/23/2024 (AM) | 09/23/2024 |
Progress Framing. PASSED. PARTIAL PASS FOR ONGOING INSPECTIONS. | ||||
Fire Rough-in Inspection | Partial Pass | 09/23/2024 | ||
Verified standpipes were installed in both stairwells. Pre-incident tour with FM5,C4, E4 (A shift). | ||||
Framing Inspection | Partial Pass | 9/25/2024 (8:00 - 10:00) | 9/25/2024 (AM) | 09/25/2024 |
Framing ; Progress inspection PASSED. PARTIAL PASS FOR ONGOING INSPECTIONS. | ||||
Framing Inspection | Partial Pass | 9/27/2024 (8:00 - 10:00) | 9/27/2024 (AM) | 09/27/2024 |
Framing inspection, Passed. (Partial pass status for ongoing inspections.) | ||||
Framing Inspection | Partial Pass | 9/30/2024 (8:00 - 10:00) | 9/30/2024 (AM) | 09/30/2024 |
Framing; floors 1-4. Passed. (Partial pass for ongoing framing inspections.) | ||||
Progress Inspection | Partial Pass | 10/2/2024 (8:00 - 10:00) | 10/2/2024 (AM) | 10/02/2024 |
Ongoing inspections. | ||||
Progress Inspection | Partial Pass | 10/4/2024 (8:00 - 10:00) | 10/4/2024 (AM) | 10/04/2024 |
Framing concepts, passed. Note partial pass for ongoing inspections. | ||||
Progress Inspection | Partial Pass | 10/7/2024 (8:00 - 10:00) | 10/7/2024 (AM) | 10/07/2024 |
Progress Framing, PASSED. (Partial pass for on going inspections.) | ||||
Progress Inspection | Partial Pass | 10/9/2024 (8:00 - 3:30) | 10/9/2024 (AM) | 10/09/2024 |
4th floor fire caulk. East to west.(Passed.) partial pass for ongoing inspections | ||||
Progress Inspection | Passed | 10/11/2024 (8:00 - 10:00) | 10/11/2024 (AM) | 10/11/2024 |
Framing firecaulk (4th floor east to west ) PASSED. (PARTIAL PASS for ongoing inspections. | ||||
Progress Inspection | Partial Pass | 10/14/2024 (8:00 - 10:00) | 10/14/2024 (AM) | 10/14/2024 |
Insulation; exterior wall with vapor barrier, and interior walls for sound insulation.PASSED. (Partial pass status for ongoing insulation inspections..) | ||||
Corrections:
Miscellaneous/Other
Comment Only
10/14/2024
3rd floor: (Interior; wall Insulation, ) (exterior wall insulation with poly vapor barrier. PASSED.
|
||||
Progress Inspection | Passed | 10/16/2024 (8:00 - 10:00) | 10/16/2024 (AM) | 10/16/2024 |
4 th floor, framing and firecaulk. Completed. Passed. (Partial pass for ongoing inspections ) | ||||
Progress Inspection | Partial Pass | 10/18/2024 (8:00 - 10:00) | 10/18/2024 (AM) | 10/21/2024 |
General walk thru, all trades, passed. Partial pass for on going inspections. | ||||
Progress Inspection | Passed | 10/21/2024 (8:00 - 10:00) | 10/21/2024 (AM) | 10/21/2024 |
On going | ||||
Progress Inspection | Partial Pass | 10/23/2024 (8:00 - 10:00) | 10/23/2024 (AM) | 10/23/2024 |
Framing and fire caulk for living units. Passed. (Partial pass status for ongoing inspections.) | ||||
Corrections:
Miscellaneous/Other
Comment Only
10/23/2024
Framing and fire caulk inspections. Passed.
|
||||
Progress Inspection | Partial Pass | 10/25/2024 (8:00 - 10:00) | 10/25/2024 (AM) | 10/25/2024 |
Progress Framing, passed. Partial pass for ongoing inspections. | ||||
Progress Inspection | Partial Pass | 10/28/2024 (8:00 - 10:00) | 10/28/2024 (AM) | 10/28/2024 |
Insulation passed | ||||
Corrections:
Miscellaneous/Other
Comment Only
10/28/2024
Insulation passed. Partial pass for on going inspections.
|
||||
Progress Inspection | Partial Pass | 10/30/2024 (8:00 - 10:00) | 10/30/2024 (AM) | 10/30/2024 |
Framing and firecaulk inspection. Passed. (Partial pass for ongolng inspections) | ||||
Progress Inspection | Passed | 11/1/2024 (8:00 - 10:00) | 11/1/2024 (AM) | 11/01/2024 |
Progress Inspection | Partial Pass | 11/4/2024 (8:00 - 10:00) | 11/4/2024 (AM) | 11/04/2024 |
Progress framing, not ready. | ||||
Corrections:
Miscellaneous/Other
Comment Only
11/04/2024
Not ready. Interior framing and fire caulking.
|
||||
Progress Inspection | Partial Pass | 11/5/2024 (Afternoon) | 11/5/2024 (PM) | 11/05/2024 |
2nd floor. Framing and fire caulk. Passed. (Partial pass status for ongoing inspections.) | ||||
Progress Inspection | Partial Pass | 11/6/2024 (8:00 - 10:00) | 11/6/2024 (AM) | 11/06/2024 |
2nd floor, framing and firecaulk inspection. Passed.(Partial pass status for additional inspections.) | ||||
Progress Inspection | Partial Pass | 11/8/2024 (8:00 - 10:00) | 11/8/2024 (AM) | 11/08/2024 |
2nd floor. Framing and firecaulk.PASSED. (PARTIAL PASS FOR ONGOING inspections.) | ||||
Progress Inspection | Partial Pass | 11/13/2024 (8:00 - 10:00) | 11/13/2024 (AM) | 11/13/2024 |
Exterior building Stucco meeting with Olympic stucco. Passed. Partial pass for ongoing inspections. | ||||
Corrections:
Miscellaneous/Other
Comment Only
11/13/2024
Stucco meeting on site, with Olympic stucco.passed.
( Partial pass for ongoing inspections)
|
||||
Progress Inspection | Partial Pass | 11/15/2024 (8:00 - 10:00) | 11/15/2024 (AM) | 11/15/2024 |
Ongoing inspections, exterior stucco progress inspections. PASSED. | ||||
Progress Inspection | Partial Pass | 11/18/2024 (8:00 - 10:00) | 11/18/2024 (AM) | 11/18/2024 |
1st floor fire caulk - ceiling only. ( 1st Floor, floor fire caulk from parking ramp below.) | ||||
Progress Inspection | Partial Pass | 11/19/2024 | ||
Progress, stucco, firecaulk, framing. | ||||
Progress Inspection | Not Ready | 11/20/2024 (8:00 - 10:00) | 11/20/2024 (AM) | 11/20/2024 |
Please schedule framing and insulation, for Friday November 21. 8;00 AM. | ||||
Corrections:
Miscellaneous/Other
Comment Only
11/20/2024
Framing and Insulation. Schedule for Thursday NOVEMBER 21, 2024.
|
||||
Progress Inspection | Partial Pass | 11/22/2024 (8:00 - 10:00) | 11/22/2024 (AM) | 11/22/2024 |
Insulation-vapor barier. Passed. ( Partial pass for ongoing inspections.) | ||||
Progress Inspection | Partial Pass | 11/25/2024 (8:00 - 10:00) | 11/25/2024 (AM) | 11/25/2024 |
Stucco exterior | ||||
Corrections:
Miscellaneous/Other
Comment Only
11/25/2024
Exterior stucco, partial pass. Ongoing.
|
||||
Progress Inspection | Partial Pass | 11/27/2024 (8:00 - 10:00) | 11/27/2024 (AM) | 11/27/2024 |
On going inspections. | ||||
Building Final Inspection | Partial Pass | 2/24/2025 (8:00 - 10:00) | 2/24/2025 (AM) | 02/27/2025 |
Building Final Inspection | Partial Pass | 2/21/2025 (8:00 - 10:00) | 2/21/2025 (AM) | 02/27/2025 |
Building Final Inspection | Partial Pass | 2/26/2025 (8:00 - 10:00) | 2/26/2025 (AM) | 02/27/2025 |
Building Final Inspection | Partial Pass | 3/3/2025 (8:00 - 10:00) | 3/3/2025 (AM) | 03/03/2025 |
Corrections:
Miscellaneous/Other
Comment Only
03/03/2025
Went through 3rd floor units and electrical closet/room for the future final. all areas inspected at 3rd level comply with code... 2 decks need t be installed yet and contractor has them on the schedule for installation... approved
|
||||
Lighting Inspection | Passed | 3/3/2025 (PM) | 03/04/2025 | |
Building Final Inspection | Partial Pass | 3/5/2025 (8:00 - 10:00) | 3/5/2025 (AM) | 03/05/2025 |
Corrections:
Miscellaneous/Other
Comment Only
03/05/2025
floors 1 and 2 for apartment units are approved for ongoing final.
|
||||
Building Final Inspection | Not Ready | 3/7/2025 (8:00 - 10:00) | 3/7/2025 (AM) | 03/07/2025 |
Building Final Inspection | Partial Pass | 3/10/2025 (8:00 - 10:00) | 3/10/2025 (AM) | 03/11/2025 |
Corrections:
Miscellaneous/Other
Comment Only
03/11/2025
Inspected for the upcoming final....
Roof and guards... approved
Garage with stripping, accessible parking and signage, Firestops, and exiting... approved
1st floor common areas... approved
Items to be completed...
1) Exterior parking accessible unloading zones need signage installed
2) signage on gate to basement garage in stair
3) Installation of bollards in garage
4) lighting inspection to be performed by planning
Testing of the C.O system in garage scheduled for 3/11.
|
||||
Building Final Inspection | Issue TCO | 3/11/2025 (AM) | 03/11/2025 | |
Corrections:
Miscellaneous/Other
Comment Only
03/11/2025
Damper testing, EM lighting, Garage CO detection, Mag hold doors, were all tested and approved.
This building meets the requirements for a TCO at this time.
when the final inspection takes place at next inspection, these items are to be completed.
1) Fire inspection with the items left to follow up on.
2) bollards to be completed for installation.
3) storage fencing units to be completed.
4) lighting inspection for exterior lighting to be completed by planning if not already done.
This building is approved for a TCO at this time.
|
||||
Building Final Inspection | Not Ready | 3/21/2025 (8:00 - 10:00) | 03/19/2025 | |
Building Final Inspection | Not Ready | 3/24/2025 (8:00 - 10:00) | 3/24/2025 (AM) | 03/19/2025 |
Building Final Inspection | Not Ready | 3/26/2025 (8:00 - 10:00) | 3/26/2025 (AM) | 03/19/2025 |
Building Final Inspection | Not Ready | 3/28/2025 (8:00 - 10:00) | 3/28/2025 (AM) | 03/19/2025 |
Building Final Inspection | Issue CO | 04/01/2025 | ||
Corrections:
Miscellaneous/Other
Comment Only
04/01/2025
This building is completed and all inspections completed.. approved to issue Certificate of Occupancy.
|