PRBD202404560
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Building Final Inspection | Pending | |||
| Drain Tile Inspection | Passed | 12/9/2024 (10:00 - 12:00) | 12/9/2024 (AM) | 12/09/2024 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/09/2024
Waterproofing, insulation, and draintile around elevator pits... approved
|
||||
| Framing Inspection | Passed | 3/18/2025 (8:00 - 10:00) | 3/18/2025 (AM) | 03/18/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/18/2025
Outer gupsum layers for west stair of 1st level... approved
|
||||
| Framing Inspection | Passed | 3/27/2025 (2:30 - 3:30) | 3/27/2025 (PM) | 03/27/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/27/2025
Second level west stair and shaft, first outer layer of gypsum approved.
|
||||
| Framing Inspection | Passed | 4/8/2025 (12:30 - 2:30) | 4/8/2025 (PM) | 04/08/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/08/2025
2nd level east stair, and mechanical shaft outer first layer of gypsum...approved.
Water proofing and foundation insulation at north side foundation ... approved.
Radon system installed in garage and first section of slab on grade poly at east end... approved
|
||||
| Progress Inspection | Passed | 4/17/2025 (12:30 - 2:30) | 4/17/2025 (PM) | 04/17/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/17/2025
Level three stair shafts and mechanical shafts, first layer of gypsum approved on the outer walls.
Slab on grade poly and lower garage. Approved.
|
||||
| Framing Inspection | Passed | 5/1/2025 (12:30 - 2:30) | 5/1/2025 (PM) | 05/01/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/01/2025
4th floor shaft walls outer gypsum layer for both mechanical and stair shafts... approved
|
||||
| Progress Inspection | Passed | 5/19/2025 (10:00 - 12:00) | 5/19/2025 (AM) | 05/19/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/19/2025
First layer of outer gypsum at Mechanical shafts and stairways of level 5... approved
|
||||
| Framing Inspection | Passed | 6/2/2025 (8:00 - 10:00) | 6/2/2025 (AM) | 06/02/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/02/2025
Progress inspection of the framing and already installed sheathing.
Framing is still ongoing, sheathing is fastened correctly and the correct sheathing as per the plan design. Ok to complete housewrap.
|
||||
| Insulation Inspection | Passed | 6/12/2025 (10:00 - 12:00) | 6/12/2025 (AM) | 06/12/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/12/2025
Insulation and gypsum shear wall at tub backs of units on 4th and 5th floors... approved.
5th floor Trash chute insulation and elevator above roof overrun insulation/poly... approved
|
||||
| Insulation Inspection | Passed | 6/13/2025 (8:00 - 10:00) | 6/13/2025 (AM) | 06/13/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/13/2025
Shear wall at tub backs of floors 1-3... approved
|
||||
| Progress Inspection | Passed | 6/17/2025 (7:00 - 8:00) | 6/17/2025 (AM) | 06/17/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/17/2025
Framing inspection of shafts listed...
Floors 1-5, mechanical, elevator, and trash shaft... approved
Elevator shafts on 5th floor to have fire caulking installed at top plate penetrations and inspected prior to covering. All holes in top and bottom plates to either be fire caulked if wiring or piping is in the holes, or blocked with a cleated stud if holes are not for any use.
|
||||
| Framing Inspection | Passed | 6/18/2025 (12:30 - 2:30) | 6/18/2025 (PM) | 06/18/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/18/2025
Firestops in shafts,( mechanical, trash, and elevator) is complete. Ok to insulate and first layer of gypsum. Call for inspection of gypsum prior to installation of second layer.
Ok to insulate the in floor sections of party walls at units on 4&5 and outside above ceiling of perimeter walls of 5th.
|
||||
| Progress Inspection | Passed | 6/20/2025 (12:30 - 2:30) | 6/20/2025 (PM) | 06/20/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/20/2025
Consult with contractor... ok to pre-rock the steel studded framing down from slab 4 ft to allow for trades to run all their plumbing and hvac. Approved to temporarily close walls on interior of retail space for use as a site office.
|
||||
| Framing Inspection | Passed | 6/24/2025 (8:00 - 10:00) | 6/24/2025 (AM) | 06/24/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/24/2025
Framing and firestops of fifth floor area B.
First layer of shaft ( mechanical, trash, and elevator) .
Mock unit of fifth floor.
Approved
|
||||
| Insulation Inspection | Passed | 6/25/2025 (2:30 - 3:30) | 6/25/2025 (PM) | 06/25/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/25/2025
5th floor mock unit insulation and vapor barrier... approved
|
||||
| Insulation Inspection | Not Ready | 6/26/2025 (8:00 - 10:00) | 6/26/2025 (AM) | 06/26/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/26/2025
Contractor canceled inspection
|
||||
| Framing Inspection | Passed | 6/30/2025 (12:30 - 2:30) | 6/30/2025 (PM) | 06/30/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/30/2025
Framing and firestops at 5th floor area A.... approved
|
||||
| Framing Inspection | Not Ready | 7/1/2025 (12:30 - 2:30) | 7/1/2025 (PM) | 07/01/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/01/2025
Not ready for framing and fire stop inspection
|
||||
| Insulation Inspection | Passed | 7/1/2025 (12:30 - 2:30) | 7/1/2025 (PM) | 07/01/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/01/2025
Insulation/vapor barrier of fifth floor area B... approved
|
||||
| Progress Inspection | Not Ready | 7/2/2025 (12:30 - 2:30) | 7/2/2025 (PM) | 07/02/2025 |
| Same day cancellation | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
07/02/2025
Inspection canceled by contractor
|
||||
| Progress Inspection | Passed | 7/3/2025 (10:00 - 12:00) | 7/3/2025 (AM) | 07/03/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/03/2025
5th floor area B, first layer of gypsum on rated ceiling... approved
|
||||
| Progress Inspection | Passed | 7/7/2025 (10:00 - 12:00) | 7/7/2025 (AM) | 07/07/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/07/2025
4th floor area B framing and firestops in units and hallway... approved
5th floor aea B gypsum shear walls and insulation at 2 hr bearing walls of area A... approved
Note... fire collar needed on radon pipe of 4th floor area B location.
|
||||
| Progress Inspection | Passed | 7/8/2025 (12:30 - 2:30) | 7/8/2025 (PM) | 07/08/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/08/2025
Insulation/vapor barrier of exterior walls on 5th floor area A... approved
|
||||
| Progress Inspection | Passed | 7/9/2025 (2:30 - 3:30) | 7/9/2025 (PM) | 07/09/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/09/2025
Exterior wall insulation/vapor barrier of 4th floor area B... approved
|
||||
| Progress Inspection | Passed | 07/10/2025 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
07/10/2025
5th floor area A , first layer of gypsum at rated ceilings.... approved
|
||||
| Progress Inspection | Passed | 7/14/2025 (10:00 - 12:00) | 7/14/2025 (AM) | 07/14/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/14/2025
5th floor area A shear walls... approved
|
||||
| Framing Inspection | Passed | 7/15/2025 (7:00 - 8:00) | 7/15/2025 (AM) | 07/15/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/15/2025
4th floor wing A, framing and fire stops... approved
|
||||
| Progress Inspection | Not Ready | 7/16/2025 (12:30 - 2:30) | 7/16/2025 (PM) | 07/16/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/16/2025
Inspection Canceled by contractor not ready
|
||||
| Housewrap Inspection | Passed | 07/16/2025 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
07/16/2025
All house wrap approved
|
||||
| Progress Inspection | Passed | 07/16/2025 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
07/16/2025
Insulation/vapor barrier at exterior walls of 4th floor area A.... approved
|
||||
| Progress Inspection | Passed | 7/18/2025 (2:30 - 3:30) | 7/18/2025 (PM) | 07/18/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/18/2025
Fourth floor area A, shear walls at half of the "A wing" units are approved and can be covered.
Bearing wall unit on west end approved to cover with second layer of gypsum.
|
||||
| Progress Inspection | Passed | 7/22/2025 (8:00 - 10:00) | 7/22/2025 (AM) | 07/22/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/22/2025
Framing and fire stops of 3rd floor area B... approved
|
||||
| Progress Inspection | Passed | 7/24/2025 (8:00 - 10:00) | 7/24/2025 (AM) | 07/24/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/24/2025
East and west stairwell framing from 3rd floor to 5 th floor.
Insulation/vapor barrier in units of 3rd floor area B.
Shear wall of units on 4th floor area B.
Approved
|
||||
| Progress Inspection | Passed | 7/29/2025 (8:00 - 10:00) | 7/29/2025 (AM) | 07/29/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/29/2025
Framing and fire stops of 3rd floor area A... approved
|
||||
| Progress Inspection | Passed | 8/1/2025 (8:00 - 10:00) | 8/1/2025 (AM) | 08/01/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/01/2025
Insulation/ vapor barrier of 3rd floor area A... approved
|
||||
| Progress Inspection | Passed | 8/4/2025 (2:30 - 3:30) | 8/4/2025 (PM) | 08/04/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/04/2025
Framing and firestops of hallways, misc rooms and units of area 2A... approved
|
||||
| Progress Inspection | Passed | 8/18/2025 (12:30 - 2:30) | 08/07/2025 | |
|
Corrections:
Miscellaneous/Other
Comment Only
08/07/2025
5 units of shear walls at area 3B.
Insulation/vapor barrier of units in area 2B
Approved
|
||||
| Progress Inspection | Passed | 8/12/2025 (8:00 - 10:00) | 8/12/2025 (AM) | 08/12/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/12/2025
First layer of gypsum at west stair... approved
2nd floor area A framing and fire stops.... approved
|
||||
| Drain Tile Inspection | Passed | 08/15/2025 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
08/15/2025
All draintile completed around perimeter of building
|
||||
| Insulation Inspection | Passed | 08/15/2025 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
08/15/2025
Exterior wall insulation/vapor barrier for floor 2, area A.... approved.
Shear walls for 2nd floor units area B... approved
|
||||
| Progress Inspection | Partial Pass | 8/18/2025 (12:30 - 2:30) | 8/18/2025 (PM) | 08/18/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
08/18/2025
Corrections that need to be reinspected....
1) units 114 & 117 need firestops at the hvac ducting, and gas piping , and condensate piping.
Units 116, 121, & 127 have empty sleevs that need to be filled with full pack mineral wool or concrete.
The remaining units, hallway and other utility rooms of that 1st foor area B are approved for framing and firestops.
|
||||
| Framing Inspection | Passed | 08/19/2025 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
08/19/2025
Framing and fire stops on all units of first floor area B are approved, corrections have been completed.
|
||||
| Progress Inspection | Passed | 8/21/2025 (12:30 - 2:30) | 8/21/2025 (PM) | 08/21/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/21/2025
Shear walls on half of units in area A 2nd floor, and insulation/ vapor barrier of units in area B first floor... approved
|
||||
| Progress Inspection | Passed | 8/25/2025 (8:00 - 10:00) | 8/25/2025 (AM) | 08/25/2025 |
|
Corrections:
Miscellaneous/Other
Resolved
08/25/2025
Corrections that need to be reinspected....
1) units 114 & 117 need firestops at the hvac ducting, and gas piping , and condensate piping.
Units 116, 121, & 127 have empty sleevs that need to be filled with full pack mineral wool or concrete.
The remaining units, hallway and other utility rooms of that 1st foor area B are approved for framing and firestops.
|
||||
|
Miscellaneous/Other
Comment Only
08/25/2025
First floor area A... framing and firestops... approved
|
||||
| Progress Inspection | Not Ready | 8/26/2025 (10:00 - 12:00) | 8/26/2025 (AM) | 08/26/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/26/2025
Viewed the 5th floor trash room front shaft wall framing.... gave contractor a list of corrections and no covering until its been rechecked and approved.
The elevator lobby ceiling of 5th floor has been framed and partially covered, contractor to remove covering so fire stops can be done and inspected.
|
||||
| Progress Inspection | Passed | 8/27/2025 (10:00 - 12:00) | 8/27/2025 (AM) | 08/27/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/27/2025
Insulation/vapor barrier at first floor area A... approved
Membrane fire stops at rated walls of units on 2nd and third floors... approved
|
||||
| Progress Inspection | Passed | 8/29/2025 (10:00 - 12:00) | 8/29/2025 (AM) | 08/29/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/29/2025
Exterior wall framing of the commons area only... ok to insulate.
Many corrections within the exterior walls of the common area, went over them with the contractor. Need to reinspect the framing and firestops within that space, no covering within the space... only the exterior walls.
|
||||
| Progress Inspection | Passed | 9/2/2025 (8:00 - 10:00) | 9/2/2025 (AM) | 09/02/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/02/2025
Drywall shear walls of first floor area B... approved
|
||||
| Progress Inspection | Not Ready | 9/3/2025 (12:30 - 2:30) | 9/3/2025 (PM) | 09/03/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/03/2025
Went over items of corrections with the commons area with contractor... reinspection of this area to be set up when ready for inspection.
|
||||
| Progress Inspection | Passed | 9/4/2025 (12:30 - 2:30) | 9/4/2025 (PM) | 09/04/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/04/2025
Exterior wall installation/vapor barrier in common area walls. Approved Framing of exterior walls in Mercantile area. Approved.
|
||||
| Progress Inspection | Not Ready | 9/8/2025 (7:00 - 8:00) | 9/8/2025 (AM) | 09/08/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/08/2025
Inspection was for the ceilling framing in commons area. The Armstrong light gage ceiling system is proprietary to holding gypsum board only as per the manufacture specs and what is listed in the ICC- ES report. Contractor and or Design team to come up with another way to support any items as blocking or other items that will be suspended from this system other than lighting or strobes.
|
||||
| Progress Inspection | Passed | 9/9/2025 (7:00 - 8:00) | 9/9/2025 (AM) | 09/09/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/09/2025
Commons area... all through floor fire stops approved, ok to cover walls only.
Fireblock at fire places with the wall framing, leave these areas open for inspection.
|
||||
| Progress Inspection | Not Ready | 9/11/2025 (12:30 - 2:30) | 9/11/2025 (PM) | 09/11/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/11/2025
Viewed the elevator front shaft wall on first floor. Shaft liner is not properly installed as the manufacturer requires for use with the tabs in the C/H studs.
Went over corrections with installers and contractor.
Contractor also wants to hang an ACT ceiling off the Armstrong light gage short span framing system. Contractor needs to get manufacture approval to do so, or figure a way to independently support the ACT ceiling from the short span ceiling.
|
||||
| Progress Inspection | Not Ready | 9/12/2025 (10:00 - 12:00) | 9/12/2025 (AM) | 09/12/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/12/2025
Nothing ready for today's inspection
|
||||
| Progress Inspection | Not Ready | 9/17/2025 (12:30 - 2:30) | 9/17/2025 (PM) | 09/17/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/17/2025
Many corrections for the common area.... rated walls need to be gypsum covered to full wall height, firestops to be completed, ceiling framing with Armstrong grid system to be installed per the system requirements... no other backing or supporting from the Armstrong system is allowed per the manufacture specs without installation of the special pieces used with this system for supports, and then it still is limited on what can be supported.
Not ready for inspection at this time.
|
||||
| Progress Inspection | Passed w/ Conditions | 9/19/2025 (12:30 - 2:30) | 9/19/2025 (PM) | 09/19/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
09/19/2025
Corrections in common area... complete Firestops at rated walls above ceiling.
Dampers at rated walls need to have the metal angles installed, not fire caulking.
Complete gypsum at rated back wall of unit that buts up to the wall of common area.
Approved to start covering the common area walls discussed with contractor that dont need to be rechecked.
|
||||
| Progress Inspection | Passed | 9/22/2025 (8:00 - 10:00) | 9/22/2025 (AM) | 09/22/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/22/2025
Rebar at north side of building of the drive lane above the PT slab... approved.
Corrections with fire stops are being addressed, the collars are being install at the dampers.
|
||||
| Progress Inspection | Passed | 9/24/2025 (12:30 - 2:30) | 9/24/2025 (PM) | 09/24/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/24/2025
Mechanical trash and elevator shaft wall infill, (framing and shaft liner and fire stops) .... approved for all floors and shafts.
|
||||
| Progress Inspection | Passed | 10/1/2025 (12:30 - 2:30) | 10/1/2025 (PM) | 10/01/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/01/2025
All shaft front walls are completed and code compliant, floors 1-5
|
||||
| Progress Inspection | Passed | 11/20/2025 (10:00 - 12:00) | 11/20/2025 (AM) | 11/20/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/20/2025
Progress of building finals ... floors 4 & 5 are completed and units and accessory rooms are approved for final.
|
||||
| Landscaping Inspection | Passed | 11/20/2025 | ||
| Progress Inspection | Passed | 12/4/2025 (8:00 - 10:00) | 12/4/2025 (AM) | 12/04/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/04/2025
Progress of building final... floors 2&3 approved for final.
|
||||
| Progress Inspection | Partial Pass | 12/4/2025 (2:30 - 3:30) | 12/4/2025 (PM) | 12/04/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/04/2025
Garage....
1) loose bollards to be fastened down, where bolts didn't grip, epoxy may be needed to set bolts.
2) complete the touch up of the fire protection onto foam
3) bollards will be needed where EV chargers are to be installed.
This is a partial pass for garage, with a follow up inspection needed.
|
||||
| Progress Inspection | Not Ready | 12/11/2025 (10:00 - 12:00) | 12/11/2025 (AM) | 12/11/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/11/2025
Testing of dampers with fire alarm panel and CO2/ NO system in gargae... not ready. Set systems up and pretest prior to setting up inspection with building and fire inspection.
|
||||
| Lighting Inspection | Passed | 12/11/2025 | ||
| Progress Inspection | Passed | 12/12/2025 (8:00 - 10:00) | 12/12/2025 (AM) | 12/12/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/12/2025
Garage... all firestops, bollards where needed, and clearance heights, protected coating on spray foam insulation...approved.
1st floor units and common areas have been inspected and are approved for the upcoming final for building.
Note... trap wraps need to be installed in the common bathrooms, contractor has been made aware of this and will be rechecked at next inspection.
The retail space has been inspected for the future turnover and is currently a compliant shell space.
Items remaining for for inspection include...
1) signage to be installed where required
2) testing of the N/O system in garage
3) testing of the dampers on all levels
4) install of remaing items with in the common area such as,,,, guard/ handrails at stair, tread finishes, trap wraps to bath sinks, flooring at entry, other finishes.
5) Finals for all trades inspections to be called in.
|
||||
| Progress Inspection | Passed | 12/15/2025 (10:00 - 12:00) | 12/15/2025 (AM) | 12/15/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/15/2025
Testing of all dampers in building and CO2 system in garage are completed and approved
|
||||
| Progress Inspection | Passed w/ Conditions | 12/18/2025 (10:00 - 12:00) | 12/18/2025 (AM) | 12/18/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/18/2025
Corrections in garage with exit signage, will recheck at final.
Approved for Temporary occupancy, with contractor to finish up remaining trim work and finishes and corrections with fire inspection and building.
Temp occupancy approved.
|
||||
| Building Final Inspection | Issue TCO | 12/18/2025 | ||
|
Corrections:
Miscellaneous/Other
Carried Forward
12/18/2025
Corrections in garage with exit signage, will recheck at final.
Approved for Temporary occupancy, with contractor to finish up remaining trim work and finishes and corrections with fire inspection and building.
Temp occupancy approved
|
||||
| Building Final Inspection | Partial Pass | 12/23/2025 (12:30 - 2:30) | 12/23/2025 (PM) | 12/23/2025 |
|
Corrections:
Miscellaneous/Other
Resolved
12/23/2025
Corrections in garage with exit signage, will recheck at final.
Approved for Temporary occupancy, with contractor to finish up remaining trim work and finishes and corrections with fire inspection and building.
Temp occupancy approved
|
||||
|
Miscellaneous/Other
Comment Only
12/23/2025
Signage is completed, corrections in garage also completed. Contractor to complete any finishes, and remove debris, materials, and any tools not needed, and set up final inspection for the final CO.
This building is approved for Temporary Occupancy.
|
||||
| Building Final Inspection | Issue CO | 12/26/2025 (10:00 - 12:00) | 12/26/2025 (AM) | 12/26/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/26/2025
Approved for final and Certificate of Occupancy.
Contractor to complete the final clean of building, remove the tape from all N/O and C/O detectors in garage, and spin the hydrant head located at drive entry as requested by fire inspection... notify inspector when this is completed.
Building is compliant and is approved for occupancy.
|
||||
| Fire Inspection Final | Passed | 12/26/2025 (10:00 - 12:00) | 12/26/2025 (AM) | 12/26/2025 |