Permit Application Status

PRBD202404686


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202404686
Building
Permit(s) Issued
LTF REAL ESTATE COMPANY
New
Residential, multiple family
Storage, low hazard
New multi-family building, 208 units, 299,199 sq ft.
04/16/2024
09/17/2024
09/29/2026

Locations

Permits

Permit Number: PRBD202404686

Building
Issued
09/17/2024
09/29/2026

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Housewrap Inspection Pending
Lighting Inspection Pending
Fire Inspection Final Pending
Landscaping Inspection Pending
Follow-up Inspection Pending
Building Final Inspection Pending
Corrections:


Miscellaneous/Other
Outstanding
03/12/2026
1. Complete work on soffits over fifth floor decks at North and south ends. 2. Remove tape and obstructions from all rated doors and adjust closers as required for full operation. 3. Remove paint and tape from all rated door labels. 4. Deck guard rail in unit number 103 has 6 inch gap at wall. Correct to maximum 4 inch gap. 5. One penetration in electrical room wall on garage level missing fire caulk. 6. Need final fire approval. 7. Confirmed letter of approval by state for elevator, approved.

Progress Inspection Pending
Footing Inspection Passed 10/2/2024 (8:00 - 10:00) 10/2/2024 (AM) 10/03/2024
Corrections:


Miscellaneous/Other
Comment Only
10/03/2024
Perimeter footing inspection to include strip footings with rebar on exterior wall at East and north sides from column line M to column line 2 approved.

Footing Inspection Passed 10/4/2024 (12:30 - 2:30) 10/4/2024 (PM) 10/04/2024
Corrections:


Miscellaneous/Other
Comment Only
10/04/2024
Strip footing on grid A, from lines 1.7 to 8.7

Footing Inspection Partial Pass 10/7/2024 (12:30 - 2:30) 10/7/2024 (PM) 10/07/2024
Ongoing footing inspection, PASSED. Partial pass for ongoing foundation inspections.
Footing Inspection Not Ready 10/8/2024 (10:00 - 12:00) 10/8/2024 (AM) 10/08/2024
Footing Inspection Passed 10/9/2024 (10:00 - 12:00) 10/9/2024 (AM) 10/09/2024
Corrections:


Miscellaneous/Other
Comment Only
10/09/2024
11 pad footings in southeast area and strip footing along south wall approved.

Footing Inspection Passed 10/11/2024 (10:00 - 12:00) 10/11/2024 (AM) 10/11/2024
Corrections:


Miscellaneous/Other
Comment Only
10/11/2024
11 pad footings on column line B, one on column 11, three on column 10.2 approved. Strip footing on south wall on column line K approved.

Footing Inspection Passed 10/15/2024 (10:00 - 12:00) 10/15/2024 (AM) 10/14/2024
Corrections:


Miscellaneous/Other
Comment Only
10/14/2024
Total of 12 pad footings on column lines D, E and J-1. Approved.

Footing Inspection Passed 10/14/2024 (10:00 - 12:00) 10/14/2024 (AM) 10/15/2024
Corrections:


Miscellaneous/Other
Comment Only
10/15/2024
Pad footings for two elevator pits approved.

Footing Inspection Passed 10/16/2024 (10:00 - 12:00) 10/16/2024 (AM) 10/16/2024
Corrections:


Miscellaneous/Other
Comment Only
10/16/2024
Six pad footings on column line G and progress inspection of waterproofing of footings for 2 elevator pits. Approved.

Footing Inspection Passed 10/17/2024 (10:00 - 12:00) 10/17/2024 (AM) 10/17/2024
Corrections:


Miscellaneous/Other
Comment Only
10/17/2024
Five pad footings as per plan marked in field approved.

Footing Inspection Passed 10/18/2024 (2:30 - 3:30) 10/18/2024 (PM) 10/18/2024
Corrections:


Miscellaneous/Other
Comment Only
10/18/2024
Poured foundation walls between grids D to E.3 of both elevators.

Footing Inspection Passed 10/21/2024 (12:30 - 2:30) 10/21/2024 (PM) 10/21/2024
Corrections:


Miscellaneous/Other
Comment Only
10/21/2024
Pad footings on grid C, lines 5.3,6,6.7,7.3,8,8.8,10 Grid F, line8.7 Grid H, lines4.4,5,6,7,8,8.8

Footing Inspection Passed 10/22/2024 (10:00 - 12:00) 10/22/2024 (AM) 10/22/2024
Corrections:


Miscellaneous/Other
Comment Only
10/22/2024
Three pad footings on column line C and strip footing for West wall approved.

Footing Inspection Passed 10/23/2024 (10:00 - 12:00) 10/23/2024 (AM) 10/23/2024
Corrections:


Miscellaneous/Other
Comment Only
10/23/2024
10 pad footings per marked plan and one correction at Northwest corner, all approved.

Footing Inspection Passed 10/10/2024 (10:00 - 12:00) 10/10/2024 (AM) 10/24/2024
Corrections:


Miscellaneous/Other
Comment Only
10/24/2024
Remaining pad footings, including all on column line 2 approved.

Framing Inspection Not Ready 1/13/2025 (10:00 - 12:00) 1/13/2025 (AM) 01/13/2025
Framing Inspection Not Ready 1/17/2025 (10:00 - 12:00) 1/17/2025 (AM) 01/17/2025
Framing Inspection Not Ready 1/21/2025 (10:00 - 12:00) 1/21/2025 (AM) 01/21/2025
Framing Inspection Passed 1/22/2025 (10:00 - 12:00) 1/22/2025 (AM) 01/22/2025
Corrections:


Miscellaneous/Other
Comment Only
01/22/2025
Progress inspection of first floor, southeast stair shaft, framing, and gyp. bd., approved.

Framing Inspection Passed 1/23/2025 (10:00 - 12:00) 1/23/2025 (AM) 01/23/2025
Corrections:


Miscellaneous/Other
Comment Only
01/23/2025
Progress inspection of second layer on first floor of stair shaft at south east corner, approved.

Framing Inspection Passed 1/27/2025 (10:00 - 12:00) 1/27/2025 (AM) 01/27/2025
Corrections:


Miscellaneous/Other
Comment Only
01/27/2025
Progress inspection of shaft, framing, and sheet rock at North east stairwell, first floor, approved.

Framing Inspection Passed 2/3/2025 (10:00 - 12:00) 2/3/2025 (AM) 02/03/2025
Corrections:


Miscellaneous/Other
Comment Only
02/03/2025
Progress inspection of various first floor framing approved.

Framing Inspection Passed 2/5/2025 (10:00 - 12:00) 2/5/2025 (AM) 02/05/2025
Corrections:


Miscellaneous/Other
Comment Only
02/05/2025
Progress inspection of rated separation wall on first floor and first floor north west stairwell shaft approved.

Framing Inspection Passed 2/10/2025 (8:00 - 10:00) 2/10/2025 (AM) 02/10/2025
Corrections:


Miscellaneous/Other
Comment Only
02/10/2025
Progress inspection of framing and sheet rock on first floor, south west stair shaft approved.

Framing Inspection Passed 2/14/2025 (10:00 - 12:00) 2/14/2025 (AM) 02/14/2025
Corrections:


Miscellaneous/Other
Comment Only
02/14/2025
Progress inspection of framing and sheet rock at second floor, south east stairwell approved.

Framing Inspection Not Ready 2/20/2025 (10:00 - 12:00) 2/20/2025 (AM) 02/20/2025
Framing Inspection Not Ready 2/21/2025 (10:00 - 12:00) 2/21/2025 (AM) 02/21/2025
Corrections:


Miscellaneous/Other
Comment Only
02/21/2025
Inspection not needed, contractor was not ready for inspection.

Framing Inspection Not Ready 2/24/2025 (10:00 - 12:00) 2/24/2025 (AM) 02/24/2025
Corrections:


Miscellaneous/Other
Comment Only
02/24/2025
Not ready for inspection

Framing Inspection Passed 2/25/2025 (10:00 - 12:00) 2/25/2025 (AM) 02/25/2025
Corrections:


Miscellaneous/Other
Comment Only
02/25/2025
Progress inspection of rated separation wall on second floor approved. Reviewed details for structural attachment of decks to be installed at later date.

Framing Inspection Passed 2/27/2025 (10:00 - 12:00) 2/27/2025 (AM) 02/27/2025
Corrections:


Miscellaneous/Other
Comment Only
02/27/2025
Progress inspection of sheet rock on rated stairwell shaft at southwest corner, second floor approved.

Framing Inspection Passed 3/3/2025 (8:00 - 10:00) 3/3/2025 (AM) 03/03/2025
Corrections:


Miscellaneous/Other
Comment Only
03/03/2025
Reviewed with superintendent on site the clarification regarding blocking in walls being eliminated when sheet rock extends full height. OK to proceed.

Framing Inspection Passed 3/4/2025 (8:00 - 10:00) 3/4/2025 (AM) 03/04/2025
Corrections:


Miscellaneous/Other
Comment Only
03/04/2025
Progress inspection of sheetrock at third floor level of south east stairwell approved.

Framing Inspection Passed 3/7/2025 (10:00 - 12:00) 3/7/2025 (AM) 03/10/2025
Corrections:


Miscellaneous/Other
Comment Only
03/10/2025
Progress inspection of various rated shafts on north side of third floor approved.

Framing Inspection Not Ready 3/13/2025 (10:00 - 12:00) 3/13/2025 (AM) 03/13/2025
Framing Inspection Passed 3/18/2025 (8:00 - 10:00) 3/18/2025 (AM) 03/18/2025
Corrections:


Miscellaneous/Other
Comment Only
03/18/2025
Progress inspection of south east stairwell shaft at fourth floor approved. Progress inspection of separation role on third and fourth floor approved. Progress inspection of stair shafts at Northwest and southwest on third floor approved.

Framing Inspection Passed 3/24/2025 (8:00 - 10:00) 3/24/2025 (AM) 03/24/2025
Corrections:


Miscellaneous/Other
Comment Only
03/24/2025
Progress inspection of all four rated stairwell shafts at fourth floor level approved.

Framing Inspection Passed 3/26/2025 3/26/2025 (AM) 03/26/2025
Corrections:


Miscellaneous/Other
Comment Only
03/26/2025
Progress inspection of rated stairwell shafts on fourth floor, north west and southwest, approved. First progress inspection of sheer wall nailing on first floor approved.

Framing Inspection Passed 4/1/2025 (10:00 - 12:00) 4/1/2025 (AM) 04/01/2025
Corrections:


Miscellaneous/Other
Comment Only
04/01/2025
Progress inspection of framing, and sheet rock at south east stairwell, fifth level, approved.

Framing Inspection Passed 4/8/2025 (8:00 - 10:00) 4/8/2025 (AM) 04/08/2025
Corrections:


Miscellaneous/Other
Comment Only
04/08/2025
Progress framing, and sheetrock of two east stairwells at fifth floor level approved. Sheer wall blocking and nailing on first floor west wing approved. Sheer walls on first floor east wing not yet complete, to be inspected later.

Framing Inspection Passed 4/14/2025 (8:00 - 10:00) 4/14/2025 (AM) 04/14/2025
Corrections:


Miscellaneous/Other
Comment Only
04/14/2025
Remainder of sheer walls on first level approved.

Framing Inspection Passed 5/1/2025 (10:00 - 12:00) 5/1/2025 (AM) 05/01/2025
Corrections:


Miscellaneous/Other
Comment Only
05/01/2025
Progress inspection to review process of inspection of fire caulking, and sheer walls at locations requiring pre-rocking.

Framing Inspection Partial Pass 5/7/2025 (10:00 - 12:00) 5/7/2025 (AM) 05/06/2025
Corrections:


Miscellaneous/Other
Comment Only
05/06/2025
Progress inspection on fourth and fifth floors, east side in areas requiring pre-rocking in toilet rooms, partially approved. Areas requiring corrections can be followed up on additional progress inspections.

Framing Inspection Passed 5/6/2025 (10:00 - 12:00) 5/6/2025 (AM) 05/07/2025
Corrections:


Miscellaneous/Other
Comment Only
05/07/2025
Progress inspection of first, second and third floors of East wing for fire, caulking, and insulation of plumbing walls needing early sheet rock. Approved.

Framing Inspection Not Ready 5/8/2025 (10:00 - 12:00) 5/8/2025 (AM) 05/08/2025
Framing Inspection Passed 5/9/2025 (10:00 - 12:00) 5/9/2025 (AM) 05/09/2025
Corrections:


Miscellaneous/Other
Comment Only
05/09/2025
Progress inspection of fire, caulking, and insulation of plumbing walls in West Wing units approved as marked in field.

Framing Inspection Passed 5/12/2025 (10:00 - 12:00) 5/12/2025 (AM) 05/12/2025
Corrections:


Miscellaneous/Other
Comment Only
05/12/2025
Foundation walls for pool equipment, room, and two north side columns for canopy approved.

Framing Inspection Passed 5/13/2025 (10:00 - 12:00) 5/13/2025 (AM) 05/13/2025
Corrections:


Miscellaneous/Other
Comment Only
05/13/2025
Corrections to fire caulking in plumbing walls on West side first and second floors approved.

Framing Inspection Passed 5/15/2025 (10:00 - 12:00) 5/15/2025 (AM) 05/15/2025
Corrections:


Miscellaneous/Other
Comment Only
05/15/2025
Shear walls on first floor of East wing approved.

Framing Inspection Passed 5/20/2025 (10:00 - 12:00) 5/20/2025 (AM) 05/20/2025
Corrections:


Miscellaneous/Other
Comment Only
05/20/2025
Completed inspection of all sheer walls requiring wood sheathing on all floors. Few minor items to be reviewed with contractor in field. Approved.

Framing Inspection Passed 5/21/2025 (10:00 - 12:00) 5/21/2025 (AM) 05/21/2025
Corrections:


Miscellaneous/Other
Comment Only
05/21/2025
Fire caulking of units on fifth floor, east wing approved.

Framing Inspection Passed 5/28/2025 (10:00 - 12:00) 5/28/2025 (AM) 05/28/2025
Corrections:


Miscellaneous/Other
Comment Only
05/28/2025
Insulation inspection of unit units on fifth floor, east side approved. No two units at south end of hall to be inspected later.

Framing Inspection Passed 6/5/2025 (10:00 - 12:00) 6/5/2025 (AM) 06/05/2025
Corrections:


Miscellaneous/Other
Comment Only
06/05/2025
Framing and fire caulking of fifth floor connection and West Wing approved.

Framing Inspection Passed 6/6/2025 (10:00 - 12:00) 6/6/2025 (AM) 06/06/2025
Corrections:


Miscellaneous/Other
Comment Only
06/06/2025
Remaining sheer walls on fourth floor approved.

Framing Inspection Failed 6/9/2025 (10:00 - 12:00) 6/9/2025 (AM) 06/09/2025
Corrections:


Miscellaneous/Other
Carried Forward
06/09/2025
Reviewed screw patterns on gyp. board shear walls on fifth floor. Corrections required in room numbers 531, 534, 547 and 549.

Framing Inspection Passed 6/11/2025 (10:00 - 12:00) 6/11/2025 (AM) 06/11/2025
Corrections:


Miscellaneous/Other
Comment Only
06/11/2025
Insulation inspection of fifth floor connection and West Wing approved.

Framing Inspection Not Ready 6/17/2025 (10:00 - 12:00) 6/17/2025 (AM) 06/17/2025
Corrections:


Miscellaneous/Other
Comment Only
06/17/2025
Preliminary walk-through for fire caulking on fourth floor, east wing. Not ready, to be reinspected. Fifth floor soffits East wingOK to enclose.

Framing Inspection Passed 6/18/2025 (10:00 - 12:00) 6/18/2025 (AM) 06/18/2025
Corrections:


Miscellaneous/Other
Comment Only
06/18/2025
Fire caulking on fourth floor, east side, approved.

Framing Inspection Passed 6/23/2025 (10:00 - 12:00) 6/23/2025 (AM) 06/23/2025
Corrections:


Miscellaneous/Other
Comment Only
06/23/2025
Above ceiling insulation in exterior walls of units on fourth floor, east wing, approved.

Framing Inspection Passed 6/26/2025 (10:00 - 12:00) 6/26/2025 (AM) 06/25/2025
Corrections:


Miscellaneous/Other
Comment Only
06/25/2025
Progress Inspection of fire caulking at plumbing penetrations in rated walls on fifth floor approved.

Framing Inspection Passed 7/2/2025 (10:00 - 12:00) 7/2/2025 (AM) 07/02/2025
Corrections:


Miscellaneous/Other
Resolved
07/02/2025
Reviewed screw patterns on gyp. board shear walls on fifth floor. Corrections required in room numbers 531, 534, 547 and 549.

Miscellaneous/Other
Comment Only
07/02/2025
Insulation in fourth floor unit on east side approved.

Framing Inspection Passed 7/3/2025 (12:30 - 2:30) 7/3/2025 (PM) 07/03/2025
Corrections:


Miscellaneous/Other
Comment Only
07/03/2025
Framing and fire caulking of fourth floor West side and connection approved.

Framing Inspection Passed 7/10/2025 (10:00 - 12:00) 7/10/2025 (AM) 07/10/2025
Corrections:


Miscellaneous/Other
Comment Only
07/10/2025
Insulation of units on fourth floor, west side and fourth floor connection approved.

Framing Inspection Passed 7/21/2025 (10:00 - 12:00) 7/21/2025 (AM) 07/21/2025
Corrections:


Miscellaneous/Other
Comment Only
07/21/2025
Partial approval for framing and fire caulk of third floor, east side approved where noted on door jambs.

Framing Inspection Passed 7/23/2025 (10:00 - 12:00) 7/23/2025 (AM) 07/23/2025
Corrections:


Miscellaneous/Other
Comment Only
07/23/2025
Remaining framing and fire caulking on third floor east side and third floor connection approved.

Framing Inspection Passed 7/24/2025 (10:00 - 12:00) 7/24/2025 (AM) 07/24/2025
Corrections:


Miscellaneous/Other
Comment Only
07/24/2025
Remaining third floor units on west side, framing, and fire caulk approved. Insulation approved for East wing units on third floor.

Framing Inspection Passed 8/1/2025 (10:00 - 12:00) 8/1/2025 (AM) 08/01/2025
Corrections:


Miscellaneous/Other
Comment Only
08/01/2025
Insulation inspection of units on third floor, west side, approved.

Framing Inspection Passed 8/7/2025 (10:00 - 12:00) 8/7/2025 (AM) 08/07/2025
Corrections:


Miscellaneous/Other
Comment Only
08/07/2025
Framing and fire caulking on second floor, east wing approved.

Framing Inspection Passed 8/14/2025 (10:00 - 12:00) 8/14/2025 (AM) 08/14/2025
Corrections:


Miscellaneous/Other
Comment Only
08/14/2025
Insulation on second floor east wing approved. Progress inspection of fire caulk on second floor Westwing OK to proceed.

Framing Inspection Passed 8/19/2025 (10:00 - 12:00) 8/19/2025 (AM) 08/19/2025
Corrections:


Miscellaneous/Other
Comment Only
08/19/2025
Framing and fire caulking of remaining units on second floor Westwing approved.

Framing Inspection Partial Pass 8/21/2025 (10:00 - 12:00) 8/21/2025 (AM) 08/21/2025
Corrections:


Miscellaneous/Other
Comment Only
08/21/2025
Progress inspection of exterior brick veneer approved. Remaining insulation inspections on second floor, West Wing approved.

Framing Inspection Passed w/ Conditions 8/26/2025 (10:00 - 12:00) 8/26/2025 (AM) 08/26/2025
Corrections:


Miscellaneous/Other
Comment Only
08/26/2025
Framing and fire caulking for units on first floor, Eastwing approved. Note, corridor walls above ceiling at south end of first floor, east wing, missing fire caulking in several locations. Note 2 units in first floor connection missing door jamb sign off sheets.

Framing Inspection Passed 9/4/2025 (8:00 - 10:00) 9/4/2025 (AM) 09/04/2025
Corrections:


Miscellaneous/Other
Comment Only
09/04/2025
Note, this inspection performed on September 2. Framing and fire caulking approved on first floor, west side. Insulation approved on first floor west side and most of connection. Common areas in middle of connection to be inspected separately.

Insulation Inspection Passed 9/16/2025 (8:00 - 10:00) 9/16/2025 (AM) 09/16/2025
Corrections:


Miscellaneous/Other
Comment Only
09/16/2025
Insulation of units on first floor, West Wing, approved.

Progress Inspection Passed 10/1/2025 (10:00 - 12:00) 10/1/2025 (AM) 10/01/2025
Corrections:


Miscellaneous/Other
Comment Only
10/01/2025
Framing and fire, caulking and insulation in first floor connection common areas approved.

Progress Inspection Passed 10/7/2025 (10:00 - 12:00) 10/7/2025 (AM) 10/09/2025
Corrections:


Miscellaneous/Other
Comment Only
10/09/2025
Progress inspection included a general walk-through and review on site to discuss rated shafts and exiting signage.

Insulation Inspection Passed 11/26/2025 (12:30 - 2:30) 11/26/2025 (PM) 11/26/2025
Corrections:


Miscellaneous/Other
Comment Only
11/26/2025
Insulation of threshold walls below windows several floors installed late for material access approved.

Progress Inspection Passed 12/4/2025 (10:00 - 12:00) 12/4/2025 (AM) 12/04/2025
Corrections:


Miscellaneous/Other
Comment Only
12/04/2025
Reviewed scheduling completion dates with contractor to determine accessible times for preliminary final inspections in individual units.

Progress Inspection Passed 12/18/2025 (10:00 - 12:00) 12/18/2025 (AM) 12/18/2025
Corrections:


Miscellaneous/Other
Comment Only
12/18/2025
Meeting with contractor to discuss scheduling for preliminary final inspections. Reviewed fire caulking needs in trash rooms at garage level. Will reinspect as required.

Progress Inspection Passed 12/30/2025 (10:00 - 12:00) 12/30/2025 (AM) 12/30/2025
Corrections:


Miscellaneous/Other
Comment Only
12/30/2025
Remove all tape and covering from labels on rated doors and rated frames. Progress inspection of fire caulking at plumbing penetrations in random locations approved.

Progress Inspection Failed 1/6/2026 (10:00 - 12:00) 1/6/2026 (AM) 01/06/2026
Corrections:


Miscellaneous/Other
Carried Forward
01/06/2026
Inspection of deck guard rails on fifth floor. Deck in unit 511 has a loose guard rail. All others on fifth floor OK.

Progress Inspection Passed 1/8/2026 (10:00 - 12:00) 1/8/2026 (AM) 01/08/2026
Corrections:


Miscellaneous/Other
Comment Only
01/08/2026
Deck guard rails throughout fourth floor approved. Note sliding glass door stuck in unit number 409, unable to check guardrail at this time.

Progress Inspection Failed 1/13/2026 (10:00 - 12:00) 1/13/2026 (AM) 01/13/2026
Corrections:


Miscellaneous/Other
Carried Forward
01/13/2026
Inspection of guard rails throughout second and third floors. Corrections required in units 236, 305, 334 and 342 as discussed with contractor in field.

Progress Inspection Failed 2/5/2026 (10:00 - 12:00) 2/5/2026 (AM) 02/05/2026
Corrections:


Miscellaneous/Other
Carried Forward
02/05/2026
The deck guard rail in unit 103 returns 7 inches shy of the building. Maximum 4 inches is allowed.

Progress Inspection Failed 2/12/2026 (10:00 - 12:00) 2/12/2026 (AM) 02/12/2026
Corrections:


Miscellaneous/Other
Carried Forward
02/12/2026
Inspection of fire caulking throughout lower level parking area. Some corrections required, to be reinspected.

Follow-up Inspection Partial Pass 03/09/2026
Check of all single-station smoke alarms inside the units. Smoke alarms need to be added to the "den" in units 116. 216. 316. 416, 516
Progress Inspection Passed 3/12/2026 (10:00 - 12:00) 3/12/2026 (AM) 03/12/2026
Corrections:


Miscellaneous/Other
Resolved
03/12/2026
Inspection of guard rails throughout second and third floors. Corrections required in units 236, 305, 334 and 342 as discussed with contractor in field.

Building Final Inspection Failed 03/12/2026
Corrections:


Miscellaneous/Other
Carried Forward
03/12/2026
1. Complete work on soffits over fifth floor decks at North and south ends. 2. Remove tape and obstructions from all rated doors and adjust closers as required for full operation. 3. Remove paint and tape from all rated door labels. 4. Deck guard rail in unit number 103 has 6 inch gap at wall. Correct to maximum 4 inch gap. 5. One penetration in electrical room wall on garage level missing fire caulk. 6. Need final fire approval. 7. Confirmed letter of approval by state for elevator, approved.

Progress Inspection Partial Pass 3/17/2026 (10:00 - 12:00) 3/17/2026 (AM) 03/17/2026
Corrections:


Miscellaneous/Other
Resolved
03/17/2026
The deck guard rail in unit 103 returns 7 inches shy of the building. Maximum 4 inches is allowed.

Miscellaneous/Other
Comment Only
03/17/2026
Progress inspection of corrections being made for last inspection progressing. OK. A partial occupancy is approved for model units number 115 and 117 only with limited access through Northwest stairwell entrance/exit.

Progress Inspection Passed 3/19/2026 (10:00 - 12:00) 3/19/2026 (AM) 03/19/2026
Corrections:


Miscellaneous/Other
Resolved
03/19/2026
Inspection of fire caulking throughout lower level parking area. Some corrections required, to be reinspected.

Miscellaneous/Other
Outstanding
03/19/2026
Meeting on site with contractor to discuss details and timing issues related to upcoming final inspection.

Progress Inspection Passed 4/2/2026 (10:00 - 12:00) 4/2/2026 (AM) 04/02/2026
Corrections:


Miscellaneous/Other
Comment Only
04/02/2026
Partial occupancy approved for two demo units at Northwest corner of first floor only. Provide protection at landing to stairwell door access as discussed in feel. OK to show common areas on first floor to public only under supervision.