Permit Application Status

PRBD202404686


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202404686
Building
Permit(s) Issued
LTF REAL ESTATE COMPANY
New
Residential, multiple family
Storage, low hazard
New multi-family building, 208 units, 299,199 sq ft.
04/16/2024
09/17/2024
10/11/2025

Locations

Permits

Permit Number: PRBD202404686

Building
Issued
09/17/2024
10/11/2025

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Insulation Inspection Pending
Housewrap Inspection Pending
Lighting Inspection Pending
Fire Inspection Final Pending
Building Final Inspection Pending
Landscaping Inspection Pending
Framing Inspection Pending
Framing Inspection Pending
Framing Inspection Pending 1/14/2025 (10:00 - 12:00)
Framing Inspection Pending 1/15/2025 (10:00 - 12:00)
Framing Inspection Pending 1/16/2025 (10:00 - 12:00)
Framing Inspection Pending 1/24/2025 (10:00 - 12:00)
Footing Inspection Passed 10/2/2024 (8:00 - 10:00) 10/2/2024 (AM) 10/03/2024
Corrections:


Miscellaneous/Other
Comment Only
10/03/2024
Perimeter footing inspection to include strip footings with rebar on exterior wall at East and north sides from column line M to column line 2 approved.

Footing Inspection Passed 10/4/2024 (12:30 - 2:30) 10/4/2024 (PM) 10/04/2024
Corrections:


Miscellaneous/Other
Comment Only
10/04/2024
Strip footing on grid A, from lines 1.7 to 8.7

Footing Inspection Partial Pass 10/7/2024 (12:30 - 2:30) 10/7/2024 (PM) 10/07/2024
Ongoing footing inspection, PASSED. Partial pass for ongoing foundation inspections.
Footing Inspection Not Ready 10/8/2024 (10:00 - 12:00) 10/8/2024 (AM) 10/08/2024
Footing Inspection Passed 10/9/2024 (10:00 - 12:00) 10/9/2024 (AM) 10/09/2024
Corrections:


Miscellaneous/Other
Comment Only
10/09/2024
11 pad footings in southeast area and strip footing along south wall approved.

Footing Inspection Passed 10/11/2024 (10:00 - 12:00) 10/11/2024 (AM) 10/11/2024
Corrections:


Miscellaneous/Other
Comment Only
10/11/2024
11 pad footings on column line B, one on column 11, three on column 10.2 approved. Strip footing on south wall on column line K approved.

Footing Inspection Passed 10/15/2024 (10:00 - 12:00) 10/15/2024 (AM) 10/14/2024
Corrections:


Miscellaneous/Other
Comment Only
10/14/2024
Total of 12 pad footings on column lines D, E and J-1. Approved.

Footing Inspection Passed 10/14/2024 (10:00 - 12:00) 10/14/2024 (AM) 10/15/2024
Corrections:


Miscellaneous/Other
Comment Only
10/15/2024
Pad footings for two elevator pits approved.

Footing Inspection Passed 10/16/2024 (10:00 - 12:00) 10/16/2024 (AM) 10/16/2024
Corrections:


Miscellaneous/Other
Comment Only
10/16/2024
Six pad footings on column line G and progress inspection of waterproofing of footings for 2 elevator pits. Approved.

Footing Inspection Passed 10/17/2024 (10:00 - 12:00) 10/17/2024 (AM) 10/17/2024
Corrections:


Miscellaneous/Other
Comment Only
10/17/2024
Five pad footings as per plan marked in field approved.

Footing Inspection Passed 10/18/2024 (2:30 - 3:30) 10/18/2024 (PM) 10/18/2024
Corrections:


Miscellaneous/Other
Comment Only
10/18/2024
Poured foundation walls between grids D to E.3 of both elevators.

Footing Inspection Passed 10/21/2024 (12:30 - 2:30) 10/21/2024 (PM) 10/21/2024
Corrections:


Miscellaneous/Other
Comment Only
10/21/2024
Pad footings on grid C, lines 5.3,6,6.7,7.3,8,8.8,10 Grid F, line8.7 Grid H, lines4.4,5,6,7,8,8.8

Footing Inspection Passed 10/22/2024 (10:00 - 12:00) 10/22/2024 (AM) 10/22/2024
Corrections:


Miscellaneous/Other
Comment Only
10/22/2024
Three pad footings on column line C and strip footing for West wall approved.

Footing Inspection Passed 10/23/2024 (10:00 - 12:00) 10/23/2024 (AM) 10/23/2024
Corrections:


Miscellaneous/Other
Comment Only
10/23/2024
10 pad footings per marked plan and one correction at Northwest corner, all approved.

Footing Inspection Passed 10/10/2024 (10:00 - 12:00) 10/10/2024 (AM) 10/24/2024
Corrections:


Miscellaneous/Other
Comment Only
10/24/2024
Remaining pad footings, including all on column line 2 approved.

Framing Inspection Not Ready 1/13/2025 (10:00 - 12:00) 1/13/2025 (AM) 01/13/2025
Framing Inspection Not Ready 1/17/2025 (10:00 - 12:00) 1/17/2025 (AM) 01/17/2025
Framing Inspection Not Ready 1/21/2025 (10:00 - 12:00) 1/21/2025 (AM) 01/21/2025
Framing Inspection Passed 1/22/2025 (10:00 - 12:00) 1/22/2025 (AM) 01/22/2025
Corrections:


Miscellaneous/Other
Comment Only
01/22/2025
Progress inspection of first floor, southeast stair shaft, framing, and gyp. bd., approved.

Framing Inspection Passed 1/23/2025 (10:00 - 12:00) 1/23/2025 (AM) 01/23/2025
Corrections:


Miscellaneous/Other
Comment Only
01/23/2025
Progress inspection of second layer on first floor of stair shaft at south east corner, approved.

Framing Inspection Passed 1/27/2025 (10:00 - 12:00) 1/27/2025 (AM) 01/27/2025
Corrections:


Miscellaneous/Other
Comment Only
01/27/2025
Progress inspection of shaft, framing, and sheet rock at North east stairwell, first floor, approved.

Framing Inspection Passed 2/3/2025 (10:00 - 12:00) 2/3/2025 (AM) 02/03/2025
Corrections:


Miscellaneous/Other
Comment Only
02/03/2025
Progress inspection of various first floor framing approved.

Framing Inspection Passed 2/5/2025 (10:00 - 12:00) 2/5/2025 (AM) 02/05/2025
Corrections:


Miscellaneous/Other
Comment Only
02/05/2025
Progress inspection of rated separation wall on first floor and first floor north west stairwell shaft approved.

Framing Inspection Passed 2/10/2025 (8:00 - 10:00) 2/10/2025 (AM) 02/10/2025
Corrections:


Miscellaneous/Other
Comment Only
02/10/2025
Progress inspection of framing and sheet rock on first floor, south west stair shaft approved.

Framing Inspection Passed 2/14/2025 (10:00 - 12:00) 2/14/2025 (AM) 02/14/2025
Corrections:


Miscellaneous/Other
Comment Only
02/14/2025
Progress inspection of framing and sheet rock at second floor, south east stairwell approved.

Framing Inspection Not Ready 2/20/2025 (10:00 - 12:00) 2/20/2025 (AM) 02/20/2025
Framing Inspection Not Ready 2/21/2025 (10:00 - 12:00) 2/21/2025 (AM) 02/21/2025
Corrections:


Miscellaneous/Other
Comment Only
02/21/2025
Inspection not needed, contractor was not ready for inspection.

Framing Inspection Not Ready 2/24/2025 (10:00 - 12:00) 2/24/2025 (AM) 02/24/2025
Corrections:


Miscellaneous/Other
Comment Only
02/24/2025
Not ready for inspection

Framing Inspection Passed 2/25/2025 (10:00 - 12:00) 2/25/2025 (AM) 02/25/2025
Corrections:


Miscellaneous/Other
Comment Only
02/25/2025
Progress inspection of rated separation wall on second floor approved. Reviewed details for structural attachment of decks to be installed at later date.

Framing Inspection Passed 2/27/2025 (10:00 - 12:00) 2/27/2025 (AM) 02/27/2025
Corrections:


Miscellaneous/Other
Comment Only
02/27/2025
Progress inspection of sheet rock on rated stairwell shaft at southwest corner, second floor approved.

Framing Inspection Passed 3/3/2025 (8:00 - 10:00) 3/3/2025 (AM) 03/03/2025
Corrections:


Miscellaneous/Other
Comment Only
03/03/2025
Reviewed with superintendent on site the clarification regarding blocking in walls being eliminated when sheet rock extends full height. OK to proceed.

Framing Inspection Passed 3/4/2025 (8:00 - 10:00) 3/4/2025 (AM) 03/04/2025
Corrections:


Miscellaneous/Other
Comment Only
03/04/2025
Progress inspection of sheetrock at third floor level of south east stairwell approved.

Framing Inspection Passed 3/7/2025 (10:00 - 12:00) 3/7/2025 (AM) 03/10/2025
Corrections:


Miscellaneous/Other
Comment Only
03/10/2025
Progress inspection of various rated shafts on north side of third floor approved.

Framing Inspection Not Ready 3/13/2025 (10:00 - 12:00) 3/13/2025 (AM) 03/13/2025
Framing Inspection Passed 3/18/2025 (8:00 - 10:00) 3/18/2025 (AM) 03/18/2025
Corrections:


Miscellaneous/Other
Comment Only
03/18/2025
Progress inspection of south east stairwell shaft at fourth floor approved. Progress inspection of separation role on third and fourth floor approved. Progress inspection of stair shafts at Northwest and southwest on third floor approved.

Framing Inspection Passed 3/24/2025 (8:00 - 10:00) 3/24/2025 (AM) 03/24/2025
Corrections:


Miscellaneous/Other
Comment Only
03/24/2025
Progress inspection of all four rated stairwell shafts at fourth floor level approved.

Framing Inspection Passed 3/26/2025 3/26/2025 (AM) 03/26/2025
Corrections:


Miscellaneous/Other
Comment Only
03/26/2025
Progress inspection of rated stairwell shafts on fourth floor, north west and southwest, approved. First progress inspection of sheer wall nailing on first floor approved.

Framing Inspection Passed 4/1/2025 (10:00 - 12:00) 4/1/2025 (AM) 04/01/2025
Corrections:


Miscellaneous/Other
Comment Only
04/01/2025
Progress inspection of framing, and sheet rock at south east stairwell, fifth level, approved.

Framing Inspection Passed 4/8/2025 (8:00 - 10:00) 4/8/2025 (AM) 04/08/2025
Corrections:


Miscellaneous/Other
Comment Only
04/08/2025
Progress framing, and sheetrock of two east stairwells at fifth floor level approved. Sheer wall blocking and nailing on first floor west wing approved. Sheer walls on first floor east wing not yet complete, to be inspected later.

Framing Inspection Passed 4/14/2025 (8:00 - 10:00) 4/14/2025 (AM) 04/14/2025
Corrections:


Miscellaneous/Other
Comment Only
04/14/2025
Remainder of sheer walls on first level approved.