Permit Application Status

PRBD202405941


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202405941
Building
Permit(s) Issued
POLAR SEMICONDUCTOR INC
Alteration/Repair/Replace
Not Required
Phase II - Infill existing loading dock with processed chilled water plant and exterior wall assembly, MEP upgrades in Phase III - Remodeling existing manufacturing areas, adding interior H-4 gas room, adding prayer/ablution rooms, remodeling accessible toilet rooms. Polar Semiconductor is proposing an interior remodel of existing buildings P1, P2, and P3 and a 3,750 square foot electrical room addition between buildings P2 and P3. The project aims to improve Polar Semiconductor’s manufacturing capabilities and increase the production of semiconductor products. The project will be executed throughout multiple phases with construction occurring over the course of multiple years. Roughly ninety percent of the scope of work is interior remodeling, mechanical/electrical upgrades, and tool installations for Polar Semiconductor’s manufacturing processes.
05/07/2024
10/04/2024
03/21/2026

Locations

Permits

Permit Number: PRBD202405941

Building
Issued
10/04/2024
03/21/2026

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Building Final Inspection Pending
Fire Inspection Final Pending
Framing Inspection Pending 10/6/2025 (10:00 - 12:00) 10/6/2025 (AM)
Framing Inspection Passed 3/18/2025 (10:00 - 12:00) 3/18/2025 (AM) 03/18/2025
Corrections:


Miscellaneous/Other
Outstanding
03/18/2025
Phase 2 framing... approved

Framing Inspection Passed 4/15/2025 (10:00 - 12:00) 4/15/2025 (AM) 04/15/2025
Corrections:


Miscellaneous/Other
Comment Only
04/15/2025
SCM room framing approved

Progress Inspection Passed 5/14/2025 (12:30 - 2:30) 5/14/2025 (PM) 05/14/2025
Above Ceiling inspection
Corrections:


Miscellaneous/Other
Comment Only
05/14/2025
Ceiling framing and above ceil.... approved

Building Final Inspection Partial Pass 6/18/2025 (8:00 - 10:00) 6/18/2025 (AM) 06/18/2025
Corrections:


Miscellaneous/Other
Comment Only
06/18/2025
Final for phase one of this project... approved

Fire Inspection Final Partial Pass 6/18/2025 (8:00 - 10:00) 6/18/2025 (AM) 06/23/2025
Framing Inspection Passed 7/3/2025 (10:00 - 12:00) 7/3/2025 (AM) 07/03/2025
Corrections:


Miscellaneous/Other
Comment Only
07/03/2025
Framing, anchoring, and housewrap... approved

Framing Inspection Passed 07/03/2025
Corrections:


Miscellaneous/Other
Comment Only
07/03/2025
Both bathrooms framing is existing and is in good condition. Backing is in place where needed for partitions, grad bars and sink installation.

Progress Inspection Passed 08/01/2025
Corrections:


Miscellaneous/Other
Comment Only
08/01/2025
MAU reinforced slab as per plan design... approved

Framing Inspection Passed 8/20/2025 (8:00 - 10:00) 8/20/2025 (AM) 08/20/2025
Corrections:


Miscellaneous/Other
Comment Only
08/20/2025
Wall framing at LL electrical room #62...approved

Framing Inspection Passed 9/18/2025 (10:00 - 12:00) 9/18/2025 (AM) 09/18/2025
Corrections:


Miscellaneous/Other
Comment Only
09/18/2025
Load room walls framing... approved

Framing Inspection Passed 9/22/2025 (10:00 - 12:00) 9/22/2025 (AM) 09/22/2025
Corrections:


Miscellaneous/Other
Comment Only
09/22/2025
Shaft wall framing and vestibule framing at new addition of electrical room... approved