PRBD202405941
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Building Final Inspection | Pending | |||
| Fire Inspection Final | Pending | |||
| Framing Inspection | Passed | 3/18/2025 (10:00 - 12:00) | 3/18/2025 (AM) | 03/18/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
03/18/2025
Phase 2 framing... approved
|
||||
| Framing Inspection | Passed | 4/15/2025 (10:00 - 12:00) | 4/15/2025 (AM) | 04/15/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/15/2025
SCM room framing approved
|
||||
| Progress Inspection | Passed | 5/14/2025 (12:30 - 2:30) | 5/14/2025 (PM) | 05/14/2025 |
| Above Ceiling inspection | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
05/14/2025
Ceiling framing and above ceil.... approved
|
||||
| Building Final Inspection | Partial Pass | 6/18/2025 (8:00 - 10:00) | 6/18/2025 (AM) | 06/18/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/18/2025
Final for phase one of this project... approved
|
||||
| Fire Inspection Final | Partial Pass | 6/18/2025 (8:00 - 10:00) | 6/18/2025 (AM) | 06/23/2025 |
| Framing Inspection | Passed | 7/3/2025 (10:00 - 12:00) | 7/3/2025 (AM) | 07/03/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/03/2025
Framing, anchoring, and housewrap... approved
|
||||
| Framing Inspection | Passed | 07/03/2025 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
07/03/2025
Both bathrooms framing is existing and is in good condition. Backing is in place where needed for partitions, grad bars and sink installation.
|
||||
| Progress Inspection | Passed | 08/01/2025 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
08/01/2025
MAU reinforced slab as per plan design... approved
|
||||
| Framing Inspection | Passed | 8/20/2025 (8:00 - 10:00) | 8/20/2025 (AM) | 08/20/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/20/2025
Wall framing at LL electrical room #62...approved
|
||||
| Framing Inspection | Passed | 9/18/2025 (10:00 - 12:00) | 9/18/2025 (AM) | 09/18/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/18/2025
Load room walls framing... approved
|
||||
| Framing Inspection | Passed | 9/22/2025 (10:00 - 12:00) | 9/22/2025 (AM) | 09/22/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/22/2025
Shaft wall framing and vestibule framing at new addition of electrical room... approved
|
||||
| Framing Inspection | Passed | 10/6/2025 (10:00 - 12:00) | 10/6/2025 (AM) | 10/06/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/06/2025
Lower level wall framing... approved
|
||||
| Framing Inspection | Passed | 10/23/2025 (12:30 - 2:30) | 10/23/2025 (PM) | 10/23/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/23/2025
P1 perimetrics.... wall framing approved.
|
||||