Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 1/21/2025 (2:30 - 3:30) | 1/21/2025 (PM) | 01/21/2025 |
Corrections:
Miscellaneous/Other
Comment Only
01/21/2025
Framing approved
|
||||
Progress Inspection | Passed w/ Conditions | 01/31/2025 | ||
Corrections:
Miscellaneous/Other
Outstanding
01/31/2025
Not ready for final inspection at this time.
Corrections...
1) emergency lighting to be checked and operable, this includes the bug eye lighting at the exit signs.( rear exit em lighting is not functional)
2) space needes to be set up with fixtures so inspector can determine aisle width for acces along with exiting.
3) boxes and storage in the storerooms canot be within 18" of sprinkler coverage, adjust storage as needed to comply.
Approval is given for space to be setup and stocked.
|
||||
Building Final Inspection | Not Ready | 1/31/2025 (12:30 - 2:30) | 1/31/2025 (PM) | 01/31/2025 |
Corrections:
Miscellaneous/Other
Comment Only
01/31/2025
Not ready for final, see todays progress inspection report for corrections.
|
||||
Fire Inspection Final | Not Ready | 1/31/2025 (10:00 - 12:00) | 1/31/2025 (AM) | 01/31/2025 |
Fire Inspection Final | Passed | 2/4/2025 (8:00 - 10:00) | 2/4/2025 (AM) | 02/04/2025 |
Building Final Inspection | Passed | 2/4/2025 (8:00 - 10:00) | 2/4/2025 (AM) | 02/04/2025 |
Corrections:
Miscellaneous/Other
Comment Only
02/04/2025
Final for this scope of work and permit approved
|