PRBD202406842
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed w/ Conditions | 7/3/2024 (8:00 - 10:00) | 7/3/2024 (AM) | 07/03/2024 |
Cigar Shop. Framing passed with conditions, to have all trade inspections (electrical, building, mechanical, fire sprinkler, | ||||
Corrections:
Miscellaneous/Other
Comment Only
07/03/2024
Framing passed with conditions.
Trade inspections required. ( Electrical, Mechanical, Fire sprinkler, Building, and electrical for exterior branding signage ).
|
||||
Building Final Inspection | Not Ready | 7/29/2024 (12:30 - 2:30) | 7/29/2024 (PM) | 07/29/2024 |
Corrections:
Miscellaneous/Other
Comment Only
07/29/2024
Not ready for final inspection.
1) complete ceiling grids with tile installation
2) remove SE front exit sign and make operable the north exit door
3) install cashwrap
4) finish bathroom.
Call for final inspection when all is completed
|
||||
Building Final Inspection | Not Ready | 07/29/2024 | ||
Building Final Inspection | Partial Pass | 7/30/2024 (2:30 - 3:30) | 7/30/2024 (PM) | 07/30/2024 |
Corrections:
Miscellaneous/Other
Carried Forward
07/30/2024
1) Install gypsum to cover overtop of the humidor due to the materials used for the ceiling are not plenum rated.
Call for reinspection for this correction when completed.
|
||||
Miscellaneous/Other
Comment Only
07/30/2024
See outstanding comment for correction and reinspection.
Temporary occupancy is approved for this space pending the outstanding correction.
|
||||
Building Final Inspection | Passed | 7/31/2024 (8:00 - 10:00) | 7/31/2024 (AM) | 07/31/2024 |
Corrections:
Miscellaneous/Other
Resolved
07/31/2024
1) Install gypsum to cover overtop of the humidor due to the materials used for the ceiling are not plenum rated.
Call for reinspection for this correction when completed.
|
||||
Miscellaneous/Other
Comment Only
07/31/2024
Corrections completed, final for this permit and scope of work approved
|
||||
Fire Inspection Final | Passed | 7/30/2024 (2:30 - 3:30) | 7/30/2024 (PM) | 07/31/2024 |