PRBD202407315
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Fire Inspection Final | Pending | |||
| Framing Inspection | Passed | 7/25/2024 (10:00 - 12:00) | 7/25/2024 (AM) | 07/25/2024 |
| Floors 16, and 22. Framing, fire caulk, fireproofing structural steel. Passed. | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
07/25/2024
Floors 12, 22. Framing and fireproofing structural steel. Passed.
|
||||
| Building Final Inspection | Passed w/ Conditions | 8/29/2024 (10:00 - 12:00) | 8/29/2024 (AM) | 08/29/2024 |
| All trade inspections to be final approved. | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
08/29/2024
Final passed with condition, all trade inspections remaining to be final approved.
|
||||
| Fire Inspection Final | Partial Pass | 8/29/2024 (10:00 - 12:00) | 8/29/2024 (AM) | 08/29/2024 |
| 16th floor: room 1605 missing hanger on sprinkler arm over, sprinkler contractor to verify sprinkler coverage in between the beams near 1631 above the cloud. 22nd floor: Surge restraint clips needed in the following areas: across from network room in the cloud, 2217 hallway area, inside office 2222. Add fire alarm notification devices in 2232 and 2226. Ok for tenant to occupy. | ||||