PRBD202410808
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 3/10/2025 (10:00 - 12:00) | 3/10/2025 (AM) | 03/10/2025 |
Corrections:
Miscellaneous/Other
Comment Only
03/10/2025
Wall framing approved
|
||||
Above Ceiling Inspection | Passed | 3/24/2025 (8:00 - 10:00) | 3/24/2025 (AM) | 03/24/2025 |
Corrections:
Miscellaneous/Other
Comment Only
03/24/2025
Sales area above ceiling and ceiling framing and supports... approved
|
||||
Framing Inspection | Passed | 4/15/2025 | 4/15/2025 (AM) | 04/15/2025 |
Corrections:
Miscellaneous/Other
Comment Only
04/15/2025
Above ceiling and ceiling framing and supports... approved
|
||||
Building Final Inspection | Passed | 4/25/2025 (12:30 - 2:30) | 4/25/2025 (PM) | 04/25/2025 |
Corrections:
Miscellaneous/Other
Comment Only
04/25/2025
Final for this buildout... approved and ok to open to public.
|
||||
Fire Inspection Final | Passed | 4/25/2025 (12:30 - 2:30) | 4/25/2025 (PM) | 04/28/2025 |