Permit Application Status

PRBD202414370


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202414370
Building
Finaled
KRAUS-ANDERSON INC
Alteration/Repair/Replace
Mercantile
Interior tenant improvement for the sales of furniture within an existing building. New storefront systems on front primary facade.
10/29/2024
12/30/2024
12/07/2025
06/10/2025

Locations

Permits

Permit Number: PRBD202414370

Building
Finaled
12/30/2024
12/07/2025

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Footing Inspection Partial Pass 2/18/2025 (10:00 - 12:00) 2/18/2025 (AM) 02/18/2025
2/18/2025 Contractor called to cancel inspection as no concrete being delivered today. [jsmidt @ 02/18/2025 8:27 AM] Bpost, on site pre inspection, questions on EM LIGHTING, and new footings Per plan.
Footing Inspection Passed 2/19/2025 (10:00 - 12:00) 2/19/2025 (AM) 02/19/2025
Special inspections for concrete footings and piers and masonry per plan. Location store front new beam and wall.
Footing Inspection Passed 2/19/2025 (10:00 - 12:00) 2/19/2025 (AM) 02/19/2025
Corrections:


Miscellaneous/Other
Comment Only
02/19/2025
Brian was there on the 18th and looked at the footings. They were approved. Seven footings with piers approved.

Framing Inspection Passed 2/28/2025 (12:30 - 2:30) 2/28/2025 (PM) 02/28/2025
Corrections:


Miscellaneous/Other
Comment Only
02/28/2025
All framing, except front office and two electrical rooms approved. Seven column footings at front of the store with rebar approved.

Footing Inspection Passed 3/12/2025 (8:00 - 10:00) 3/12/2025 (AM) 03/12/2025
Corrections:


Miscellaneous/Other
Comment Only
03/12/2025
Stoop footing and slab infills i rear of store... approved

Framing Inspection Passed 3/17/2025 (8:00 - 10:00) 3/17/2025 (AM) 03/17/2025
Corrections:


Miscellaneous/Other
Comment Only
03/17/2025
Remaining office wall framing, approved.

Framing Inspection Passed 4/25/2025 (10:00 - 12:00) 4/25/2025 (AM) 04/25/2025
Corrections:


Miscellaneous/Other
Comment Only
04/25/2025
Above ceiling, and ceiling framing / supports.. approved

Building Final Inspection Partial Pass 6/3/2025 (12:30 - 2:30) 6/3/2025 (PM) 06/03/2025
Corrections:


Miscellaneous/Other
Comment Only
06/03/2025
EM lighting checked and approved. Waiting for some signage to be installed and knox box and address numbers. Inspection for full final to be set up with building and fire when all is completed. TCO will be allowed at this time for setup of this space.

Fire Inspection Final Partial Pass 6/3/2025 (12:30 - 2:30) 6/3/2025 (PM) 06/04/2025
Building Final Inspection Passed 6/10/2025 (12:30 - 2:30) 6/10/2025 (PM) 06/10/2025
Corrections:


Miscellaneous/Other
Comment Only
06/10/2025
Final for occupancy for this space approved.

Fire Inspection Final Passed 6/10/2025 (12:30 - 2:30) 6/10/2025 (PM) 06/10/2025