PRBD202414370
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Footing Inspection | Partial Pass | 2/18/2025 (10:00 - 12:00) | 2/18/2025 (AM) | 02/18/2025 |
2/18/2025 Contractor called to cancel inspection as no concrete being delivered today. [jsmidt @ 02/18/2025 8:27 AM] Bpost, on site pre inspection, questions on EM LIGHTING, and new footings Per plan. | ||||
Footing Inspection | Passed | 2/19/2025 (10:00 - 12:00) | 2/19/2025 (AM) | 02/19/2025 |
Special inspections for concrete footings and piers and masonry per plan. Location store front new beam and wall. | ||||
Footing Inspection | Passed | 2/19/2025 (10:00 - 12:00) | 2/19/2025 (AM) | 02/19/2025 |
Corrections:
Miscellaneous/Other
Comment Only
02/19/2025
Brian was there on the 18th and looked at the footings. They were approved. Seven footings with piers approved.
|
||||
Framing Inspection | Passed | 2/28/2025 (12:30 - 2:30) | 2/28/2025 (PM) | 02/28/2025 |
Corrections:
Miscellaneous/Other
Comment Only
02/28/2025
All framing, except front office and two electrical rooms approved. Seven column footings at front of the store with rebar approved.
|
||||
Footing Inspection | Passed | 3/12/2025 (8:00 - 10:00) | 3/12/2025 (AM) | 03/12/2025 |
Corrections:
Miscellaneous/Other
Comment Only
03/12/2025
Stoop footing and slab infills i rear of store... approved
|
||||
Framing Inspection | Passed | 3/17/2025 (8:00 - 10:00) | 3/17/2025 (AM) | 03/17/2025 |
Corrections:
Miscellaneous/Other
Comment Only
03/17/2025
Remaining office wall framing, approved.
|
||||
Framing Inspection | Passed | 4/25/2025 (10:00 - 12:00) | 4/25/2025 (AM) | 04/25/2025 |
Corrections:
Miscellaneous/Other
Comment Only
04/25/2025
Above ceiling, and ceiling framing / supports.. approved
|
||||
Building Final Inspection | Partial Pass | 6/3/2025 (12:30 - 2:30) | 6/3/2025 (PM) | 06/03/2025 |
Corrections:
Miscellaneous/Other
Comment Only
06/03/2025
EM lighting checked and approved.
Waiting for some signage to be installed and knox box and address numbers. Inspection for full final to be set up with building and fire when all is completed.
TCO will be allowed at this time for setup of this space.
|
||||
Fire Inspection Final | Partial Pass | 6/3/2025 (12:30 - 2:30) | 6/3/2025 (PM) | 06/04/2025 |
Building Final Inspection | Passed | 6/10/2025 (12:30 - 2:30) | 6/10/2025 (PM) | 06/10/2025 |
Corrections:
Miscellaneous/Other
Comment Only
06/10/2025
Final for occupancy for this space approved.
|
||||
Fire Inspection Final | Passed | 6/10/2025 (12:30 - 2:30) | 6/10/2025 (PM) | 06/10/2025 |