PRBD202414370
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Inspection Final | Pending | |||
Building Final Inspection | Pending | |||
Framing Inspection | Pending | 4/25/2025 (10:00 - 12:00) | 4/25/2025 (AM) | |
Footing Inspection | Partial Pass | 2/18/2025 (10:00 - 12:00) | 2/18/2025 (AM) | 02/18/2025 |
2/18/2025 Contractor called to cancel inspection as no concrete being delivered today. [jsmidt @ 02/18/2025 8:27 AM] Bpost, on site pre inspection, questions on EM LIGHTING, and new footings Per plan. | ||||
Footing Inspection | Passed | 2/19/2025 (10:00 - 12:00) | 2/19/2025 (AM) | 02/19/2025 |
Special inspections for concrete footings and piers and masonry per plan. Location store front new beam and wall. | ||||
Footing Inspection | Passed | 2/19/2025 (10:00 - 12:00) | 2/19/2025 (AM) | 02/19/2025 |
Corrections:
Miscellaneous/Other
Comment Only
02/19/2025
Brian was there on the 18th and looked at the footings. They were approved. Seven footings with piers approved.
|
||||
Framing Inspection | Passed | 2/28/2025 (12:30 - 2:30) | 2/28/2025 (PM) | 02/28/2025 |
Corrections:
Miscellaneous/Other
Comment Only
02/28/2025
All framing, except front office and two electrical rooms approved. Seven column footings at front of the store with rebar approved.
|
||||
Footing Inspection | Passed | 3/12/2025 (8:00 - 10:00) | 3/12/2025 (AM) | 03/12/2025 |
Corrections:
Miscellaneous/Other
Comment Only
03/12/2025
Stoop footing and slab infills i rear of store... approved
|
||||
Framing Inspection | Passed | 3/17/2025 (8:00 - 10:00) | 3/17/2025 (AM) | 03/17/2025 |
Corrections:
Miscellaneous/Other
Comment Only
03/17/2025
Remaining office wall framing, approved.
|