PRBD202414759
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Building Final Inspection | Pending | |||
| Fire Inspection Final | Pending | |||
| Framing Inspection | Passed | 7/3/2025 (10:00 - 12:00) | 7/3/2025 (AM) | 07/03/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/03/2025
Several miscellaneous framing issues on both main level and lower level approved. Note, drinking fountain cane guards will be required on fountains, protruding into hallway.
|
||||
| Above Ceiling Inspection | Passed | 7/22/2025 (8:00 - 10:00) | 7/22/2025 (AM) | 07/22/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/22/2025
Above ceiling progress inspection of both levels approved
|
||||
| Building Final Inspection | Issue TCO | 8/21/2025 (8:00 - 10:00) | 8/21/2025 (AM) | 08/21/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/21/2025
20 day temporary occupancy for use by faculty only approved contingent on temporary occupancy being issued by electrical inspector. Call for final when ready.
|
||||
| Fire Inspection Final | Partial Pass | 8/27/2025 (12:30 - 2:30) | 8/27/2025 (PM) | 08/26/2025 |
| Fire Inspection Final | Partial Pass | 8/20/2025 (12:30 - 2:30) | 8/20/2025 (PM) | 08/26/2025 |
| Fire Inspection Final | Partial Pass | 8/27/2025 (12:30 - 2:30) | 8/27/2025 (PM) | 08/28/2025 |
| Phase 1A | ||||
| Building Final Inspection | Partial Pass | 8/28/2025 (10:00 - 12:00) | 8/28/2025 (AM) | 08/28/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/28/2025
Partial occupancy approved for phase 1A of multi phase project.
|
||||
| Framing Inspection | Passed | 9/9/2025 (8:00 - 10:00) | 9/9/2025 (AM) | 09/09/2025 |
| Main level-A wing | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
09/09/2025
Framing for restroom and wall in room 202C, approved.
|
||||
| Progress Inspection | Passed | 9/24/2025 (10:00 - 12:00) | 9/24/2025 (AM) | 09/24/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/24/2025
Progress inspection of above ceiling, fire caulking at rated corridor walls approved.
|
||||
| Building Final Inspection | Partial Pass | 10/10/2025 (8:00 - 10:00) | 10/10/2025 (AM) | 10/10/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/10/2025
Partial final approved for phase 1B.
|
||||
| Fire Inspection Final | Partial Pass | 10/13/2025 (8:00 - 10:00) | 10/13/2025 (AM) | 10/13/2025 |
| "A" wing 200 classrooms except for A208 needs to add notification device. | ||||
| Building Final Inspection | Partial Pass | 12/22/2025 (8:00 - 10:00) | 12/22/2025 (AM) | 12/22/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/22/2025
Final approved for wing in phase 1 – C only.
|
||||
| Fire Inspection Final | Partial Pass | 12/24/2025 (8:00 - 10:00) | 12/24/2025 (AM) | 12/29/2025 |
| Lower level A-wing approved. Needs to repair smoke rated wall above A103. | ||||
| Framing Inspection | Passed | 2/4/2026 (8:00 - 10:00) | 2/4/2026 (AM) | 02/04/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/04/2026
Phase 1-D, toilet rooms framing approved.
|
||||
| Progress Inspection | Passed | 2/19/2026 (8:00 - 10:00) | 2/19/2026 (AM) | 02/19/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/19/2026
Reviewed on site rated wall in classroom above ceiling requiring fire caulk repairs. Proceed as discussed and call for inspection when ready.
|
||||
| Progress Inspection | Passed | 3/3/2026 (10:00 - 12:00) | 3/3/2026 (AM) | 03/03/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/03/2026
Reviewed exiting needs on site with contractor to accommodate temporary blocking of one exit at basketball court. OK to proceed as discussed in field. Called for inspection when barricades installed.
|
||||