PRBD202414781
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Building Final Inspection | Pending | |||
Corrections:
Miscellaneous/Other
Outstanding
08/21/2025
Still need final electrical approval. 20 day temporary occupancy approved for use by staff and faculty only. Call for final when ready.
|
||||
Framing Inspection | Passed | 6/26/2025 (8:00 - 10:00) | 6/26/2025 (AM) | 06/25/2025 |
Corrections:
Miscellaneous/Other
Comment Only
06/25/2025
Framing inspection of all but stage ceiling approved. Stage ceiling to be inspected separately.
|
||||
Framing Inspection | Passed | 7/29/2025 (8:00 - 10:00) | 7/29/2025 (AM) | 07/29/2025 |
Corrections:
Miscellaneous/Other
Comment Only
07/29/2025
Above ceiling framing inspection at theater stage approved.
|
||||
Building Final Inspection | Issue TCO | 8/21/2025 (8:00 - 10:00) | 8/21/2025 (AM) | 08/21/2025 |
Corrections:
Miscellaneous/Other
Carried Forward
08/21/2025
Still need final electrical approval. 20 day temporary occupancy approved for use by staff and faculty only. Call for final when ready.
|
||||
Fire Inspection Final | Partial Pass | 8/27/2025 (12:30 - 2:30) | 8/27/2025 (PM) | 08/26/2025 |
Fire Inspection Final | Partial Pass | 8/20/2025 (12:30 - 2:30) | 8/20/2025 (PM) | 08/26/2025 |
Fire Inspection Final | Passed | 8/27/2025 (12:30 - 2:30) | 8/27/2025 (PM) | 08/28/2025 |
Building Final Inspection | Passed | 8/28/2025 (10:00 - 12:00) | 8/28/2025 (AM) | 08/28/2025 |