PRBD202415165
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Building Final Inspection | Not Ready | 11/22/2024 | 11/22/2024 | |
Corrections:
Miscellaneous/Other
Carried Forward
11/22/2024
This space is not fully completed. An approval to bring in stock and set up will be allowed. Follow up inspection required before opening.
|
||||
Building Final Inspection | Not Ready | 11/22/2024 (2:30 - 3:30) | 11/22/2024 (PM) | 11/22/2024 |
Corrections:
Miscellaneous/Other
Comment Only
11/22/2024
Duct penetration at shaft has been corrected. All work is done and inspected.
Condition for final is to have Environmental Health follow up with equipment installation of pop dispenser and sneeze guards.
This is also pending fire inspection final.
|
||||
Fire Inspection Final | Passed | 11/22/2024 (8:00 - 10:00) | 11/22/2024 (AM) | 11/26/2024 |
Building Final Inspection | Passed | 11/26/2024 (8:00 - 10:00) | 11/26/2024 (AM) | 11/26/2024 |
Corrections:
Miscellaneous/Other
Resolved
11/26/2024
This space is not fully completed. An approval to bring in stock and set up will be allowed. Follow up inspection required before opening.
|
||||
Miscellaneous/Other
Comment Only
11/26/2024
Final approved, pending follow up inspection by EH.
|