PRBD202415765
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 1/31/2025 (12:30 - 2:30) | 1/31/2025 (PM) | 01/31/2025 |
Corrections:
Miscellaneous/Other
Comment Only
01/31/2025
Framing approved
|
||||
Fire Inspection Final | Passed | 02/25/2025 | ||
Framing Inspection | Passed | 2/27/2025 (8:00 - 10:00) | 2/27/2025 (AM) | 02/27/2025 |
Corrections:
Miscellaneous/Other
Comment Only
02/27/2025
Exhaust venting for dryer and for above stove hood vent in traing room has been framed around and encapsulated with gypsum board and fire caulked as needed to remove these items from being exposed in a plenum ceiling... approved.
Walk through of spaces being worked on, all work is completed and exiting is correct and approved. Set up final inspection when the remaining ceiling has been installed in the training room.
|
||||
Building Final Inspection | Passed | 4/10/2025 (8:00 - 10:00) | 4/10/2025 (AM) | 04/10/2025 |
Corrections:
Miscellaneous/Other
Comment Only
04/10/2025
Final for this scope of work and permit approved
|