PRBD202416627
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Inspection Final | Pending | |||
Building Final Inspection | Pending | |||
Footing Inspection | Passed | 3/13/2025 (8:00 - 10:00) | 3/13/2025 (AM) | 03/13/2025 |
Corrections:
Miscellaneous/Other
Comment Only
03/13/2025
2 pad footings with rebar mat as per desing plans, and slab on grade poly.... approved
|
||||
Progress Inspection | Passed | 3/14/2025 (8:00 - 10:00) | 3/14/2025 (AM) | 03/14/2025 |
Corrections:
Miscellaneous/Other
Comment Only
03/14/2025
Slab inspection with number four rebar each way at 16 inches approved.
|
||||
Framing Inspection | Passed | 3/27/2025 (10:00 - 12:00) | 3/27/2025 (AM) | 03/27/2025 |
Corrections:
Miscellaneous/Other
Comment Only
03/27/2025
Wall framing and soffit framing....approved.
|
||||
Progress Inspection | Passed | 4/1/2025 (8:00 - 10:00) | 4/1/2025 (AM) | 04/01/2025 |
Corrections:
Miscellaneous/Other
Comment Only
04/01/2025
The 2 pad footings that were originally placed did not make poundage break though the concrete mix was approved for use. Contractor decided to remove them and redo footing pads. Rebar and pad size/ depth approved.
|