PRBD202416627
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Building Final Inspection | Pending | |||
Footing Inspection | Passed | 3/13/2025 (8:00 - 10:00) | 3/13/2025 (AM) | 03/13/2025 |
Corrections:
Miscellaneous/Other
Comment Only
03/13/2025
2 pad footings with rebar mat as per desing plans, and slab on grade poly.... approved
|
||||
Progress Inspection | Passed | 3/14/2025 (8:00 - 10:00) | 3/14/2025 (AM) | 03/14/2025 |
Corrections:
Miscellaneous/Other
Comment Only
03/14/2025
Slab inspection with number four rebar each way at 16 inches approved.
|
||||
Framing Inspection | Passed | 3/27/2025 (10:00 - 12:00) | 3/27/2025 (AM) | 03/27/2025 |
Corrections:
Miscellaneous/Other
Comment Only
03/27/2025
Wall framing and soffit framing....approved.
|
||||
Progress Inspection | Passed | 4/1/2025 (8:00 - 10:00) | 4/1/2025 (AM) | 04/01/2025 |
Corrections:
Miscellaneous/Other
Comment Only
04/01/2025
The 2 pad footings that were originally placed did not make poundage break though the concrete mix was approved for use. Contractor decided to remove them and redo footing pads. Rebar and pad size/ depth approved.
|
||||
Above Ceiling Inspection | Passed | 5/20/2025 (8:00 - 10:00) | 5/20/2025 (AM) | 05/20/2025 |
Corrections:
Miscellaneous/Other
Comment Only
05/20/2025
Above ceiling and ceiling supports... approved
|
||||
Framing Inspection | Passed | 6/4/2025 (7:00 - 8:00) | 6/4/2025 (AM) | 06/04/2025 |
Corrections:
Miscellaneous/Other
Comment Only
06/04/2025
Wall section framing approved
|
||||
Progress Inspection | Passed | 7/22/2025 (12:30 - 2:30) | 7/22/2025 (PM) | 07/22/2025 |
Corrections:
Miscellaneous/Other
Comment Only
07/22/2025
Went over the buildout and time line for possible turnover use of these restrooms by Aug 1st.
There are pieces that are on back order and wont be in by that date, trades inspections are set up for the week of possible turnover. Contractor to set up inspection for building inspector about mid week and we can revisit the potential of turnover use for the upcoming event.
|
||||
Building Final Inspection | Partial Pass | 7/31/2025 (7:00 - 8:00) | 7/31/2025 (AM) | 07/31/2025 |
Corrections:
Miscellaneous/Other
Comment Only
07/31/2025
Bathrooms are built to the approved plans. What remains to be completd is the glass panels to be installed when they come in.
Bathrooms are approved to open for public use.
Call cor final inspection when all glazing is in and completed.
|
||||
Fire Inspection Final | Passed | 7/31/2025 (8:00 - 10:00) | 7/31/2025 (AM) | 07/31/2025 |