Permit Application Status

PRBD202416627


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202416627
Building
Permit(s) Issued
CITY OF BLOOMINGTON
Alteration/Repair/Replace
Not Required
Selective demolition of existing Men’s. Women’s and Family restrooms located adjacent to the west entrance to the Civic Plaza Building. New construction, fixtures and finishes to provide single user restrooms stalls, universal changing room, and urinal room.
12/26/2024
02/19/2025
01/27/2026

Locations

Permits

Permit Number: PRBD202416627

Building
Issued
02/19/2025
01/27/2026

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Building Final Inspection Pending
Footing Inspection Passed 3/13/2025 (8:00 - 10:00) 3/13/2025 (AM) 03/13/2025
Corrections:


Miscellaneous/Other
Comment Only
03/13/2025
2 pad footings with rebar mat as per desing plans, and slab on grade poly.... approved

Progress Inspection Passed 3/14/2025 (8:00 - 10:00) 3/14/2025 (AM) 03/14/2025
Corrections:


Miscellaneous/Other
Comment Only
03/14/2025
Slab inspection with number four rebar each way at 16 inches approved.

Framing Inspection Passed 3/27/2025 (10:00 - 12:00) 3/27/2025 (AM) 03/27/2025
Corrections:


Miscellaneous/Other
Comment Only
03/27/2025
Wall framing and soffit framing....approved.

Progress Inspection Passed 4/1/2025 (8:00 - 10:00) 4/1/2025 (AM) 04/01/2025
Corrections:


Miscellaneous/Other
Comment Only
04/01/2025
The 2 pad footings that were originally placed did not make poundage break though the concrete mix was approved for use. Contractor decided to remove them and redo footing pads. Rebar and pad size/ depth approved.

Above Ceiling Inspection Passed 5/20/2025 (8:00 - 10:00) 5/20/2025 (AM) 05/20/2025
Corrections:


Miscellaneous/Other
Comment Only
05/20/2025
Above ceiling and ceiling supports... approved

Framing Inspection Passed 6/4/2025 (7:00 - 8:00) 6/4/2025 (AM) 06/04/2025
Corrections:


Miscellaneous/Other
Comment Only
06/04/2025
Wall section framing approved

Progress Inspection Passed 7/22/2025 (12:30 - 2:30) 7/22/2025 (PM) 07/22/2025
Corrections:


Miscellaneous/Other
Comment Only
07/22/2025
Went over the buildout and time line for possible turnover use of these restrooms by Aug 1st. There are pieces that are on back order and wont be in by that date, trades inspections are set up for the week of possible turnover. Contractor to set up inspection for building inspector about mid week and we can revisit the potential of turnover use for the upcoming event.

Building Final Inspection Partial Pass 7/31/2025 (7:00 - 8:00) 7/31/2025 (AM) 07/31/2025
Corrections:


Miscellaneous/Other
Comment Only
07/31/2025
Bathrooms are built to the approved plans. What remains to be completd is the glass panels to be installed when they come in. Bathrooms are approved to open for public use. Call cor final inspection when all glazing is in and completed.

Fire Inspection Final Passed 7/31/2025 (8:00 - 10:00) 7/31/2025 (AM) 07/31/2025