| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Framing Inspection | Partial Pass | 2/11/2025 (8:00 - 10:00) | 2/11/2025 (AM) | 02/12/2025 |
| Need to install accessible restroom for existing space. | ||||
| Above Ceiling Inspection | Partial Pass | 2/11/2025 (8:00 - 10:00) | 2/11/2025 (AM) | 02/12/2025 |
| Provide city of Bloomington, environmental health permits, for adding new cooler. | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
02/12/2025
A. Provide all required city additional permits, for adding new cooler.
B. Existing restrooms located in grocery store.
|
||||
| Progress Inspection | Passed | 2/28/2025 (12:30 - 2:30) | 2/28/2025 (PM) | 02/28/2025 |
| Above ceiling inspection | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
02/28/2025
Progress inspection approved. Call for final when ready.
|
||||
| Building Final Inspection | Passed w/ Conditions | 4/4/2025 (10:00 - 12:00) | 4/4/2025 (AM) | 04/04/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
04/04/2025
Installation approved, this is a conditional final that is pending approval of the fire inspector due to the storage of goods being up to the ceiling and impeding sprinkler coverage. Fire inspector will revisit this site to make sure this is corrected and can then close permit.
|
||||
| Fire Inspection Final | Partial Pass | 4/4/2025 (10:00 - 12:00) | 4/4/2025 (AM) | 04/10/2025 |
| Fire Inspection Final | Passed | 7/8/2025 (8:00 - 10:00) | 7/8/2025 (AM) | 07/08/2025 |