Permit Application Status

PRBD202500302


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202500302
Building
Permit(s) Issued
BLMGTN SCHOOL DIST #271
Not Required
The work that will be completed at Jefferson High School stadium consists of the demo and replacement of some fences, a new entry gate to the stadium, building a concessions stand and entry plaza, new accessible sidewalks, replace temporary bleachers with permanent bleachers and a press box. The field work will consist of replacement of the old synthetic turf with new, new lights and sound system.
01/09/2025
05/23/2025
03/28/2026

Locations

Permits

Permit Number: PRBD202500302

Building
Issued
05/23/2025
03/28/2026

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Insulation Inspection Pending
Lath Inspection Pending
Gypsum Board/Sheet Rock Inspection Pending
Erosion Control Inspection Pending
Building Final Inspection Pending 10/10/2025 (12:30 - 2:30) 10/10/2025 (PM)
Landscaping Inspection Pending 10/31/2025
Footing Inspection Passed 6/18/2025 (8:00 - 10:00) 6/18/2025 (AM) 06/18/2025
Corrections:


Miscellaneous/Other
Comment Only
06/18/2025
Strip footings with rebar as per plan for structure at Northwest corner, Johnson Avenue approved.

Framing Inspection Passed 7/21/2025 (12:30 - 2:30) 7/21/2025 (PM) 07/21/2025
Corrections:


Miscellaneous/Other
Comment Only
07/21/2025
Roof framing/ trusses and holddowns.. appoved

Framing Inspection Passed 7/31/2025 (8:00 - 10:00) 7/31/2025 (AM) 07/31/2025
Metal stud framing for Concession stand ceiling approved
Corrections:


Miscellaneous/Other
Comment Only
07/31/2025
Metal stud framing for concessions stand ceiling approved.

Footing Inspection Passed 8/1/2025 (10:00 - 12:00) 8/1/2025 (AM) 08/01/2025
Corrections:


Miscellaneous/Other
Comment Only
08/01/2025
Retaining wall footing at northeast corner of field with rebar as per plan approved. Note, submit special inspectors summary report at final inspection.

Footing Inspection Passed 8/5/2025 (8:00 - 10:00) 8/5/2025 (AM) 08/05/2025
Corrections:


Miscellaneous/Other
Comment Only
08/05/2025
Two pad footings for entry wall at northwest corner as per drawings, approved.

Progress Inspection Passed 8/6/2025 (10:00 - 12:00) 8/6/2025 (AM) 08/06/2025
Corrections:


Miscellaneous/Other
Comment Only
08/06/2025
Foundation wall/retaining wall with rebarapproved.

Footing Inspection Passed 8/7/2025 (10:00 - 12:00) 8/7/2025 (AM) 08/07/2025
Corrections:


Miscellaneous/Other
Comment Only
08/07/2025
Foundation walls for entry gate at Northwest corner approved.

Progress Inspection Passed 8/14/2025 (12:30 - 2:30) 8/14/2025 (PM) 08/14/2025
Corrections:


Miscellaneous/Other
Comment Only
08/14/2025
120 ft of poured wall, epoxy coated rebar as per design... approved

Progress Inspection Passed 9/2/2025 (2:30 - 3:30) 9/2/2025 (PM) 09/02/2025
Corrections:


Miscellaneous/Other
Comment Only
09/02/2025
Slab on grade with epoxy coated rebar as per plan design... approved

Building Final Inspection Not Ready 9/9/2025 (12:30 - 2:30) 9/9/2025 (PM) 09/09/2025
Corrections:


Miscellaneous/Other
Comment Only
09/09/2025
Went over the progress and sequencing of the project with contractor to gage what will be completed in order for a Temp occupancy of the site. Concrete will be placed and ready for all the path entry/ exits of the field and to the concession area. Remainder site area will be outlined with snow fencing to to define the areas in which work is ongoing. Accessible parking signs have been installed to the designated parking and unloading stalls. Bleacher inspection is scheduled for 9/10/25. Final inspection is not quite ready at this time, but would be ready for Temp by end of week.

Fire Inspection Final Passed 9/10/2025 (10:00 - 12:00) 9/10/2025 (AM) 09/10/2025
Owner to provide fire extinguisher inside press box and concession building.
Building Final Inspection Issue TCO 9/10/2025 (10:00 - 12:00) 9/10/2025 (AM) 09/10/2025
Corrections:


Miscellaneous/Other
Outstanding
09/10/2025
1. Need fire extinguishers as required on plan. Obtain fire inspection approval. 2. Provide protection for accessible ramp edges from parking lot to bleachers as discussed. 3. Temporary occupancy approved for use of bleachers, conditional on completion of items one and two above. Call for final when ready.

Progress Inspection Passed 09/12/2025
Corrections:


Miscellaneous/Other
Comment Only
09/12/2025
Epoxy coated rear for for sidewalk with a turned down footing on one side and tied into poured wall on the other side is as per plans... approved to place concrete.

Building Final Inspection Partial Pass 9/16/2025 (8:00 - 10:00) 9/16/2025 (AM) 09/16/2025
Corrections:


Miscellaneous/Other
Comment Only
09/16/2025
Follow up inspection for protective fencing for accessible ramp approved. Call four final when landscaping complete.

Lighting Inspection Passed 9/26/2025 09/29/2025