Permit Application Status

PRBD202500303


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202500303
Building
Finaled
BLMGTN SCHOOL DIST #271
New
Not Required
The work that will be completed at Kennedy High School stadium consists of the demo and replacement of some fences, a new entry gate to the stadium, building a concessions stand and entry plaza, new accessible sidewalks, replace existing bleachers with new bleachers and a press box. The field work will consist of replacement of the old synthetic turf with new and new lights and a sound system.
01/09/2025
05/19/2025
04/28/2026
10/30/2025

Locations

Permits

Permit Number: PRBD202500303

Building
Finaled
05/19/2025
04/28/2026

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Footing Inspection Passed 5/22/2025 (12:30 - 2:30) 5/22/2025 (PM) 05/22/2025
Corrections:


Miscellaneous/Other
Comment Only
05/22/2025
Footings for the consession stand... approved

Footing Inspection Passed 6/11/2025 (10:00 - 12:00) 6/11/2025 (AM) 06/11/2025
Corrections:


Miscellaneous/Other
Comment Only
06/11/2025
2 rows of footings for bleachers, outside roww close to track and inside row. Approved Air barrier spray applied barrier at concession building... approved

Footing Inspection Passed 6/12/2025 (7:00 - 8:00) 6/12/2025 (AM) 06/12/2025
Corrections:


Miscellaneous/Other
Comment Only
06/12/2025
Piers on the 2 lines of footings pour on 6/11( grids A & B)

Footing Inspection Passed 6/20/2025 (10:00 - 12:00) 6/20/2025 (AM) 06/20/2025
Corrections:


Miscellaneous/Other
Comment Only
06/20/2025
Footings and piers for grids C and D.... approved for concrete

Framing Inspection Passed 6/24/2025 (10:00 - 12:00) 6/24/2025 (AM) 06/24/2025
Corrections:


Miscellaneous/Other
Comment Only
06/24/2025
Roof framing for concession building approved

Insulation Inspection Passed 6/26/2025 (8:00 - 10:00) 6/26/2025 (AM) 06/26/2025
Corrections:


Miscellaneous/Other
Comment Only
06/26/2025
Slab on grad poly sealing... approved

Above Ceiling Inspection Passed 7/17/2025 (8:00 - 10:00) 7/17/2025 (AM) 07/17/2025
The framing
Corrections:


Miscellaneous/Other
Comment Only
07/17/2025
Ceiling framing.. approved

Footing Inspection Passed 8/7/2025 (8:00 - 10:00) 8/7/2025 (AM) 08/07/2025
Corrections:


Miscellaneous/Other
Comment Only
08/07/2025
Three pad footings at entry with rebar as per plan on Sandy soil approved.

Progress Inspection Passed 8/26/2025 (8:00 - 10:00) 8/26/2025 (AM) 08/26/2025
Corrections:


Miscellaneous/Other
Comment Only
08/26/2025
Concession building and bleachers are approved for code compliance. Special inspection reports are required to be sent to inspector for this project. Lighting and landscape inspections need to be set up with planning and are still outstanding. Plumbing final needed for the concession building, pending the issue for winterizing building when not in use. set up final inspection when ready, Remaining site work to be completed for full final of permit. The concession building and bleachers are approved for temp occupancy, any conditions for PPE use on site is through the contractor while work is in process.

Progress Inspection Not Ready 8/27/2025 (8:00 - 10:00) 8/27/2025 (AM) 08/27/2025
Landscaping Inspection Passed 9/19/2025 09/05/2025
Fire Inspection Final Passed 9/18/2025 (8:00 - 10:00) 9/18/2025 (AM) 09/18/2025
Building Final Inspection Passed 9/18/2025 (8:00 - 10:00) 9/18/2025 (AM) 09/18/2025
Corrections:


Miscellaneous/Other
Comment Only
09/18/2025
All work is completed and approved. Final for this permit is approved

Lighting Inspection Failed 9/29/2025 09/30/2025
Lighting Inspection Passed 10/31/2025 10/30/2025