PRBD202500303
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Footing Inspection | Passed | 5/22/2025 (12:30 - 2:30) | 5/22/2025 (PM) | 05/22/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
05/22/2025
Footings for the consession stand... approved
|
||||
| Footing Inspection | Passed | 6/11/2025 (10:00 - 12:00) | 6/11/2025 (AM) | 06/11/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/11/2025
2 rows of footings for bleachers, outside roww close to track and inside row. Approved
Air barrier spray applied barrier at concession building... approved
|
||||
| Footing Inspection | Passed | 6/12/2025 (7:00 - 8:00) | 6/12/2025 (AM) | 06/12/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/12/2025
Piers on the 2 lines of footings pour on 6/11( grids A & B)
|
||||
| Footing Inspection | Passed | 6/20/2025 (10:00 - 12:00) | 6/20/2025 (AM) | 06/20/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/20/2025
Footings and piers for grids C and D.... approved for concrete
|
||||
| Framing Inspection | Passed | 6/24/2025 (10:00 - 12:00) | 6/24/2025 (AM) | 06/24/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/24/2025
Roof framing for concession building approved
|
||||
| Insulation Inspection | Passed | 6/26/2025 (8:00 - 10:00) | 6/26/2025 (AM) | 06/26/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
06/26/2025
Slab on grad poly sealing... approved
|
||||
| Above Ceiling Inspection | Passed | 7/17/2025 (8:00 - 10:00) | 7/17/2025 (AM) | 07/17/2025 |
| The framing | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
07/17/2025
Ceiling framing.. approved
|
||||
| Footing Inspection | Passed | 8/7/2025 (8:00 - 10:00) | 8/7/2025 (AM) | 08/07/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/07/2025
Three pad footings at entry with rebar as per plan on Sandy soil approved.
|
||||
| Progress Inspection | Passed | 8/26/2025 (8:00 - 10:00) | 8/26/2025 (AM) | 08/26/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/26/2025
Concession building and bleachers are approved for code compliance.
Special inspection reports are required to be sent to inspector for this project.
Lighting and landscape inspections need to be set up with planning and are still outstanding.
Plumbing final needed for the concession building, pending the issue for winterizing building when not in use. set up final inspection when ready,
Remaining site work to be completed for full final of permit.
The concession building and bleachers are approved for temp occupancy, any conditions for PPE use on site is through the contractor while work is in process.
|
||||
| Progress Inspection | Not Ready | 8/27/2025 (8:00 - 10:00) | 8/27/2025 (AM) | 08/27/2025 |
| Landscaping Inspection | Passed | 9/19/2025 | 09/05/2025 | |
| Fire Inspection Final | Passed | 9/18/2025 (8:00 - 10:00) | 9/18/2025 (AM) | 09/18/2025 |
| Building Final Inspection | Passed | 9/18/2025 (8:00 - 10:00) | 9/18/2025 (AM) | 09/18/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
09/18/2025
All work is completed and approved. Final for this permit is approved
|
||||
| Lighting Inspection | Failed | 9/29/2025 | 09/30/2025 | |
| Lighting Inspection | Passed | 10/31/2025 | 10/30/2025 | |