Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Framing Inspection | Passed | 3/19/2025 (12:30 - 2:30) | 3/19/2025 (PM) | 03/19/2025 |
Corrections:
Miscellaneous/Other
Comment Only
03/19/2025
Framing of wall and bumpouts... approved
|
||||
Building Final Inspection | Not Ready | 5/9/2025 (8:00 - 10:00) | 5/9/2025 (AM) | 05/09/2025 |
Corrections:
Miscellaneous/Other
Comment Only
05/09/2025
Approved to stock in the stockroom only.
No stock in sales area at this time, overhead work must finish up first.
|
||||
Building Final Inspection | Partial Pass | 5/14/2025 (8:00 - 10:00) | 5/14/2025 (AM) | 05/14/2025 |
Corrections:
Miscellaneous/Other
Comment Only
05/14/2025
Approved to stock in sales area as well as stockroom.
Call for final when all is completed and ready for inspection.
|
||||
Fire Inspection Final | Partial Pass | 5/14/2025 (8:00 - 10:00) | 5/14/2025 (AM) | 05/15/2025 |
Building Final Inspection | Passed w/ Conditions | 5/22/2025 (8:00 - 10:00) | 5/22/2025 (AM) | 05/22/2025 |
Corrections:
Miscellaneous/Other
Comment Only
05/22/2025
Approved for final, pending the installation of the fitting room accessible signage.
|
||||
Fire Inspection Final | Passed | 5/22/2025 (8:00 - 10:00) | 5/22/2025 (AM) | 05/22/2025 |