PRBD202505317
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Framing Inspection | Passed | 7/30/2025 (10:00 - 12:00) | 7/30/2025 (AM) | 07/30/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
07/30/2025
Framing and fire stops to all back of house... approved
|
||||
| Framing Inspection | Passed w/ Conditions | 08/14/2025 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
08/14/2025
Sales area and storefront framing approved, pending fire inspection and any electrical inspection that may need to be done prior to covering. Note.... beam at storefront to be patched in with fireproofing, will need to verify at next inspection
|
||||
| Framing Inspection | Passed | 8/15/2025 (8:00 - 10:00) | 8/15/2025 (AM) | 08/15/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/15/2025
Not ready for inspection
|
||||
| Fire Inspection Final | Partial Pass | 10/3/2025 (7:00 - 8:00) | 10/3/2025 (AM) | 10/03/2025 |
| TCO - approved to stock | ||||
| Progress Inspection | Passed | 10/03/2025 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
10/03/2025
Today's inspection is a progress inspection to allow the business to stock the sales are and the storeroom.
This cannot be a TCO due to additional testing of smoke evac system to be performed and the open trades permits that still need final inspections.
Approved for stock and store setup only in the storeroom and sales areas.
|
||||
| Building Final Inspection | Not Ready | 10/3/2025 (8:00 - 10:00) | 10/3/2025 (AM) | 10/03/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
10/03/2025
Not ready for final inspection. Went through space and gave corrections to contractor to items that need to be completed. The city will allow stock and setup of this space, see to Progress inspection dated 10/3/25.
|
||||
| Fire Inspection Final | Partial Pass | 10/8/2025 (8:00 - 10:00) | 10/8/2025 (AM) | 10/09/2025 |
| Smoke control test | ||||
| Fire Inspection Final | Passed | 10/13/2025 (12:30 - 2:30) | 10/13/2025 (PM) | 10/13/2025 |
| Building Final Inspection | Issue TCO | 10/13/2025 (12:30 - 2:30) | 10/13/2025 (PM) | 10/13/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
10/13/2025
Back storage room is not being taken over by the mall, it will be for the tennant to use.... the columns need to have protection around them per the malls requirement at 8ft tall. (Code does require protection, but not at the 8 ft height. )
Contractor to send photos of this when completed.
|
||||
|
Miscellaneous/Other
Comment Only
10/13/2025
All other corrections given to contractor have been completed, see outstanding comment for final correction.
This space is approved for Temporary Occupancy pending completion within 30 days of this date.
|
||||
| Building Final Inspection | Issue CO | 10/14/2025 | ||
|
Corrections:
Miscellaneous/Other
Comment Only
10/14/2025
Column protection has been installed, all work and inspections completed. Final for this permit approved, ok to issue Certificate of Occupancy
|
||||