PRBD202505901
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Progress Inspection | Passed | 8/6/2025 (8:00 - 10:00) | 8/6/2025 (AM) | 08/06/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/06/2025
The added mall smoke bulkhead , framing and sealing to this space is approved.
Wall framing of what is currently in place approved.
Call for electrical and sprinkler inspections or the ceiling, building above ceiling inspection to be performed when the trades inspections are approved.
|
||||
| Framing Inspection | Passed w/ Conditions | 8/19/2025 (8:00 - 10:00) | 8/19/2025 (AM) | 08/19/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
08/19/2025
Walls and above ceiling and ceiling framing.... approved
See outstanding comments for correction.
|
||||
|
Miscellaneous/Other
Outstanding
08/19/2025
2 floor drains and one 2" drain piping to be fire stopped... pictures to verify to be sent to inspector, or set up separate inspection and have access to space below.
|
||||
| Building Final Inspection | Not Ready | 10/30/2025 (12:30 - 2:30) | 10/30/2025 (PM) | 10/30/2025 |
| SAME DAY CANCEL | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
10/30/2025
Inspection canceled by contractor
|
||||
| Above Ceiling Inspection | Passed | 10/30/2025 (12:30 - 2:30) | 10/30/2025 (PM) | 10/30/2025 |
| SAME DAY INSPECTION-CANCEL | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
10/30/2025
The above ceiling inspection was already viewed at time of mechanical and framing inspection.
|
||||
| Fire Inspection Final | Not Ready | 10/30/2025 (12:30 - 2:30) | 10/30/2025 (PM) | 11/03/2025 |
| CANCELED-Same Day | ||||
| Building Final Inspection | Partial Pass | 11/4/2025 (10:00 - 12:00) | 11/4/2025 (AM) | 11/04/2025 |
|
Corrections:
Miscellaneous/Other
Carried Forward
11/04/2025
Corrections for final....
1) complete storefront finishes at wall to ceiling and floor base as shown onplans.
2) install fire extinguisher to hang on wall at back of space
3) adjust rear door to properly close and latch.
4) provide " No storage " stencil an wall in front of electrical panel and transformer.
|
||||
|
Miscellaneous/Other
Comment Only
11/04/2025
Approved for temp CO to get setup and get completed for the final. Electrical final scheduled for today, all permits to be final for C of O.
|
||||
| Fire Inspection Final | Passed | 11/4/2025 (10:00 - 12:00) | 11/4/2025 (AM) | 11/06/2025 |
| Building Final Inspection | Passed | 11/7/2025 (12:30 - 2:30) | 11/7/2025 (PM) | 11/06/2025 |
|
Corrections:
Miscellaneous/Other
Resolved
11/06/2025
Corrections for final....
1) complete storefront finishes at wall to ceiling and floor base as shown onplans.
2) install fire extinguisher to hang on wall at back of space
3) adjust rear door to properly close and latch.
4) provide " No storage " stencil an wall in front of electrical panel and transformer.
|
||||
|
Miscellaneous/Other
Comment Only
11/06/2025
Corrections completed, final for this permit approved
|
||||