PRBD202507095
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Framing Inspection | Passed | 8/18/2025 (8:00 - 10:00) | 8/18/2025 (AM) | 08/18/2025 |
|
Corrections:
Miscellaneous/Other
Outstanding
08/18/2025
Remove old gypsum from wall behind where new hood is to be placed and replace with cement board.
|
||||
|
Miscellaneous/Other
Comment Only
08/18/2025
Framing approved. See outstanding comments for correction are hood wall covering.
|
||||
| Building Final Inspection | Passed | 11/6/2025 (12:30 - 2:30) | 11/6/2025 (PM) | 11/06/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
11/06/2025
All corrections completed and approved, ok to open to public, and final for this permit approved.
|
||||
| Fire Inspection Final | Passed | 11/6/2025 (12:30 - 2:30) | 11/6/2025 (PM) | 11/10/2025 |