PRBD202507492
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Above Ceiling Inspection | Pending | |||
Fire Inspection Final | Pending | |||
Building Final Inspection | Pending | |||
Framing Inspection | Passed | 8/12/2025 (10:00 - 12:00) | 8/12/2025 (AM) | 08/12/2025 |
Corrections:
Miscellaneous/Other
Comment Only
08/12/2025
Approved to install the cement bord on the wall behind hood.
Framing is not yet completed and to be inspected when ready.
|
||||
Progress Inspection | Passed | 8/15/2025 (10:00 - 12:00) | 8/15/2025 (AM) | 08/15/2025 |
Floor inspection | ||||
Corrections:
Miscellaneous/Other
Comment Only
08/15/2025
Floor holes being patched with concrete... approved
|
||||
Framing Inspection | Passed | 9/4/2025 (8:00 - 10:00) | 9/4/2025 (AM) | 09/04/2025 |
Corrections:
Miscellaneous/Other
Comment Only
09/04/2025
Small soffits in back hall, and partial framing of storefront approved.
Ok to cover the small soffits and sides of the storefront soffit.
|