Permit Application Status

PRBD202507693


You will only be able to view fees or view conditions if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRBD202507693
Building
Finaled
MOAC MALL HOLDINGS LLC
Alteration/Repair/Replace
Mercantile
Full Remodel Scope: New finishes on existing storefront construction New wall and floor fixtures in sales area New finishes in sales area: floor tile, paint, ACT ceiling tile New light fixtures No new wall construction Refurbish existing toilet room Electrical scope: circuiting for new floor fixtures, circuiting for new light fixtures. No HVAC work Minor plumbing work: Installation of new hot water tank, mop sink & drinking fountains
07/02/2025
08/13/2025
05/04/2026
11/05/2025

Locations

Permits

Permit Number: PRBD202507693

Building
Finaled
08/13/2025
05/04/2026

Deposits & Bonds

There are no deposits or bonds for this permit application.

Inspections

Inspection Outcome Requested Scheduled Date Complete
Framing Inspection Passed 10/16/2025
Corrections:


Miscellaneous/Other
Comment Only
10/16/2025
Framing viewed at a previous site visit inspection and approved

Progress Inspection Passed w/ Conditions 10/16/2025 (10:00 - 12:00) 10/16/2025 (AM) 10/16/2025
Corrections:


Miscellaneous/Other
Comment Only
10/16/2025
Bulkhead at storefront... approved pending the sealing at penetrations.

Above Ceiling Inspection Passed 10/23/2025 (12:30 - 2:30) 10/23/2025 (PM) 10/23/2025
Corrections:


Miscellaneous/Other
Comment Only
10/23/2025
Above ceiling and ceiling framing approved

Building Final Inspection Partial Pass 11/4/2025 (10:00 - 12:00) 11/4/2025 (AM) 11/04/2025
Corrections:


Miscellaneous/Other
Carried Forward
11/04/2025
Corrections.... 1) install kick plate at inner exit door to highlight door and smoke seal at exit door. 2) install fire extinguisher as per fire inspection.

Miscellaneous/Other
Comment Only
11/04/2025
Approved for temp to stock and set up space.

Fire Inspection Final Passed 11/4/2025 (10:00 - 12:00) 11/4/2025 (AM) 11/05/2025
Building Final Inspection Passed 11/05/2025
Corrections:


Miscellaneous/Other
Resolved
11/05/2025
Corrections.... 1) install kick plate at inner exit door to highlight door and smoke seal at exit door. 2) install fire extinguisher as per fire inspection.

Miscellaneous/Other
Comment Only
11/05/2025
Corrections completed, final for this scope of work and permit approved