PRBD202508000
There are no deposits or bonds for this permit application.
Inspection | Outcome | Requested | Scheduled | Date Complete |
---|---|---|---|---|
Fire Inspection Final | Pending | |||
Building Final Inspection | Pending | |||
Framing Inspection | Passed | 9/15/2025 (8:00 - 10:00) | 9/15/2025 (AM) | 09/15/2025 |
Corrections:
Miscellaneous/Other
Comment Only
09/15/2025
Interior Wall framing approved
|
||||
Above Ceiling Inspection | Passed | 9/26/2025 (10:00 - 12:00) | 9/26/2025 (AM) | 09/26/2025 |
Corrections:
Miscellaneous/Other
Comment Only
09/26/2025
Hard lid ceiling install, and above ceiling... approved and ok to cover.
|