PRBD202512105
There are no deposits or bonds for this permit application.
| Inspection | Outcome | Requested | Scheduled | Date Complete |
|---|---|---|---|---|
| Fire Inspection Final | Pending | |||
| Building Final Inspection | Pending | |||
| Fire Rough-in Inspection | Pending | |||
| Progress Inspection | Pending | |||
| Above Ceiling Inspection | Pending | 4/8/2026 (8:00 - 10:00) | 4/8/2026 (AM) | |
| Progress Inspection | Passed | 12/22/2025 (7:00 - 8:00) | 12/22/2025 (AM) | 12/22/2025 |
|
Corrections:
Miscellaneous/Other
Comment Only
12/22/2025
This was a consultation inspection with contractor, wanted to meet Inspector and go over for inspections and requirements for this mall project.
|
||||
| Fire Rough-in Inspection | Not Ready | 12/22/2025 (7:00 - 8:00) | 12/22/2025 (AM) | 12/23/2025 |
| Framing Inspection | Passed | 1/13/2026 (8:00 - 10:00) | 1/13/2026 (AM) | 01/13/2026 |
| Exterior Facade framing- approved | ||||
|
Corrections:
Miscellaneous/Other
Comment Only
01/13/2026
Exterior Facade framing- approved
|
||||
| Framing Inspection | Passed | 2/11/2026 (8:00 - 10:00) | 2/11/2026 (AM) | 02/11/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/11/2026
Framing in back of house lower lovel, and cleaner/ compound area... approved
|
||||
| Framing Inspection | Passed | 2/17/2026 (10:00 - 12:00) | 2/17/2026 (AM) | 02/17/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
02/17/2026
Framing at exterior facade... approved
|
||||
| Progress Inspection | Passed | 3/3/2026 (8:00 - 10:00) | 3/3/2026 (AM) | 03/03/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/03/2026
Structural steel installed for the floor infill...Special inspection to provide reports to inspector for bolting and fireproofing.
|
||||
| Progress Inspection | Passed | 3/4/2026 (12:30 - 2:30) | 3/4/2026 (PM) | 03/04/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/04/2026
Floor infill around the escalator in this space of 2nd floor... dowels have been epoxied in place and viewed by 3rd party inspection, wire mesh is in place and ready for concrete.... approved
|
||||
| Footing Inspection | Passed | 3/12/2026 (10:00 - 12:00) | 3/12/2026 (PM) | 03/12/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/12/2026
Elevator pad rebar... double mat #6 bars each way 12" oc at both mats. Wall rebar in place and as per design.
Scissor lift pad .... rebar #4 each way 12" oc. Both mats.
Approved to place concrete.
|
||||
| Progress Inspection | Not Ready | 3/16/2026 (8:00 - 10:00) | 3/16/2026 (AM) | 03/16/2026 |
|
Corrections:
Miscellaneous/Other
Comment Only
03/16/2026
Sump pit.... water in pit at this time, no rebar placed. Contis trying to dewater, and will probably raise the slab height of pit do to the water table height.
Contractor can reschedule inspection if they will not have approval to raise slab, or send photos of bar in place if concrete to still be placed today. Terracon inspection is the third party and will also verify rebar .
|
||||